Museum Entrance Museum Entrance Museum
Museum
Friends of Durham Mining Museum
Events Calendar
e-Books and Books for sale
Photograph Gallery
Document Archive
Main Document Archive
Newspaper Articles
Local Record Extracts
D.M.A. Document Archive
Transactions of I.M.E.
Miners' Welfare
N.C.B. Archive
The Colliery Engineer
The Colliery Guardian
Mine & Quarry Engineering
Mining Journal
The Science and Art of Mining
Coal Magazine
Coal News
Coke and Gas
Coke and Gas - Main Index
Coke and Gas - Subject Index
Master Name Index
What's new in the site
Mining
Mining History
Colliery Index
Colliery Maps
Company Overviews
Who's Who
Mineral Information
Managers Certificates
Educational Material
Bibliography
Statistics
Workers/Employee Lists
Notes for Family Historians
War Service information
Disasters
Disaster Reports
Names of those killed
Disasters in the 1700s
Disasters in the 1800s
Disasters in the 1900s
Memorials
Awards for Gallantry
On this day ...

Links to other sites of interest
Industrial Heritage Days Out
Former www.pitwork.net web site

Index to site

Contact and address details

Share Page with Social Media

Share on Facebook

Share with Reddit

Share on Delicious

Title Prev Page Return to Index Next Page Title
 
Masthead
May, 1959

The Cwm coking plant

An account of the planning and construction of the National Coal Board’s new works near Pontypridd together with a detailed description of the complete undertaking.

The Cwm coking plant and its neighbour at Coedely have centralised the N.C.B.’s foundry coke production in South Wales. The choice of the Cwm site was itself an interesting technical exercise owing to the many factors involved. At vesting date the N.C.B. inherited foundry coke plants, all old and relatively small, at Bargoed, Maritime, Coedely and Tondu, of which only Coedely was worth developing, since by building new ovens there the coking side could be brought up to the capacity of the byproduct plant (about 500 tons of coal a day), thus providing increased capacity at reasonable capital cost; the other plants were unsuitably sited and not adjacent to theii main coal supplies.

Centralisation of foundry coke production thus ideally demanded a site to accommodate a coking plant of economic size — about 1,500 tons of coal a day — near to a colliery big enough to supply all or most of the coal required, and of course with an adequate water supply. If the plant was to pay its way the gas must either be sold to the Wales Gas Board or, failing this, be used internally on an economic basis.

The first survey of coal supplies showed that Cwm colliery, which supplied about two-thirds of the Maritime requirements, had room for a new coke plant if the existing stream and road were diverted, but that the colliery output was far too small. Moreover the colliery was practically dry (5,000 gallons an hour) and the stream through the site, though freeflowing in winter, ran dry in most summers. Neither the stream nor the small sewage system of Lantwit Fardre, the nearest village, could be used for effluent disposal.

As regards gas disposal, if the new plant on normal maximum load supplied 8½-9 million cu. ft. a day the Wales Gas Board could take the whole of it in winter but less than a quarter in summer.

Water supply

Even if the colliery output could be increased by developments as yet undetermined, the site was useless unless water could be laid on. The Cwm and Maritime shafts were about three miles apart with a considerable ridge of high ground in between; they were, however, connected by a heading. The Rhondda River ran within half a mile of the Maritime shaft, and into the river two miles up-stream from Maritime the Hetty Pit was pumping large amounts of water; in addition the old Penhriw shaft near the Maritime ovens was used for district drainage, and on the high ground above Maritime was a small reservoir supplying this plant.

Thus, if the water on the Maritime side of the hill could be collected, diverted 3½ miles underground and raised at Cwm there were prospects of enough water for the Cwm coke plant and also for the new coal washery which would be needed there. Measurements over a period indicated that the various colliery supplies would be adequate in a good season but would fall short in a dry season, and the River Board’s permission was therefore sought to pump from the river into the Hetty Pit ponds if need arose.

The final scheme was to lay a surface pipeline for about 2½ miles from Hetty to the Maritime shaft, thence down the shaft underground for 3½ miles and up the Cwm shaft to the adjacent small high-level reservoir. The Penhriw shaft, from which water was previously pumped to the surface at Maritime, was to be connected to the Cwm system by driving a heading to the pump lodge, the water being then diverted underground to the foot of the Cwm shaft and so to the surface. The Maritime reservoirs were also to be connected into this system.

These sources, with the water from Cwm itself, and the water available from the stream on the site in the wet season, formed the total water supply. In view of the long pipelines, however, storage of at least seven days’ water on the coke-oven site was essential. Since the colliery pumping was largely on a two-shift basis, the high-level reservoir adjacent to the colliery overflowed during pumping shifts to the low-level storage and was kept to constant level on night shifts by reverse pumping from the low-level reservoirs. With this scheme, complex as it seems, the water supply (see Fig. 2) was assured and from this point of view the site was suitable.

Coal supply

The Mining Planning Departments now investigated colliery development. The coal, about 22 per cent. volatile matter and 4 per cent. ash, was of excellent quality and ideal for the purpose, but the colliery must clearly be developed to at least one million tons a year to supply the plant. Reserves were adequate, but it was finally decided that the technical and manpower needs could only be met by ceasing to raise coal at four neighbouring pits and diverting their output to the Cwm shafts; because of manpower difficulties it was decided to use the existing shafts to get the men to their work and to modernise the pit-head bath facilities, etc. accordingly. On this basis it seemed feasible to increase output to over a million tons a year, but some of the seams contained about 1.2 per cent. sulphur, which was thought too high to mix in for foundry coke production. The mining system was therefore adjusted to segregate the high-sulphur seams from those containing about 06 per cent. sulphur; the surface plant was also arranged to handle two coal varieties, the washery taking two streams but the froth flotation section taking both varieties below 1/16 in. as a single unit.

A further complication was that Coedely must now be supplied from the reconstructed Cwm colliery, and it thus appeared that total coal requirements would be of the order of million tons a year for coking purposes. Even a large colliery could only meet this demand by partial crushing of large coals.

Gas and steam

It was decided to deal with the gas available for sale by using for steam-raising the 6½ million cu. ft. a day of coke-oven gas which seemed likely to be surplus in summer. Allowing about 15 per cent. of solid fuel to cover the grates under these conditions, this gave an approximate steam-raising capacity of 100,000 lb. an hour. As the coke-oven demand would probably be about 30,000 lb. an hour, there was a clear case for a power station with pass-out turbines using about 100,000 lb. of steam an hour, passing out 30,000 lb. an hour to the ovens, and supplying power at a constant load into the colliery grid scheme already existing at Cwm.

The final scheme allowed for feed water heating with low-pressure steam from the coke-oven turbines and various inter-connections between the coke ovens and the power station for maximum fuel efficiency. In winter the power station load could be met wholly by coke breeze or low-grade coal.

Effluent disposal

The final problem was disposal of coke-oven effluents, for which chemical methods were reected as too elaborate and costly. Experimental work was started at Maritime on effluent disposal through the washery and using bacteriological methods; the final process proved wholly successful, and in view of the results of a full-scale unit at Maritime the Glamorgan River Board withdrew its objection to the siting of the plant at Cwm.

Placing of the contract

On the foregoing technical basis tenders were called, and a contract was placed with Simon-Carves Ltd. for the whole of the coking plant proper (beginning at the belts from the washery and ending with delivery of gas to the Wales Gas Board grid) and for the power station which produces 8,000 kW of power for the colliery grid.

Site planning

The coke-oven site is long and narrow and slopes in two directions in a valley. To facilitate planning and to determine the approximate extent of earthmoving, a sand model on a scale of 20 feet to the inch was built in a tray, the sand being formed to correspond with the levels from the colliery survey with the terraces excavated and levelled to spot heights; enlarged photographs of this model were of considerable value in discussions between the N.C.B. and Simon-Carves. The accompanying photograph (Fig. 3) shows the model after excavation, with a preliminary layout of the various units.

The final installation

The installation as finally planned comprises 108 ovens with four 500-ton blending bunkers and a 3,000-ton service bunker fed by belt either from the washery or from a wagon tippler — coke screening plant with rail loading and provision for future road loading — byproduct plant including sulphate-of-ammonia production and crude benzole recovery, purifiers for surplus gas, and compressors for gas delivery to the Wales Gas Board grid — a power station with boilers fired by solid fuel or coke-oven gas — a low level reservoir holding a week’s water supply — and a bacteriological effluent treatment plant. A small balance holder is provided for change-over gas, and the Wales Gas Board erected on the site a 1,000,000 cu. ft. holder on the inlet to the compressors. There is provision for a producer gas plant and for the extra purifiers which will be needed for the extra surplus gas which will be available if the ovens are heated by producer gas.

Coal plant

The plant is designed to handle two different coals drawn either direct from the washery or by rail from a wagon tippler feeding by belt on to the belt system from the washery. Four 500-ton drainage blending bunkers feed over Richard Simon constant-weight belt feeders to the hammer mill feeder conveyors.

There are two B.J.D. hammer mills (one a standby) crushing 1 in.-0, 80 per cent. through in. square mesh. A magnetic separator for tramp iron is fitted over the feed chute, and the mills are equipped with dust extraction gear which returns the dust to the belt leading to the service bunker. The bunker is fed by a rotating shuttle belt and holds 3,000 tons in two compartments, either of which can be emptied independently.

The oven charger cars are fed from the bunker by the slot and belt system. The bunker hopper bottom slopes steeply to eight slots with steel trunking leading to eight groups of four reciprocating tray feeders; eight belts collect from the feeders, four belts serving the north and four the south side of the oven battery. The belts feed into steel hoppers so placed that their mouthpieces are above the charger car hoppers when the car is on the weighbridge; the mouthpiece doors are opened and closed by thrusters interlocked with the driving gear of the tray feeders and belts, and as a further precaution an interlock prevents the belts working unless the charger car is in position. In emergency the cars can be fed direct from the service bunker by bypass chutes, four on the north and four on the south side.

Coal handling capacities

Feed to blending bunkers 200 tons/hour
Feed to hammer mills 160 tons / hour
Hammer mills 160 tons/hour each
Feed to service bunker 160 tons/hour

A belt weigher is provided in the feed belt to the blending bunkers.

Coke ovens

On each side of the service bunker there is a battery of 54 ovens divided into two blocks of 27 ovens. The principal cold dimensions are:

Length over oven sole 44 ft. 7 in.
Chamber height 12 ft. 6 in.
Mean width 1 ft. 6 in.
Oven taper 3 in.

Using coal of 6 to 8 per cent, moisture, the designed throughput is 1,350 tons a day with a coking time of 30 hours or 1,530 tons a day with a coking time of 26 hours.

The batteries are braced longitudinally by reinforced concrete end and intermediate buttresses with eight longitudinal tie bars. Cross-bracing is by buckstays formed of 14 in. x 12 in. broad-flanged beams tied to the nozzle decking at the bottom and joined at the top by pairs of 2½ in. diameter tie rods, both top and bottom rods having volute springs. The buckstays have pressure plates and screws to brace the regenerator walls behind them, the intermediate regenerator walls being braced by subsidiary buckstays carried on stringers from the main beams.

The ovens are of the compound type, though at present without lean gas fittings. Apart from having a single waste-gas flue (which, as shown in Fig. 5, is on the coke side) they are of standard Simon-Carves underjet hairpin-flue design with its well-known advantages of robustness and simple oven-temperature control. The ascension pipes are fitted with liquorsealed butterfly valves, steam injectors and liquor sprays. Each block of 27 ovens has separate double collecting mains with crossover connections, each side being controlled by its own Askania governor; the mains have end offtakes, and the foul mains cross the ram tracks on two pipe bridges, one to each battery, which also carry the mains for circulating liquor, steam and water. The oven doors are of the Wolff hammer set type, with latch screws mechanically operated from the extractor heads.

The side platforms are lowered, the coke side platform being carried on the waste gas flue, while the ram-side platform is supported at the inner edge from the buckstays and at the outer edge by steel columns.

There is one reinforced concrete quenching station at the north end of the plant, with provision for a second at the south end.

Magnetic alignment device. There are two sets of oven machines, of similar design to those at the Nantgarw coking plant in order to reduce the necessary stock of spare parts. Though the machines are otherwise of standard type, the magnetic alignment device is of special interest.

This equipment, shown in Fig. 6. ensures that coke car, guide and ram are correctly aligned on the same oven before coke can be pushed. Each oven has a pair of electrically connected coils, and similar coils are fitted on the ram and coke guide. The ram coil operates a relay in the power circuit of the ram motor on the forward stroke. The guide coil is connected to an alternating current source; in this circuit a switch closes when the guide is fully racked in, and a second switch closes when the coke car is correctly placed to receive coke; the alternating current in the guide coil then transmits through the two connected oven coils to the receiving coil on the ram, energising the relay and allowing the motor to drive the ram forward. Coke car and guide are interlocked by a bar on the car which closes a limit switch on the guide; should the car overrun the guide while coke is being pushed, the circuit is broken and the ram stops. A hand-operated switch enables the guide operator to break the circuit and stop the ram at will. The interlock works on the forward stroke of the ram, which may be withdrawn under power if pushing is stopped. The coils of the location system enable speech transmission to be provided between ram and guide when both machines are correctly placed.

None of the equipment is exposed to great heat, and the whole is well protected from dirt.

Coke handling plant

This plant, with a capacity of 80 tons an hour, comprises the coke screening and conveying system from the coke wharf to the delivery of large and domestic coke into rail wagons.

Two quenching cars feed coke on to a coke wharf 201 ft. long, from which it is fed through manual gates on to a 42 in. wide 80 tons an hour conveyor running horizontally below the lip of the wharf and then inclining upwards to feed coke to either of two 5-shaft rotary grizzly screens on the upper floor of the primary screen house; the screens are mounted on movable carriages so that either can be quickly moved out of position for servicing. The plus 3! in. cube overs from the screen are discharged on to a 42 in. wide 80 tons an hour cross conveyor and thence to a 42 in. wide boom loader conveyor discharging to rail wagons. Inside the screen house a horizontal length of the boom loader conveyor is carried on special idlers to facilitate the picking of ‘dead ends’ off the belt, for which purpose also the belt is driven through a 3-speed gearbox giving wagon loading capacities of 80, 60 or 40 tons an hour; the dead ends are dropped through the conveyor floor into a hopper, which, when full, is emptied through a cut-off gate into rail wagons.

The throughs of the screen pass through chutes to an inclined 24 in. wide 40 tons an hour conveyor feeding to 40 tons an hour reciprocating screens located over five 50-ton domestic bunkers, into which coke is discharged in the five sizes of 0-3/8 in 3/8-¾ in., ¾-1½ in., l½-2½ in. and 2½-3½ in. The bunkers are located over the rail tracks, and the breeze bunker discharges direct to rail wagons. Sized coke from the other four bunkers is fed to debreezing screens, from which the overs discharge into wagons; the breeze is delivered to an 18 in. wide 20 tons an hour conveyor feeding a bucket elevator at the breeze end of the bunkers, where the breeze or small coke is elevated and discharged either into the breeze bunker or on to the reciprocating screens.

The bunkers have side openings from which any size of coke may be fed by vibratory pan feeders to a 24 in. wide 40 tons an hour conveyor delivering to the tail end of the boom loader conveyor, this arrangement allowing domestic coke to be mixed as required with large coke and fed into wagons. The conveyor below the bunker side openings is reversible, so that domestic coke may be delivered to the producer plant if and when it is installed.

On the opposite side of the bunkers are openings, at present blanked off, to which chutes to road lorries or automatic bag filling and weighing machines may be fitted at a future date. Double bull head rails are laid under the bunkers and the roadway is finished level with the tops of the rails to allow lorries to run under the bunkers for loading.

 

Prev Page Return to Top of Page Next Page

 

mail
Mail:
Webmaster
Back
Back
Home
Home
Open Government Licence   Contains public sector information licensed under the Open Government Licence v3.0.

Copyright © 1999-2024 by The Durham Mining Museum and its contributors
Registered Charity No: 1110608
Page last updated: 31 Dec 2022

Privacy Policy
 
Terms & Conditions
 
Search
Search
Print
Print