water tubs, containing 50 and 140 gallons each. The sinking was then suspended, and the first metal wedging crib (14 feet by 6 inches) laid and two fathoms of light metal tubbing put on to outset the main body of the feeder, and the shaft walled up and secured to the bank, and driven between them and the two pits for conveying the water between the middle and top set of pumps. The machinery and pumps being in readiness, the sinking was resumed on the 19th Nov.. and continued down to a depth of 70- fathoms, when a double metal wedging crib was laid to rest the two standing sets upon, and the shafts tubbed off and closed under the first wedging crib. The sinking was then resumed and continued 6 fathoms further, where another wedging crib was solid and the shafts rendered dry to this point, being the last tubbing got in before arriving at the sand. After leaving a sufficient strength of limestone as a support to this last named crib, the shafts were enlarged or belled out before arriving at the sand, so as to be better enabled to contend with the anticipated difficulties and also to maintain in the end the full diameter of the shafts. This latter resumption of sinking had not been proceeded with far before the bottom of the pit blew up like a blast, and a deluge of water, sand, &c., was thrown up which speedily drove all hands out of the bottom. The lower sets of pumps being then short and hung upon strong 7 inch ground ropes attached to seven-fold blocks and crabs, were hove up out of the bottom, and the water allowed to settle. Upon plumbing the pit it was found that 9 feet in depth of sand over the whole bottom of the shaft had been sent up through the fissure. The two machines went 18 strokes per minute with a 4 feet stroke equal to 684 gallons per minute.
The East Pit was sunk upon one of the boreholes which followed the course of that shaft pretty regularly. The borehole was kept secured in advance by a long plug; when, however, the sinking was within 12 fathoms above the bed of sand, the plug burst out and a considerable quantity of sand was thrown up. This was the first intimation we had of the loose nature of this formidable opponent. The feeder through this borehole kept the 16 inch set going 12 strokes per minute with a 4½ feet stroke; the pressure of water in the other pit being 18 fathoms. Both pits being now opened to the sand, the gross amount of the feeders of water proceeding from it found to be more than a match for the pumping power applied, which, at this time, was confined to the 16 inch sets attached to the machines, the east main engine being yet in the hands of the manufacturer. During the progress of sinking thus far, the system of intercepting each considerable feeder of water as it was met with, was steadily practised, and every good foundation for a wedging crib promptly, and with great success, turned to account. By this means the shafts were kept remarkably dry until the period when the and feeder forcibly broke away through the bottom. The metal tubbing was carefully backed up with marl, and the marl on being saturated with water, became like cement and formed an impervious backing.
The metal tubbing used in these shafts was in segments of 2 feet and 18 inches in height, having ten segments to the course or ring. The thickness of metal varied as the pressure increased, being ¾ inch at the top, 1 inch in the middle, and 1¼ inch at the lower part of the limestone and sand. In front of the sand tubbing, where the pressure was greatest, metal rings 9 inches in depth were placed in additional security in front of the joints and set firmly against them with iron keys. The sheathing used was made out of clean Memel deals, planed to a uniform thickness of ½ an inch, and wedged until no moisture was visible at the joints, which were then adzed off. Previously to being put in, the tubbing was all carefully examined. the front surface scraped and painted with a strong-bodied anti-corrosive paint, which remained afterwards like an enamel upon its surface.
From a diary kept by Mr. Potter at the time, the operations appear to have been thus continued : On the 9th Aug. 1839, the sinkers got into the Middle Pit for 16 hours. Lowered the set 10 inches. and took off limestone sides for scale.. The two machines, (middle and west) kept the feeder at Il strokes per minute. The west machine (commenced pumping Aug. 2, 1839), having a 5½ feet stroke for all the three sets of 16 inch pumps attached to it. The middle machine had also a 5 feet 8 inch stroke in the pit, and those machines were going 16 strokes each whilst the men were in the bottom. Sept. 3rd — the east machine was going 12 strokes per minute (4½ feet strokes equal to 456 gallons per minute) exclusively, with water passing through the 1½ inch borehole, whilst the pressure of the water in the other pit showed a column of 18 fathoms. 9th — the low set of the middle machine having got choked with sand, it was hove up to the level of the standing set and hung upon the ground spears, but the water was never again drawn down to the bucket door until May 5, 1840, when the east main engine started work. Nov. 26th — got the water down in the East Pit and put a plug in the borehole, which enabled us to get the two 19 inch twin standing sets for the main engine in dry. Mar. 4th. 1840 — started the new 20 horse machine (Hawthorne's) in the East Pit for drawing stones, &c. Apr. 29th — started the east main engine. May 4th — resumed sinking in the East Pit, and drilled two additional holes down to the sand (7 feet) to draw off more water for the main engine. 5th. — got the water in the Middle Pit down to the bucket door of the choked set; this set having been hung for eight months on the ground ropes and spears. 22nd — the sand broke away from the bottom of the East Pit through a thin stratum of soft blue marl, the sinkers having great difficulty to save themselves. The rapidly with which the water came off, accompanied by a mass of loose sand, was so great that the two V bobs, or standing sets of the main engine, were instantly choked and held the engine fast. whilst the column of water rose 20 fathoms up the shaft in a very short time. An auxiliary 19 inch set of pumps was hung in the fore pit and attached to the main engine after having loosed off both the two V bobs and low sets. June 1st — got new set started, and on the 4th lowered the water down to the bucket door of the standing sets, when we found the working barrels and all below one solid mass of sand, as were also the delivery drifts leading to the high set. The feeders were found at this time to amount to 3.285 gallons per minute; our gross pumping power 4,341 gallons per minute. 16th — the sinkers got again into the bottom of the Middle Pit, and commenced filling away the cast-up sand, which was 4 fathoms above the bottom when they last left off. It was now clearly ascertained that the present engine and pumping power, although unprecedently extensive, was insufficient to combat with the difficulties with any apparent chance of success. June 26th — all the engines were stopped.
At this period the area of both pits was sufficiently occupied with pumps, ground spears, &c., to render it unadvisable, if not impossible to place any additional sets in them. Hence, if more pumps and machinery were required, more pit room would also be required to accommodate them. A proposition was then made and submitted to Messrs. Wood and Johnson to sink another shaft of larger diameter and place upon it two pumping engines, capable of delivering at bank two sets of pumps, each from a depth of 90 to 100 fathoms. This was approved of, and no time lost in putting it into execution. This shaft became afterwards invaluable as a general upcast shaft to the colliery. These twin engines, manufactured by Messrs. Hawks & Co., were of 450 horse power each, high pressure, and supplied with steam from 18 cylindrical boilers, placed in a most formidable line, and flanked by two chimneys of 80 feet in height each. A horizontal machine of 60 horse power was erected, to draw the sinking stones: and another of 14 horse power, to do the jack work, &c. The ground was broken for this pit July 7, 1840, the diameter set off being 18¼ feet, to allow for walling inside; this, with nine sinkers in the bottom, in a shift, was a formidable looking shaft. Probably no pit in the whole annals of sinking ever went more rapidly down until stopped by the feeder of water; the 40 fathoms were accomplished in 40 days. By the end of Jan. 1841, this shaft was sunk, walled, tubbed, and bratticed to the depth of 73 fathoms; being divided in to three parts, two for the pumps and one for the sinkers. The two new pumping engines were set to work in Feb. and March; every appliance being completed, and the water standing in the pit was drawn down and the sinking resumed. On the 16th April a borehole was put down from the bottom of the new pit into the sand, then within four feet, to lay the water on to the new engines. Immediately afterwards the bottom of the shaft blew up from the pressure. and the water to the same level as it was in the other pits, and thenceforward continued to rise and fall regularly with them, showing a free communication between them all May 9th — the whole of the limestone being taken off in the East Pit, and that shaft