Museum Entrance Museum
Museum
Friends of Durham Mining Museum
Events Calendar
e-Books and Books for sale
Photograph Gallery
Document Archive
Main Document Archive
Newspaper Articles
Local Record Extracts
D.M.A. Document Archive
Transactions of I.M.E.
Miners' Welfare
N.C.B. Archive
The Colliery Engineer
The Colliery Guardian
Mine & Quarry Engineering
Mine & Quarry Engineering - Main Index
Mine & Quarry Engineering - Subject Index
Mining Journal
The Science and Art of Mining
Coal Magazine
Coal News
Coke and Gas
Master Name Index
What's new in the site
Mining
Mining History
Colliery Index
Colliery Maps
Company Overviews
Who's Who
Mineral Information
Managers Certificates
Educational Material
Bibliography
Statistics
Workers/Employee Lists
Notes for Family Historians
War Service information
Disasters
Disaster Reports
Names of those killed
Disasters in the 1700s
Disasters in the 1800s
Disasters in the 1900s
Memorials
Awards for Gallantry
On this day ...

Links to other sites of interest
Industrial Heritage Days Out
Former www.pitwork.net web site

Index to site

Contact and address details

Share Page with Social Media

Share on Facebook

Share with Reddit

Share on Delicious

Title Prev Page Return to Index Next Page Title
 
 Mine & Quarry Engineering August, 1959 

Springing method

Although heading blasting was first introduced during 1937, the rock was mainly won prior to 1950 by means of a shothole springing technique. The method at Shap was to drill four boreholes from the top of the quarry to a depth of 30 ft., and to a 30 ft. square pattern as regards spacing and burden; however, the position of joints and fissures was naturally taken into consideration. Eight pounds of blasting powder was then placed in each hole, occupying about 2 ft. of the hole, and the remainder filled with dry sand. The four charges were then fired instantaneously using electric detonators. This first spring would have little or no visible effect, and the boreholes were then cleared of sand using a blast of compressed air, this also serving to cool the hole.

This procedure was repeated with increasing amounts of powder — 12 lb. of powder was used in the second springing — until a crack 3-4 in. wide was visible on the surface, usually running along the line of boreholes. This crack generally appeared after the fourth or fifth springing and when it became visible no further sand stemming was used ; the blasting powder was run into the boreholes and found its way into the cracks on either side. The charge was then fired, using only one detonator, the high temperature flame of the initiated portion igniting the powder in both the holes and the cracks.

The total amount of powder used in the penultimate spring was about 100 lb., and the amount in the last springing was up to 200 lb. This whole operation, if weather conditions allowed, occupied up to three weeks, in which as many as nine springings might have been made. However, the results obtained were dependent directly on the skill of the shotfirer and the decision to cease springing and make the final blast was made by an experienced quarryman after observing the face carefully during the later stages of springing.

For this final blast, seven times the amount of powder used in the last springing was used; for example, if the amount of powder used in the last springing had been 180 lb., the final blast would be loaded with 1,260 b. This would bring down a rock tonnage of up to 30,000 tons, with individual blocks of stone up to 1,000 tons in weight.

A total amount of 1,800 to 2,000 lb. of explosive was used in the whole operation, giving a yield ratio of 13-17 tons per pound of blasting powder. The operation was, however, somewhat dependent upon the weather, and delays of several weeks or even months were quite common; for this and other reasons the practice was abandoned in favour of beading blasts.

Large blocks unsuitable for masoning were broken by the quarrymen, using I.C.I. Sabulite in 1¼ in. shotholes which were drilled with jackhammers. About 12-15 such rocks were treated every week. This secondary breaking was performed by a team of 18 men, using approximately 3,000 detonators monthly.

However, no secondary blasting is now undertaken in the quarry, rock unsuitable for masonry work being broken into uniform fragments suitable for crushing by means of a drop-hammer weighing approximately 6,000 lb. This drop-hammer — referred to in the quarry as a "tup" — is fitted with a base of chrome-steel. It is raised to a height of 35-40 ft. on the jib of a Ruston-Bucyrus 38-RB, and dropped onto the rock required to be broken. Large blocks are thus shattered swiftly, easily and economically. The 38-RB excavator is driven by a six-cylinder diesel engine developing 132 b.h.p. at 1,000 r.p.m., and has ample power for this duty, the jib being maintained at 45 deg. Fragments are occasionally thrown a short distance, but the operator is adequately protected and no other persons are in the immediate vicinity.

When this drop-ball technique was introduced at the quarry, a certain amount of difficulty was encountered in attaching the drop-hammer to the wire rope of the 38-RB, chains of all sizes being prone to breakage. The problem was overcome by using a 3 ft. length of discarded excavator rope which was passed through a hole drilled in a 4½ in. diameter by 1 in. thick steel plate and knotted. Two U-shaped pieces of 1 in. diameter steel rod, welded together, were then welded to the perimeter of the steel plate and enclosing the lifting ring of the drop-hammer.

A similar arrangement was then made at the other end of the short length of rope, the U-pieces passing through an eye on the rope of the 38-RB. Although simple, this method has proved particularly effective, and breakages are confined to the easily replaceable length of discarded rope.

The output of this drop-hammer is sufficient to keep the face shovel supplied with material. However, any large boulders positioned dangerously on the quarry face and out of reach of the drop-hammer are normally brought down with a small charge of gelignite fired by means of Cordtex.

Masoning stone

Large blocks suitable for masoning are split by a process known as reaming and a block split in this manner is shown in Fig. 10. A 1½ in. diameter hole is first drilled into the centre of the block, its position governed by the size of finished stone required. Then a tool termed a reamer is inserted in the hole, cutting two deep triangular grooves on opposite sides of the hole; the intended direction of fracture is along a line drawn through the apices of the triangles. While drilling, the reamer does not, of course, revolve in the hole.

Dependent on the required dimensions of the block to be split, up to 3 lb. of blasting powder may be placed in the hole, stemmed with dry sand and fired electrically. This results in a clean fracture as shown in Fig. 10, with no fragments being thrown by the blast.

Rough blocks cut in this manner are hauled across the quarry floor by means of a Henderson derrick crane which has a jib 110 ft. long and which is powered by a 45 h.p., 700 r.p.m. motor, In the quarry there are two such cranes, each capable of lifting a maximum load of 10 tons; they are located so that all parts of the working face are within reach. The rough blocks are dragged to the immediate vicinity of the derrick where they are further split into the sizes required by the masonry department.

Splitting is effected by plug and feather, along a line of holes drilled 6 in. deep and 9 in. apart. After this preliminary dressing, typical results of which are depicted in Fig. 11, the blocks are approximately cubical in shape. They are loaded onto lorries and transported by road to the main works, where they are off-loaded by an overhead travelling crane made by Herbert Morris Limited. This unit, of 10 tons capacity, carries the blocks to the bays where they are shaped and trimmed by skilled masons using air-powered tools.

After trimming, the blocks to be made into slabs are sawn by a gang saw, manufactured by Anderson Grice Co. Ltd., of Carnoustie. It can be used with from one to six adjustable blades, and is powered by a 20 h.p. motor at 480 r.p.m., giving 90 strokes per minute. The blades of the gang saw are of mild steel plate, and are fed with 3/8 in. diameter hardened steel balls and sand.

On completion of the sawing, the slabs are cut to the desired shape by a Hydro-Carbo diamond-tipped circular saw blade made by Alexander Wilson (Aberdeen) Limited. This blade is fixed directly to a 10 h.p., 975 r.p.m. motor with an extended nose; the sawing operation is hydraulically controlled.

Polishing is done with machines supplied by George Cassie and Son Limited of Aberdeen. Three polishers are used, one of them a small mobile model mounted on a tripod. The other two are powered by 7½ h.p. motors and may be operated at one of two speeds dependent on the surface of the granite. A speed of 720 r.p.m. is used for the preliminary stages, while a speed of 1,420 r.p.m. is employed for the final work.

Several slabs are set up on the polishing bed at one time, and the rotary polishing head is directed manually over the whole surface. The grinding media are fed to the head, shot being used in the initial stages while the final polish is imparted with a glossing pad. About two days are spent on the complete operation.

Loading and transport

Prior to 1950 stone for the crushing plant was broken and loaded entirely by hand into special tipping wagons which were hauled by steam locomotive along a broad gauge railway to the main works. A team of 18 rock-breakers was employed for this purpose. Masoning stone was loaded by mobile steam crane and transported in a similar manner. During 1950, however, the decision to modernise the quarry was made, and a Broadbent 42 in. by 36 in. primary crusher was installed. As a result this labour force was diverted to other jobs, although the crushed rock was still transported by rail to the secondary crushing plant at the main works.

Two secondary crushers, together with screening plant, were installed in the quarry during 1953, resulting in the closure of the railway, and the quarry becoming self-contained.

The rock now broken by the drop-hammer is loaded by a 33-RB excavator powered by a five-cylinder diesel engine, developing 110 h.p. at 1,000 r.p.m. This machine is fitted with a 1½ cu. yd. face shovel attachment and loads the rock into a 4½ cu. yd. Aveling-Barford dumper which is powered by a 55 h.p. diesel engine. This vehicle is used to carry the material 200-600 ft. to the reception chute.

(To be concluded)

Drawings and Photographs accompanying the article

 

Prev Page Return to Top of Page Next Page

Article reproduced from a copy of the magazine held at National Mining Museum Scotland, Newtongrange, Midlothian.

 

mail
Mail:
Webmaster
Back
Back
Home
Home
Open Government Licence   Contains public sector information licensed under the Open Government Licence v3.0.

Copyright © 1999-2024 by The Durham Mining Museum and its contributors
Registered Charity No: 1110608
Page last updated: 17 Jan 2023

Privacy Policy
 
Terms & Conditions
 
Search
Search
Print
Print