If any fall of roof or side displaces, breaks or renders ineffective any support at any place where any person has to pass or work (broadly, if a cavity forms where a further fall might cause injury) provisions against extension of the fall must be taken before the debris is cleared (Reg. 21). Generally, the ground at the ends of the fall should be supported to prevent it extending in length and then the ground exposed by the cavity should he secured. Fig. 28 shows how the sides of a small cavity at the face may he secured with stretchers, In the case of a fall in weaker ground, supports spanning the cavity may be set, and these would act as a base for supports set to the cavity roof (Fig. 29(a)). The cavity sides must also be supported; one method is shown in Fig. 29(b), and bolts or struts from the floor may be suitable. The coal opposite to the broken roof may have to be got by hand, as in Fig. 29(c), which shows how supports can be set in the hand-worked length to retain support in the cavity; a row of bars has been set in advance, and then the props in the row marked "X" may be taken out and the conveyor advanced without disturbing the supports in the cavity. Working by hand should continue until the roof over the conveyor is supported by bars set under firm roof; at that stage (Fig. 29(d)), power loading can be restarted throughout the face. Until the roof recovers its usual strength, extra advance support, through bolting or forepoling with small section girders set in holes bored in the seam at roof level, would help to prevent further falls; indeed if such steps were taken as soon as weak roof was observed, roof troubles of this kind might be averted.
Should a large fall occur, the debris can be cleared only by working and supporting across the face on the buttock, and extensive forepoling and lagging will be necessary for this to be done safely (Fig. 30(a)). Half arch girders may be set, as in Fig. 30(b) as clearing of the fall progresses and the face side of the cavity may be supported with roof bolts. Further falls may occur (as shown by the dotted line in Fig. 30(b)) as props are removed for the conveyor to be advanced, and it may be necessary to dismantle the conveyor and re-establish the face by breasting or heading it out (Fig. 30(c)).
The ground above the cavity may be so broken that the person in charge may consider that the process of supporting the exposed roof and sides would be dangerous. In that case, he should ensure that no one works in the vicinity of the cavity, except in accordance with directions given by the manager. For some situations the manager would he able to specify a method of procedure in advance, but in the worst cases he would wish to see the site himself before deciding upon what should be done; falls from cavities may involve the additional hazard of ignition of firedamp. A narrow high cavity, such as might develop near a fault plane, may be dealt with by crossing the cavity with girders which should be securely supported and heavily lagged (Fig. 31). The treatment of a larger fall in badly disturbed ground is shown in Fig. 32. First, the fall is prevented from extending, the arch girders adjacent to it being stabilised by chains and strutting (Fig. 32(a)). Forepoling from these girders into the fall area allows the debris to be removed gradually and further supports set (Fig. 32(b) and (c)). During these operations the cavity should be ventilated, by pipes or, possibly, through a firedamp drainage borehole reaching ground above the fall. Generally, such large cavities should be filled (Fig. 32(d)), the available lightweight filling materials being most suitable for the purpose, and the lagging being covered with brattice cloth or similar material to retain the filling, In some cases, the ground may be so broken that it is necessary to inject a binding agent into it, and into the fallen ground also, before recovery operations are attempted.
The manager must specify the system of packing to be used on any longwall face (Reg. 22 and Fig. 33), though he is not required to include in this packs built to deal with temporary or local weaknesses, such as faults crossing the face.
The spacings and widths of the packs should he chosen to suit the existing conditions. The maximum distance between the face and the packs opposite must be specified, but no limit has been put in the Regulations to this distance, partly because improvements in practice, such as the use of machines forming their own stables, may allow the distance to he much less than any that could be fixed to apply generally now, but the most critical distance, that between the face of a stable and the pack opposite, should be kept as small as possible. A limit of 7 feet is put to the distance that the face can advance between packing operations. This is partly to restrict the pack-to-face distance permissible and partly to prevent the removal of highly resistant props from a large area of roof in a short time. The pack must he built forward along its whole width before the face has advanced more than 7 feet. The amount by which the pack is advanced need not always be the same; this allows some flexibility, but the pack must always be kept within the distance of the face specified under Regulation 22(1).
In Regulation 23(1), the requirement that support rules shall provide for the setting and maintenance of supports at waste edges to prevent the breaking of the roof overriding the supports at the face is continued; in many cases this calls for the setting of chocks or chock-props to supplement the props set in the normal system (Fig. 34).
A new problem affecting wastes has arisen partly because of the more rapid rate of face advance and partly because waste edges are, on the whole, carried closer to the coal face. This may lead to the waste edge being in advance of the front line of the adjacent packs. So far as strip packs are concerned, the difficulty can he overcome by building them progressively during coal getting operations; the use of readily withdrawable supports makes it practicable to carry out the two operations on the same shift. However, it is not always practicable to rip during coal getting and so the waste may tend to get ahead of the roadside packs. In some such cases, a pack not less than 6 feet wide (Fig. 35) or cogs of timber, not less than 4 feet wide, are built at the edge of the roadside pack farther from the road as the waste is advanced. Experience has shown that with either of these practices, the roof does not break into the remaining pack space and, therefore, these arrangements may be prescribed in support rules. An alternative, made possible under Regulation 23(2), allows the waste edge to be taken up to 5 feet ahead of the pack front (Fig. 36). If this is done, some extra supports, which may be props, chocks or powered supports attached to the back of the face powered supports, must be set at the sides of the waste. Also, material for the pack must not, unless exemption is granted in special circumstances, for example, where the seam is highly inclined, be obtained from the waste; experience has shown the risks of falls extending from a waste side into a pack space and of obtaining stone from the side of a waste.
New methods of working and support are continually being devised, and some of them may not fit into the pattern of the new Regulations. H.M. Inspectors will then have to consider whether they can, without loss of safety, allow the necessary exemptions to permit trials.
Extensions of remote control are likely and they will affect many support operations. Methods of working that remove persons from disturbed ground must be beneficial, for example, the use of ripping machines avoids persons having to work near recently blasted ripping. Developments in powered supports already enable a support to be moved by an operator under the protection of the next support, or positioned even more remotely. However, though a fall occurring whilst no one is near cannot cause any direct injury, someone may be hurt whilst clearing the fall, and thus even with remote operation, it is necessary that the supports should be set promptly and accurately.
As more machines are used on or near to faces and as face supports become more complicated, they must affect each other increasingly; for example, the anchorages necessary to secure conveyors not only have to be fitted into the pattern of support but may themselves influence the roof condition. The less supports have to be held back or disturbed on account of machinery the better and yet the risk of machinery displacing supports must be avoided. These matters will have to be further considered in the future.
Deficiencies in support lead, in the long run if not always immediately, to roof troubles. The improved support measures required by these Regulations should result in better roofs, improved working conditions and a further reduction in accidents from falls of ground.