Museum Entrance Museum
Museum
Friends of Durham Mining Museum
Events Calendar
e-Books and Books for sale
Photograph Gallery
Document Archive
Main Document Archive
Newspaper Articles
Local Record Extracts
D.M.A. Document Archive
Transactions of I.M.E.
Miners' Welfare
N.C.B. Archive
The Colliery Engineer
The Colliery Guardian
Mine & Quarry Engineering
Mine & Quarry Engineering - Main Index
Mine & Quarry Engineering - Subject Index
Mining Journal
The Science and Art of Mining
Coal Magazine
Coal News
Coke and Gas
Master Name Index
What's new in the site
Mining
Mining History
Colliery Index
Colliery Maps
Company Overviews
Who's Who
Mineral Information
Managers Certificates
Educational Material
Bibliography
Statistics
Workers/Employee Lists
Notes for Family Historians
War Service information
Disasters
Disaster Reports
Names of those killed
Disasters in the 1700s
Disasters in the 1800s
Disasters in the 1900s
Memorials
Awards for Gallantry
On this day ...

Links to other sites of interest
Industrial Heritage Days Out
Former www.pitwork.net web site

Index to site

Contact and address details

Share Page with Social Media

Share on Facebook

Share with Reddit

Share on Delicious

Title Prev Page Return to Index Next Page Title
 
Masthead
January, 1954

The Billingham Mine - Part 2

The description of the post-war conversion to trackless mining methods being implemented at this anhydrite property of Imperial Chemical Industries Limited is continued with a reference to rotary drilling research and details of stone-loading and diesel-haulage practice underground.

It is the aim of the management to replace pneumatic drilling in favour of electric rotary for the following reasons :—

  1. The dust problem. Much of the dust created by drilling dry with pneumatic drills and which limits the number of drills to two per face, would be eliminated by rotary drills, as they tend to produce more chippings than dust.
  2. Drilling efficiency. At the moment, 150 ft. per driller shift is obtained from the temporary carriage mountings used in the new panels. With the present rotary drill rig, one man has drilled 250 ft. in 5½ hours at penetration rate of 13½ in. per min. As it is the future intention to mount two rotary drills on booms on one carriage and operated by one driller, figures of 600 ft. per driller shift should be entirely feasible.
  3. Electric power. The mine is responsible for providing compressed air not only for its underground operation, but also for the whole factory area. Any saving of air in the mine would permit a greater proportion to be available for the works.

Fig. 14 shows the 5 h.p. electric rotary drill and boom mounting, connecting to the 17-ton Ruston tracked diesel carriage. As will be seen in the illustration, a remote-control push-button panel controls the aligning of drill and boom in any required position or direction. Both drill and booms were made by Hardypick Limited of Sheffield to I.C.I. specification, while the controls were worked out by the research department of the mine.

The drill bores a 1 3/8 in. hole, using tungsten-carbide type M bits, produced by Victor Products (Wallsend) Ltd., Northumberland, and is operated at 150 r.p.m. and a penetration rate of between 13½ and 15 in. per min. Two feeler rams have been fitted and these are extended to the face to preload the boom to the same stress as obtained in drilling. As the drill bit comes on to the face, the back pressure (measured by Statimeter) is transferred from the feeler rams to the drill bit.

Research is continuing with this drill technique, and the frontispiece illustration opposite depicts the latest development in which the mounting of the rotary drill booms is shown on a six-wheeled chassis. The management also hope to be able to reduce the diameter of the hole bored with rotary drilling from 1 3/8 in. to 1 5/16 in., since Special Rules have now been established, permitting 1/16 in. clearance over the size of the explosive used when shotholes are rotary drilled.

Stone-handling

It is in their methods of handling the broken anhydrite underground that the staff at Billingham have effected their greatest step to date in the modernisation programme. As the differences between the old method of working and the new are most marked, they will be discussed separately in the following paragraphs. However, both handling circuits marry up as may be seen from a reference to the flowsheet shown on the left.

Old method of working

Loading at the face into 25-cwt. mine tubs is done with scraper-loaders. Although these were originally of Holman and Sullivan manufacture, it was found that modification was necessary to enable the machines to stand up to the arduous duty of handling anhydrite, and the loaders now in use were built at the mine to a modified design. Powered by a 30 h.p. electric motor, and using 5/8 in. wire rope, the loader operates a 44-in, scraper blade. Eight-inch snatch blocks are used, and a normal face blast may be mucked out with five settings of this block.

Twin track of standard mine gauge (2 ft. 6 in.) is laid close to the scraper-loader, enabling empty tubs to be brought up on one line, while full ones are handled on the other. The switch for bringing the empties under the loader is of interest, being designed and made up at the mine ; the rails of the turn-out branch are brought into the straightaway at a slightly higher elevation at the point of intersection. Thus the flange of the wheel of the empty car is at the same height as the top of the rail of the straight track at this point, enabling the car to ride over without derailing. By this device, no movable points are required, the filled cars moving down the straightaway line ready for making up into a train.

As was shown in the mine plan reproduced as Fig. 4 on page 435 of our December, 1953 issue, the old workings are bisected by a double-track locomotive haulage road 18 ft. wide, called the Main West Level. From this level, rope haulage inclines 18 ft. wide by 9 ft. high are driven every 120 yards to both rise and (lip sides. Trains of tubs loaded by the scraper loaders at the face are moved to these rise or dip haulages by means of either Sullivan F.113 7½ h.p. Turbinair or Holman 14 h.p. vee-haulage tugger hoists, dependent on the gradients.

The dip haulages are double-drum units of 150 h.p., operating on a main-and-tail system; both Bever Dorling and Tinsley haulages are used, and on average grades haul a 25-ton payload. A typical installation may be seen in Fig. 18. The rise haulages, having only empties to raise, are 60 h.p. direct-drum type, but are provided with a two-speed gear as they have initially to move the loaded trains around the curves from the loader levels into the haulage plane. These haulages are of Tinsley manufacture, and are fitted with two independent braking systems, a hand lever operating a band brake on a 1 ft. 4 in. dia. drum on the first speed shaft and a foot and screw brake to a pair of double-caliper drum brakes.

Considerable research has been made at the mine into the subject of suitable safety devices for controlling runaway trains in these haulage ways and a derailing ramp was designed and put into use that will effectively stop a heavy train of tubs at speed.*

Prior to the installation of this device a steel warrick was the standard safety measure adopted, and these steel beams are still retained their main purpose now, however, is to operate by means of a mercury switch, electric signal lights which indicate at the intersection with the motor road whether a train is approaching. In the event of a runaway train, the alarm is given automatically when any bell push is depressed continuously by means of separate flashing lights at the intersection of the haulage incline with a motor road and with the locomotive haulage level.

At the Main West Level, these haulages leave their trains of full cars, and pick up the empties. This level was driven along the strike of the seam at a 1 in 80 grade in favour of the loaded tubs; this inclination limits the quantity of empties taken in by the locomotive, while the number of full tubs (up to 100) in a train coming into the tippler is controlled by the braking capacity of the locomotive. For this duty there are two six ton 74 h.p. English Electric trolley locomotives, operating on a two-wire system at 250 volts obtained from twin Mather and Platt motor-generator sets. One set is operated with the other available as a standby; each is of 100 kW capacity operating at 1,200 r.p.m. As is standard throughout the mine, Allen West starters are employed. This motor-generator equipment is located in a room adjacent to the haulage road. Safety switches for stopping the motor-generator set are operated from trip lines running the whole length of the Main West Level and in the area of the tippler, and the weighbridge.

Loaded cars run over a weighbridge, Fig. 19, before proceeding on down to the rotary tippler which is illustrated in Fig. 20; this is of Nortons (Tividale) manufacture, and is fully automatic being operated by the weight of the tub; the emptied tub is displaced from the tippler by the full one entering. A safety device ensures that only one tub at a time can enter and be tipped. A capacity of 300 tubs per hour can be handled by this plant.

The tubs in use underground are made by Allens of Tipton and are of 1/8 in. plate with a capacity of 27 cu. ft.; the axles are fitted with Skefko tapered roller bearings. Although not particularly suited to the present form of haulage, these tubs were originally designed and installed for hand-loading, and as tub-handling the anhydrite will be completely superseded by diesel trucks in the future, it is considered uneconomic to expend capital on any aspect of this form of haulage.

From the tippler, the broken stone falls by gravity to a storage bin or pocket, from which it is drawn into the skips through 4½-ton capacity measuring chutes which are fitted with air-operated arc gates.

New method of working

Loading at the face in the new panels is being done with Joy loaders into diesel-powered truck transport as may be seen from Figs. 21 and 22. Although development is still continuing on this method of mining, with the equipment available an output of 16-18 tons per manshift underground is already being obtained from these panels. This form of handling, from the face to the crusher in one operation, gives great advantages in capital expenditure on equipment, in economy of labour and in the elimination of dust that would be present if numerous transfer points were required.

In 1947, the first Joy loader was installed; this was an 11 B.U., 14 V, primarily a coal-loader, but it had modified track rollers and was fitted with an extended boom to permit stone to be discharged at 11 ft. or higher from the floor level, necessary for the transport then contemplated for the future. Later machines are of the 18 H.R. type, using the standard boom discharging at 8½ ft. above ground level into pneumatic tyred trucks fitted with specially wide and low bodies. This boom is free to move through a 45 deg. arc, to permit easy truck loading, though in practice only about 10 deg. of this movement can be used before trouble ensues due to the conveyor chain riding over the side plates.

* "New Derailing ramp in Billingham mine." by G. Eland Stewart, B.ENG.(Min.), Colliery Engineering, November, 1951.

Drawings and Photographs accompanying the article

 

Prev Page Return to Top of Page Next Page

Article reproduced from a copy of the magazine held at National Mining Museum Scotland, Newtongrange, Midlothian.

 

mail
Mail:
Webmaster
Back
Back
Home
Home
Open Government Licence   Contains public sector information licensed under the Open Government Licence v3.0.

Copyright © 1999-2024 by The Durham Mining Museum and its contributors
Registered Charity No: 1110608
Page last updated: 17 Jan 2023

Privacy Policy
 
Terms & Conditions
 
Search
Search
Print
Print