1. Introduction The stability of a colliery rubbish tip is dependent on:
2. Strength of the Supporting Ground To ensure stability, the ground chosen as the site for a tip must be suitable for bearing the load to which it is to be subjected. In the South Wales Coalfield, the hills are formed in general of pennant sandstone covered more or less completely with layers of soil and subsoil. The sandstone is much fissured and is readily permeable by water. The valley bottoms are, in many cases, formed in alluvium, and this is in some parts overlaid on boulder clay which may cover the lower slopes of the hills. Thus, the ground in the valleys is often inferior as a foundation, considered solely from the standpoint of strength, to that of the hilltops. As a foundation, alluvial deposits are perhaps the worst type of ground. Clay is treacherous. If dry and containing boulders it may be capable of bearing a heavy load; but if wet and plastic, it is quite unsuitable, and it is very quickly affected by water. Sand is unsuitable when wet. Gravel is almost invariably good. Rock is best if it is the bedrock, and not an overlying layer which may disintegrate. Appendix I, compiled to show the permissible loadings on various types of ground on building sites, gives values of the safe pressure on foundations. A column is added to show the height of colliery tip corresponding to each load for tip refuse weighing 100 lbs. a cubic foot. 3. Inclination of Supporting Ground Inclination of the supporting ground affects the loading of the supporting ground, the distance to which, in the event of a slide, the material can travel and the action of water. Horizontal Surface If the ground surface is horizontal and the ground weak or affected by water, the tip may be raised to a greater height than the foundation can bear. The tip then sinks into the surface and the ground is squeezed out from beneath it in precisely the same way as a weak floor "creeps" in underground workings. This causes a slide of the tip material as shown in Appendix II. A slide under such conditions is of little consequence where there is no property near the tip which can sustain damage and where water courses are not liable to be choked. Where, on the other hand, the space around the tip is restricted, considerable damage may result. Inclined Surface In South Wales, many colliery tips are situated on sloping ground on the crowns or sides of hills. This ground may be bare unweathered rock or there may be a layer of soil and sub-soil of greater or less thickness. This surface layer may fail under load, and slide down the slope taking with it the tip which it supports. The probability of the occurrence of such a failure is greater if the layer of soil and subsoil is thick, or if it lies upon a smooth surface of bedrock inclined in the direction of the slope of the hill (Appendix III). 4. Action of Water In South Wales the action of water has been the most important factor in causing both landslides and slides of rubbish tips. A foundation of soil and subsoil, of clay or of sand is weakened considerably if water has access to it, and a supporting bed initially of sufficient strength may rapidly deteriorate. This is shown by the values given in Appendix I. The amount of water which falls annually upon the hills in South Wales is enormous. If the rainfall is 60 inches in a year, and this is the average value, the weight of water deposited upon a surface 100 yards square is about 12,500 tons. All of this water must flow from the surface or soak into the ground, and the greatest danger of sliding exists when a tip is so placed and aligned on a sloping surface that its presence interferes with the drainage. This is shown on Appendix IV. Rain water which penetrates a permeable rock such as Pennant sandstone, sinks until it is stopped by a bed of impermeable rock, usually a fireclay or a shale. When such a bed crops out on the slope of a hill, the water issues from the ground and a line of springs is formed as shown in Appendix V. These springs may flow continuously, or intermittently following a period of wet weather. If a rubbish tip is extended so as to cover such an outcrop, the issuing water may be checked or dammed, and a slide may result. Springs of water may also occur where the lower slopes of a hill are formed of impermeable beds overlying the permeable rock, as shown in Appendix VI. The tendency of a rubbish tip to prevent the drainage of water through it increases as the material composing it is weathered. In addition to water drained from the hillside, an immense amount of rain falls directly upon the surface of a large tip, and washes down to its base the fine clay products of weathering. It is then more liable to dam back water. A slide is usually the result of a combination of these circumstances:
5. Composition of Tip Material The material to be tipped differs greatly in both size and composition. This results in variation in the angle of repose that it takes up, and this must be taken into account when deciding on the location and subsequent management of the tip. The inclusion of such materials as "tailings" in the general run of rubbish for disposal can result in a marked lowering in the angle of repose from as high as 27° to as low as 4-5°. The tip then becomes completely unmanageable. 6. Precautions to Prevent Sliding
|
![]() |
||||||||
|
Mail: Webmaster |
Back |
Home |
Copyright © 1999-2024 by The Durham Mining Museum and its contributors Registered Charity No: 1110608 Page last updated: 31 Dec 2022
|
Search |
|
|||