National Coal Board
No. 2 Area — Durham Division
Herrington Colliery Reconstruction
The Reconstruction Programme:
This visualised the coal from the neighbouring Dorothea Colliery being absorbed into Herrington Colliery, with a planned output of 3,000 tons per day raised.
In order to carry out this Reconstruction programme, and to deal with the additional output, a major programme of drifts and construction of new roadways out of old was commenced. The new roadways, 13,000 yards of which were completed during 1953, 1954 and 1955, were at the 980' BOD. level, and were driven at suitable gradients to allow the installation of diesel locomotive haulage with 2½ ton mine cars. Connections were made to existing roads of suitable gradient, and 4,100 yards of these roadways were enlarged to accommodate the locomotive haulage.
Completely new winding arrangements were necessary, and two new electric winders were installed together with skip winding plant in the No. 1 Shaft. The deepening of the No. 2 Shaft was achieved by sinking upwards from 980' B.O.D. to 777' B.O.D. the work being carried out whilst the shaft above 777' B.O.D. was still in use.
The quantity of air required to ventilate the enlarged mine was obtained by the installation of a new fan and the use of Dorothea Shaft as an additional Downcast Shaft, the Margaret Pit Shaft, which was already sunk to the Busty Seam being used as an additional Upcast Shaft.
Originally it was planned that the raw coal would go to a Central Washer, but eventually it was decided that it would be more economical to install a separate Washery plant at Herrington Colliery.
Many of the surface buildings were in a dilapidated condition and unsuitable for the reconstructed colliery. It was decided, therefore, that it would also be more efficient to completely reconstruct the surface layout.
The Scheme received Board approval in 1951, and the work of reconstruction commenced in 1953. Skip winding was commenced in August 1955, being the first such installation to work in County Durham. The Washer commenced working in mid-December 1956, and Dorothea Colliery was absorbed into Herrington as from January 1st, 1957. Development work underground continued during 1956/57, but was considerably hampered by unexpected faulting.
The Surface Reconstruction has involved the installation of two new winding engines, a new fan, the building of new winding engine houses, shaft top equipment, workshops, stores, offices, lamp cabin, two coal bunkers of 1,000 tons capacity each to serve the new 250 tons per hour coal washery, the extension of the pithead baths, improvements to the Medical Centre and the building of a new Canteen and car park.
The major portion of the surface reconstruction was completed by the end of 1957, and the opening in December 1958, of the extensions of the Pithead Baths, Medical Centre, and new Canteen, mark the completion of the surface reconstruction.