Museum Entrance Museum
Museum
Friends of Durham Mining Museum
Events Calendar
e-Books and Books for sale
Photograph Gallery
Document Archive
Main Document Archive
Newspaper Articles
Local Record Extracts
D.M.A. Document Archive
Transactions of I.M.E.
Miners' Welfare
N.C.B. Archive
The Colliery Engineer
The Colliery Guardian
Mine & Quarry Engineering
Mine & Quarry Engineering - Main Index
Mine & Quarry Engineering - Subject Index
Mining Journal
The Science and Art of Mining
Coal Magazine
Coal News
Coke and Gas
Master Name Index
What's new in the site
Mining
Mining History
Colliery Index
Colliery Maps
Company Overviews
Who's Who
Mineral Information
Managers Certificates
Educational Material
Bibliography
Statistics
Workers/Employee Lists
Notes for Family Historians
War Service information
Disasters
Disaster Reports
Names of those killed
Disasters in the 1700s
Disasters in the 1800s
Disasters in the 1900s
Memorials
Awards for Gallantry
On this day ...

Links to other sites of interest
Industrial Heritage Days Out
Former www.pitwork.net web site

Index to site

Contact and address details

Share Page with Social Media

Share on Facebook

Share with Reddit

Share on Delicious

Title Prev Page Return to Index Next Page Title
 
 Mine & Quarry Engineering February, 1954 

Electrical

Fig. 39 shows the arrangement of the electrical supply to underground. Power at 3,300 volts is taken underground via No. 1 shaft, and to the panels and to development headings where it is transformed at 150 kVA mobile sub-stations to 425 volts. Each of these sub-stations serves three Reyrolle twin gate-end switches which are mounted on skids to enable them to be kept up to the working faces. Thus these G.E. switches are always maintained within a maximum distance of 200 yards from the face machinery, although the distance is normally limited to one 100 yard trailing cable. Three G.E. switches per transformer with up to 200 yards of 0.04 sq. in. trailing cable, are considered to be a maximum due to the voltage drop (up to 12 per cent.) from the face load.

Electricars made by Austin, Crompton Parkinson Limited, Birmingham, and Smith's Electric Vehicles Limited, Gateshead, are used underground for transporting personnel, see Fig. 40. and adapted for carrying explosives and for the survey crew. All electric motors noted in use at Billingham were of Mather and Platt manufacture, with starters supplied by Allen West and Co. Ltd., Brighton.

An underground telephone system employing Siemens equipment is installed with approximately 50 extensions enabling close contact to be maintained with all parts of the mine and surface.

Surveying

On the mine staff is a chief surveyor and two qualified assistants, who are responsible for the routine surveying work underground. Among these duties in, the new type mining areas comes the task of marking tip each drill hole in a face prior to bringing in the drilling carriage. The surveyors use an Electricar adapted specially for this purpose, although it is also used for their transportation around the 200 miles of roads that at present exist at Billingham. Mounted on this vehicle is a projector, which projects a spot of light on to the face according to the predetermined standard drilling pattern. A paint gun operated by oxygen under pressure marks the face in the circles of light. Fig. 41 shows this vehicle in use at a face. By this means, a considerable saving in surveyor's time is effected, while ensuring that drill holes are placed accurately for every face blast.

A sampler is employed underground on day shift, and he normally visits all working faces in rotation. Samples taken underground are either from drill cuttings, by a groove sample cut from floor to roof, or more recently by a minute pistol grip drill, compressed air operated, that collects drillings into a container in a few seconds. Samples are assayed for SiO2, CaSO4, and NaCl. A daily output grade is returned from grab samples taken in the process plant, and, should these values appear erratic, investigations are immediately made underground to locate the cause.

Compressed air

Air for the pneumatic drills is supplied through 1-in, hose and line oilers connected up to Saunders Streamline rubber-diaphragm valves, which are in general use underground and are giving satisfactory service. Three-inch pipelines connect up to the 6-in. lines in the rise and dip haulages, and air is brought down the skip shaft and into these workings by a 10-in, main. Pressure at the face averages around 80 lb. per sq. in., while at the compressors, located on surface, it is constant at 90 lb. per sq. in. Moisture traps are inserted in the compressed-air lines at regular intervals.

To keep them out of the way of the diesel transport, compressed air lines and electric cables are supported by chains from roof bolts. By employing chain suspension, any misalignment of bolt holes can be overcome.

As has been mentioned before, compressed air for both the mine and the I.C.I. factory is supplied from installations under the control of the mine management. For this there are eight compressor installations, all of Bellis and Morcom manufacture, and powered by Mather and Platt electric motors. In the mine air station, there are two 305 b.h.p. machines, each of 1,470 cu. ft. per min. rating, and two of 650 b.h.p. supplying 2,770 cu. ft. per min. individually. In the central air station, there are three compressors each supplying 940 cu. ft. per min., and one at 2,060 cu. ft. per min. With the introduction of electric rotary drilling for production underground, more of the total compressed air delivery (13,400 cu. ft. per min.) will be available for use in the factory, and it is understood that the demand from this source is increasing.

Hoists

The present winder installations at both cage and skip shafts are similar, although built to the opposite hand. They were built by Scott and Hodgson and have 9 ft. parallel drums giving a rope speed of 930 ft. per min. Driven by a 350 h.p. 3,300 volts a.c. induction motor through gearing, the skip hoist handles ore at the rate of 200 tons per hour, in balanced skips, each of which contains 4¼ tons of anhydrite when loaded; locked-coil ropes of 1 ¼ in. diameter are used at both shafts.

As a third kiln for sulphuric acid manufacture will soon be completed, increased production will be required from the mine. The present winder imposes a limit on output, and it is understood that a new semiautomatic skip hoist to handle 300 tons per hour, has been ordered from the English Electric Co. Ltd. and M. B. Wild and Co. Ltd. (Birmingham), and will be installed this year.

Mill

Fig. 42 shows the present flowsheet for the mill. This plant was erected in 1927, and it is intended that this should, in keeping with the policy of modernising for increased production, be remodelled in the near future.

Anhydrite, from the 150-ton headframe bunker, is fed to three Hadfields size 7½ style A gyratory crushers through Ross chain feeders, which may be seen in Fig. 43. The stone is crushed to -3 in., and passed to three rotary screens, the undersize (-1 in.) being conveyed to the sulphuric-acid plant (4,000 tons per week) or to a 3,000 ton storage bin for onward transmission by bi-cable ropeway to the ammonium sulphate plant. Using 1 cwt. buckets, 100 tons per hour are handled over this ½ mile ropeway, and disposal by this means accounts for 11,000 tons per week.

The oversize from the screens (+ 1 in. to - 3 in.) may be conveyed to a transfer point for loading to rail for shipment to the company's Prudhoe works, which is 20 miles distant and which requires approximately 5,000 tons per week; alternatively it may be transferred to the stockpile, or taken on for further crushing. In the latter case, the material is conveyed to three 80-ton surge bunkers from which the stone is fed to Hadfields design C standard 48 in. disc secondary crushers, reducing the size to 1 in. when it joins the undersize from the rotary screens for either the ammonium sulphate or sulphuric acid plants.

To allow for the mine's annual holiday, or other shut-downs, a stockpile, which may be seen in Fig. 44 is maintained. A total of 45,000 tons may be stored in the area allotted, 10,000 tons of which will be under cover: Only material of over 1 in. size is stockpiled, as the action of rain on the fine sizes would create great difficulties in the reclamation. Feed to the pile is by a 30-in. Sutcliffe conveyor fitted with a throw-off carriage. The conveyor is reversible, and reclamation from the pile is accomplished with a Goliath crane and grab, manufactured by Stothert and Pitt, at a rate of 170 tons per hour. The grab transfers anhydrite from the pile to a hopper feeding on to the reversible conveyor belt. To obtain the maximum possible tonnage to be stored, the grab may be used as well as a bulldozer for heaping the stockpile.

Dust suppression and collection is carried out by means of a Visco-Beth bag-type dust filter. The collected dust is mixed with water and granulated to form pellets suitable for disposal.

The treatment plant contains 18 conveyors with widths ranging from 16 in. to 30 in., and manufactured by such firms as Mitchell Ropeways Limited, Fraser and Chalmers Engineering Works and Richard Sutcliffe Limited. The belt conveying material to the stockpile is equipped with a Samuel Dennison belt weigher, so that an accurate account may be kept on the stone being piled. Drives to the various major items of plant in the mill are by belt, although this form of power transmission is being superseded in favour of individual motors driving through Radicon gearboxes.

Acknowledgments

We should like to express our appreciation to Imperial Chemical Industries Limited for arranging our visit to this outstanding British property and, in particular, to Mr G. Eland Stewart, the mine agent and manager, who was good enough to devote much of his time to giving us every help in providing information, and showing us the achievements underground.

Drawings and Photographs accompanying the article

 

Prev Page Return to Top of Page Next Page

Article reproduced from a copy of the magazine held at National Mining Museum Scotland, Newtongrange, Midlothian.

 

mail
Mail:
Webmaster
Back
Back
Home
Home
Open Government Licence   Contains public sector information licensed under the Open Government Licence v3.0.

Copyright © 1999-2024 by The Durham Mining Museum and its contributors
Registered Charity No: 1110608
Page last updated: 17 Jan 2023

Privacy Policy
 
Terms & Conditions
 
Search
Search
Print
Print