General
9. Plan No. 2 shows, with other information, the face and inbye sections of the ventilating roads of No. 2 District. No. 2 face, 155 yards long, was nearly 1½ miles from the pit bottom and was advancing southwards, in the solid, on a rising gradient of 1 in 6.25 with a very slight rise from the intake gate to the return gate. Started in September, 1960, the face had advanced 765 yards at a rate of about 10 yards per week. No. 5 face, advancing in the same direction, was 400 yards behind and 33 yards to the east of No. 2 face.
10. After infusion by water, the face was cut about 1 foot above floor level by an electrically driven machine mounted on an armoured flexible conveyor. Until 3rd February, 1962, the depth of cut was 6 feet 6 inches, but on that day the jib was changed and the depth of cut increased to 7 feet 6 inches. Coal in the stables was cut at floor level by shortwall machines. After cutting, all the coal was won by an Eq.S. explosive and compressed air picks. The same type of explosive was used in taking down the gate rippings which were kept well up to the face. The normal cycle of face operations was as follows
| | (a) |
Afternoon shift: advance the face conveyor; drill shotholes in the face; withdraw supports from the waste; drill and cut the stables; rip the intake gate;
|
| | (b) |
Night shift: rip the return gate; cut the face line; commence filling; and
|
| | (c) |
Day shift: complete filling.
|
I refer later to shotfiring procedure in relation to these operations.
11. The roof at the face was supported by friction type yielding props set to corrugated steel bars 8 feet long. Additional friction props were set as breakers at the edge of the waste which was completely caved between the 6 yards wide intake gate pack and the 8 yards wide return gate pack. The intake gate, 14 feet wide and 10 feet high, and the return gate, 10 feet wide and 8 feet high, were supported by arched steel girders which were stilted and backed with fire-resistant wood boards.
12. Coal from the face conveyor was transferred to a belt conveyor in the intake gate, the first stage of a trunk belt conveyor system to the shaft bottom. Some supplies reached the face by the surface drift and the intake gate, using the tub track provided in that gate. Other supplies came down No. 3 shaft and along the main intake airway in tubs to the Cut-back. There the tubs passed through separation doors into the main return airway, where they were taken by an endless rope haulage to a point in the return some 300 yards outbye of the face ripping; the tubs were then hauled inbye by an electrically driven direct rope engine situated near the face ripping.
Ventilation
13. Statutory records show that for some months before the explosion the quantity of air, as measured at a point in the intake gate 10 yards outbye from the face, was slightly in excess of 20,000 cubic feet per minute. The records also show that during the three months before the explosion the firedamp content of samples of air collected at a point in the return gate 10 yards from the face varied between 0.4 and 0.7 per cent., but occasionally it was outside these limits.
14. Firedamp was drained by holes, 120 feet long, bored from the return gate into the shale above the waste, at intervals of 35 yards. The holes were connected to a pipe range 6 inches in diameter, which was increased to 8 inches in the main return to the bottom of No. 2 shaft, and to 12 inches in the shaft. The firedamp was drawn from the boreholes and discharged to atmosphere by an exhauster situated on the surface. The quantity of gas drained averaged over 100 cubic feet per minute, which represented about 55 per cent. of the make of firedamp on the face.
Shotfiring
15. The practice was to fire shots in the intake gate stable, and also in some of the top coal on the face, during the night shift to facilitate the start of filling operations. The return gate stable was fired either at the end of the night shift or at the commencement of the day shift, according to how work had progressed. The remainder of the top coal followed by the bottom coal was fired during the day shift. The intake gate ripping was fired on the afternoon shift and the return gate ripping on the night shift. In addition to the deputies, who were not authorised to fire more than ten shots per shift, there were shotfirers available on the day and night shifts and they each carried 40 detonators. In order to ensure that all demands for shotfiring were met, some of the shotfirers' shifts were "staggered" with the main working shifts. As a result, there were frequently three shotfirers available at the beginning of the day shift.
Precautions against coal dust
16. The volatile content of the coal was 32 per cent., but the management had not formally declared this figure to H.M. Inspectors, and were thus required by law to ensure that a minimum of 75 per cent, incombustible material was always present on the roof, sides and floor of the roadways. At the last statutory sampling before the explosion, the incombustible content of most of the road dust samples was well in excess of the minimum required; the lowest recorded was 76.2 per cent.
17. A Polish type stone dust barrier consisting of 17 heavy shelves and 8 light shelves, covering about 50 yards of roadway, was sited in the intake gate about 300 yards from the ripping. One hundred yards farther inbye there was a similar barrier composed of 12 light shelves.
Automatic firedamp detectors
18. Automatic firedamp alarms were not in use at the time of the explosion, a matter to which I will refer later.
General experience
19. With the exception of the ignition in the undercut, to which I have referred earlier, the working of the district appears to have progressed without any untoward incident. The general impression created by witnesses was that the ventilation of the district had always been good, and that men working on the face were obliged to wear coats or woollen garments to keep warm. There were no reports of firedamp having been detected other than occasionally in the return gate stable.