34. It was immediately obvious to the men in the pit bottom that a serious accident had occurred and the onsetter entered his cabin to telephone to the surface while the winding rope was still falling down the shaft. He was unable to obtain an answer to his emergency call on the automatic telephone but spoke to the surface operator on a magneto telephone. The mine emergency organisation was brought into operation with a control centre at the surface.
35. On the north side of the pit bottom some of the tangled winding rope had to be moved aside and there was difficulty in opening the cage gates because their vertical slide rods had been distorted by the crash. Nevertheless, once the gates were opened the removal of casualties proceeded quickly. Injections of morphia were given to the very seriously injured as they lay in the pit bottom before being transported to the surface. Some were brought out through the adjacent No. 2 shaft and to minimise delay others were carried down a steep drift to No. 4 shaft some 700 yards away. The last casualty arrived at the medical centre about two hours after the accident.
36. In the early stages of the recovery there was some delay in sending casualties to hospital but the situation improved when additional ambulances arrived from the County Authority. The mobile emergency winding engine from Mansfield Rescue Station was in position alongside No. 3 shaft about 80 minutes after the accident.
37. J. Maxwell, who that morning had started work at Markham for the first time, was in the pit bottom at the time of the accident and was seriously injured when he fell from the top deck platform while assisting in the recovery.