Logo Museum
Museum
Friends of Durham Mining Museum
Events Calendar
e-Books and Books for sale
Photograph Gallery
Document Archive
Main Document Archive
Newspaper Articles
Articles by date
Articles by colliery
Personal name index
Local Record Extracts
D.M.A. Document Archive
Transactions of I.M.E.
Miners' Welfare
N.C.B. Archive
The Colliery Engineer
The Colliery Guardian
Mine & Quarry Engineering
Mining Journal
The Science and Art of Mining
Coal Magazine
Coal News
Coke and Gas
Master Name Index
What's new in the site
Mining
Mining History
Colliery Index
Colliery Maps
Company Overviews
Who's Who
Mineral Information
Managers Certificates
Educational Material
Bibliography
Statistics
Workers/Employee Lists
Notes for Family Historians
War Service information
Disasters
Disaster Reports
Names of those killed
Disasters in the 1700s
Disasters in the 1800s
Disasters in the 1900s
Memorials
Awards for Gallantry
On this day ...

Links to other sites of interest
Industrial Heritage Days Out
Former www.pitwork.net web site

Index to site

Contact and address details

Share Page with Social Media

Share on Facebook

Share with Reddit

Share on Delicious


 Newspaper Articles Index Newspaper Articles 

15th December 1928, Page: 164, Column: 1

Machine Mining — Underground Conveying

By David Jackson, B.Sc.

From paper read at the November meeting of the Past and Present Mining Students' Association in the Wigan Mining and Technical Collage.

Economic pressure has been very severe in coal mining during the last few years, even in the coalfields with the least natural difficulties. Much attention has had to be directed to reduction in cost of production, and it has been generally recognised that, as in most other industries, the greatest economies are to be effected by concentration of production. The technical and economic advantages of intensive mining are, therefore, engaging the close attention of mining engineers at the moment. Intensive mining, or the concentrated production of coal, can be sub-divided into two distinct branches : (a) The getting of a maximum output per yard of face, and, (b) The collecting of that output and the delivering of it to the mechanical haulage. Both branches, which are definitely linked together, present many problems due to the varying and difficult conditions ever present in mining, and it is not possible to deal other than generally with either of them in one paper. Much attention, however, is being given at the present moment to underground conveying, and it is hoped that the following notes, which show to a certain extent the trend of modern practice, will serve as a basis for a good discussion.

The Getting of Coal.

In order to provide a background for the subject, it is necessary to give a brief outline of the history of the getting of coal. Coal was mined first of all at the outcrops of seams, and when that source became exhausted shallow bell-pits were sunk to the seams in the immediate vicinity of the outcrops. The amount of coal that could be extracted from these bell-pits was limited by the area that could be worked till the sides of the pits began to cave in. With increase in thickness of overlying strata, it became a difficult matter to get coal by bell-pits which produced only a small amount, and roads were driven in the seams in a haphazard manner from the bottom of these shafts, the pillars formed acting as supports to the roof. Advantage was soon taken of the cleavages in the coal, and thus it came that the pillar and stall system of working was adopted. The thicker and shallower seams were mined first, and the pillar and stall method of working proved satisfactory, and still is in many cases.

When the thicker seams in certain districts were worked out attention had to be directed to the thinner ones. It soon became apparent that the pillar and stall method of working did not permit of winning the coal economically from these thin seams. This and other reasons such as taking advantage of the roof weight in working led to the adoption of the longwall method of mining. In longwall working the face is advanced or retreated, as the case may be, in a line, and all the coal from the area worked is extracted in one operation.

A small tram was early adopted as the means of transporting the coal from the working place or face to the surface. In longwall working roads were formed at intervals to take these trams to and from the face. The distance apart of the roads and their dimensions varied with the conditions of the seams, but in general they were brought as close as possible to reduce the number of times the furthest away coal had to be thrown along the face before being filled into the tram at the roadhead.

The introduction of coal-cutters to facilitate the getting of coal brought new conditions. The yield o£ coal per yard of face per shift was increased greatly, and therefore much larger outputs had to be dealt with per gate-road. The long drawing roads common on hand-got faces were incapable of dealing with the outputs, and economy in collection was enforced. With coal-cutting came shorter drawing roads, more cross cuts, and more regular extensions of haulage.

The advantages and success of longwall work in thin seams coupled with the disadvantages of pillars in deep seams led to the adoption of the longwall method, or its variants, in thick seams. The same practice of collecting the coal by means of trams taken to the face through gate-roads followed in thick seams, but the distance apart of the gates was increased, and rail tracks were laid along the face to take the trams to any part of the face. The advantage of having the tram at the place where the coal is to be filled was recognised. To maintain this advantage in some of the thinner seams sacrifices have been made in other directions. In some cases, machines undercut deep in the floor to give extra height, in other cases smaller or specially designed trams have been adopted for working in thinner seams. By this method of taking trams along the face the coal is filled where it is got, but transport to the mechanical haulage is complicated and costly. The trams have to be man-handled up and down the face, twisted about on flat sheets, and often taken outbye a considerable distance to the haulage, and thus the coal-getter spends a large part of the shift doing work other than getting or filling coal. The method adopted of collecting the coal to the haulage in both thick and thin seams was, and is still, in the majority of cases by hand-putting, or drawing, the trams to and from the face through comparatively close gate-roads.

Reference has been made to the taking of trams along the face, so that the coal is filled where it is got, but this procedure is possible only in seams of moderate inclination. In the more highly inclined seams, such as are common in this district, the taking of trams to numerous gate-roads serving the face is a difficult matter. It is often necessary to plan the faces with special reference to tram distribution, which is always costly in seams with heavy gradients ; the man-handling of trams on heavy gradients is difficult, arduous, and sometimes dangerous work.

Conveying.

The introduction of conveying in underground workings is a step to bridge the gap between the coal face, where the coal is produced, and the main transport arteries leading to the shaft. The function of conveyors is in the collecting of the coal and in the delivering of it to main loading points on main haulage roads.

Advantages of Conveying. — Many advantages may be claimed for underground conveying, but most of them are applicable to particular conditions only, and incidental to the principal advantages which are :— (a) Reduced cost in transport between the mechanical haulage and the moving face, or, in other words, reduced cost in collecting and delivering the coal to the mechanical haulage. (b) Increased production per coal-getter, or filler, (c) Concentration of work, or reduction of pitroom.

(a) The conveying of coal mechanically eliminates the distribution and man-handling of trams to numerous points along the face, and in gate-roads which, for economic reasons, are usually of small dimensions. The coal produced from the length of face along which the conveyors are laid, is collected and delivered to the main road to the section. It is no longer necessary to lay tracks and maintain roadways at short intervals along the face, and thus the main road to the section benefits in that the economy resulting from the elimination of numerous roadways handling low outputs, more than balances the cost of making and maintaining one roadway suitable for handling the output collected from the district. The reduction in the number of roadways and the increase in the size of those remaining simplifies and improves ventilation.

(b) It is difficult to assess the advantages of a face conveyor to the coal-getter or filler in seams in which tubs are taken along the face, but it will be agreed that where tubs have to be brought from a pass-bye, manoeuvred on flat sheets, taken along the face, filled and returned to the pass-bye, a large percentage of the filler's shift is taken up with work, more arduous than the actual filling of the coal. Indeed, it may be added that the type of tram in use, in the seams of our coalfields which are thick enough to have the tram taken along the face, is such that filling into it is difficult due to the height the coal has to be raised. In this connection, it is interesting to note that, in America, the tendency in the design of trams for seams in which the coal is loaded by hand in the stalls, is to produce very wide but very shallow trams. It is considered to be an unnecessary waste of labour to throw coal over the side of a high tram. It is much easier to fill or roll coal on to a low conveyor on the face, than to fill it into a tram.

It is easier to realise the advantage of a face conveyor to the coal-filler in a seam in which a tram cannot be taken along the face. Where coal is filled into trams at gate-heads in such thin seam workings, it has to be thrown several times before it is filled into the tram, and there may be considerable breakage of coal in this casting. A conveyor laid along the face at the elbow of the filler eliminates this arduous work, and the output per filler on the conveyor should be something like his output by the old system multiplied by the average number of times he had to throw the coal. Thus, if his output was 5 tons per shift and he had to handle the coal an average of three times his output on to the conveyor should be 15 tons per shift, which is a figure common in actual practice.

(c) Concentration. The production of maximum outputs from concentrated areas brings, by reduction of pitroom, economies which need not be stressed.

Roof Control.

In the early period of conveying there were many failures, but most of these failures can be attributed, not to unfavourable seam conditions, but to concentration on, and asking too much of, advantages incidental to the proper function of the conveyor. It is hoped, therefore, that the following notes on roof control are appropriate in this paper. Roof control is one of the most important and most difficult operations in the getting of coal, and ought always to receive very careful consideration in laying out intensive mining faces. Whatever the method of getting the coal may be, it is necessary to keep up the roof, while working under it, and to let it down in the gob as the face and plant move forward. Although there are now many examples of roofs being sheared off behind the face and its machinery, and the active weight taken off the face in this way, which is undoubtedly a good procedure in many seams, and one worthy of consideration, the general practice is to use temporary or warning supports immediately at the face, and control the roof by pack walls in the goaf.

The introduction of conveying, with consequent reduction in the number of haulage roads, and much possible reduction in ripping, is no excuse for neglecting the roof or the goaf. Indeed, it allows full scope for roof control, that is, for handling just sufficient packing material and building the required number and size of packs to control the roof properly. Packing material is always available and at no greater cost than by ripping, as on the hand-drawn faces.

The chief disadvantage associated with the face conveyor is the increased area of roof exposed. When a face is machine cut the conveyor is generally laid in the track behind that traversed by the coal-cutter on the previous shift. This track is usually covered with coal holings after the face is cut. The roof from the back of the cut to the row of props behind the conveyor is exposed, and packs or buildings must be this distance away from solid coal. In some cases roof troubles due to this exposed roof have been avoided by laying the conveyor in the track of the coal-cutter after the face is cut. This method has the disadvantage that it may then be necessary to provide breaking in places for the men to work before the conveyor can run continuously. Difficulties with tender roofs are sometimes overcome by working on the "buttock" or end of the cut coal. Any disturbance or trouble with the roof is not usually experienced immediately the roof is exposed. It is some time later that the trouble occurs, that is, there is a time lag. The obvious procedure is to advance the face as rapidly as possible so that the roof disturbance takes place behind the working face and its machinery of production. The best conditions are achieved when the active roof disturbance is timed to take place exactly where and when it is necessary to sheer off, or break up, the roof in the gob. Conveying coal increases greatly the rate of advance of the face in that a larger output can be cleared per yard of face per shift, than by any other means. In addition, the conveyor demands a reasonably straight line of face, which is essential to good roof control. A maximum rate of advance with a straight face is therefore achieved.

Systematic timbering between the solid coal and goaf packs or gob line is of great importance on conveyor faces ; and it is sound policy to class the roofs of all conveyor faces under two headings :— (a) Good roofs which require props. (b) All other roofs. Bad roofs and particularly those with an immediate stratum of varying thickness liable to fall out at any moment, are generally well strapped. All roofs other than the very good roofs should be systematically strapped in the same way. On faces with good and bad patches of roof much attention is devoted to the uncertain roof by all face workers. Systematic strapping under these conditions may appear extravagant at first sight, but the extra cost is amply repaid by the added sense of security of the face workers, who can devote their whole attention to their work.

To be Concluded.


Names mentioned in this article

 

 Name  Age  Occupation  Notes 
Jackson, David      



Related Articles

Pub.
Date
Article (Newspaper)
15 Dec 1928  Machine Mining — Underground Conveying (The Science and Art of Mining)
29 Dec 1928  Machine Mining — Underground Conveying (The Science and Art of Mining)

 

mail
Mail:
Webmaster
Back
Back
Home
Home
Open Government Licence   Contains public sector information licensed under the Open Government Licence v3.0.

Copyright © 1999-2024 by The Durham Mining Museum and its contributors
Registered Charity No: 1110608
Page last updated: 28 Nov 2022

Privacy Policy
 
Terms & Conditions
 
Search
Search
Print
Print