II. The New South Locomotive Tunnel
General
The tunnel was started in August, 1956, at a gradient, rising inbye, of 1 in 180. It was driven to a point 82 yards beyond the main return and was then stopped for an explosion-proof air crossing to be made.
The tunnel was re-started in March, 1957. The Arley seam (2 feet 7 inches thick) had been encountered in the roof a short time before the tunnel had stopped. The seam dipped slightly in the direction of the advance of the tunnel; when the floor of the seam reached a point a foot or so below the tunnel floor a small area of known old workings was struck; appropriate arrangements had been made in the driving of the tunnel to approach this goaf. Although the old workings were of a solid nature there was a slight draw of air into them from the tunnel.
In June, 1957, a faulted zone was encountered but no unusual trouble was experienced; a second faulted area, 90 feet wide was encountered in September. This was crossed successfully but after a distance of 40 feet had been driven, the Arley seam was struck again, unexpectedly, in the roof. The Arley dipped at the gradient of 1 in 9 in the line of the tunnel, gradually passed through the tunnel face and went out in the floor within a distance of 60 yards. Soon afterwards, as Plate I shows, the line of drivage of the tunnel was turned through a considerable angle; normal strata consisting of grey bind with ironstone bands was encountered up to the time of the explosion.
On 18th June a notice was given by Mr. L. C. A. Benson, H.M. Senior District Inspector of Mines and Quarries, exempting the tunnel from the requirements of sub-section (1) of Section 24 of the Mines and Quarries Act, 1954, subject to the condition, among others, that not more than 20 persons were employed in the tunnel at any one time.
A compressed air driven endless rope haulage was installed in the tunnel just inbye of the air crossing, reaching as far as the bend in the road. At the time of the explosion preparations were being made for the installation of a smaller haulage to operate between the bend and the tunnel face.
The tunnel was supported by arch girders 15/16 feet by 13 feet set 3 feet apart. Conventional covering wood was placed behind the girders and as a precaution against fire dangers, concrete slabs were placed between the flanges of adjacent girders to give a completely incombustible roadway lining. Much of the floor was paved with bricks.
Until the air crossing was completed at the beginning of 1957 the tunnel was ventilated by a 24-inch compressed air driven Dollery and Palmer fan situated in the Main Pit Tunnel, and steel tubes 2 feet in diameter, the tunnel itself being the return. After the air crossing had been completed the arrangements were altered, ventilation being provided in the tunnel by the installation of similar 2 feet tubes suspended about 10 feet from the floor and reaching from the return airway through the new air crossing walls to within a distance of approximately 50 yards from the tunnel face; the length of the tunnel beyond the end of these tubes was ventilated by a compressed air operated forcing fan placed 11 yards on the intake side of the inbye end of the tubes, 24-inch canvas ducting being used to convey the air to the tunnel face. The short length of steel tubes which passed through the air crossing was 3 feet in diameter. The tunnel itself was now the intake, and the steel tubes, which were extended as the face advanced, were the return.
According to the ventilation records, the forcing fan was delivering a quantity of 4,920 cubic feet of air per minute at the inbye end of its duct on the day before the explosion. The fan was also recorded as drawing its air from a current of 10,000 cubic feet per minute; this figure, on account of the impossibility of measuring the air flow in the tunnel itself on account of the low velocity, was assumed to be the same as that said to be measured as entering the return tubes.
Gas was reported as having been found on one occasion only, on the nightshift of 23rd October, 1957, when the report of E. Higson, deputy, said "1½ per cent. of firedamp in cavity beyond the last arch; cleared by new crinoline (air duct) at 11.15 p.m.". At this time the Arley seam was probably present near the floor of the tunnel on the second occasion when it was exposed during the driving of the tunnel.
Shot firing and excavation of ground
During the driving of the first 280 yards of the tunnel the shots were fired in rounds of six using a Davis-Derby six shot exploder, unsheathed Polar Ajax explosive and approved cable with simultaneous detonators. On 27th May, 1957, a notice was given permitting the use of an unapproved Beethoven exploder, and larger rounds of shots with half second delay detonators began to be fired. Among the conditions attached to the legal instrument was one that a minimum quantity of 25 cubic feet of air per minute must be supplied at the face of the tunnel for every square foot of cross sectional area; it was a statutory requirement, of course, that two single core cables should be used for connecting the exploder to the shots. Three months after the Beethoven exploder was introduced, a different type of shot firing cable, viz., single core 3/0.036 V.I.R. insulated jute filled single wire armoured cable with overall braiding was brought into use. The shots were fired from a station which at the time of the explosion was 670 feet back from the tunnel face.
A later legal instrument consenting to the use of a similar exploder in another part of the colliery required that certain daily sampling of the general body of the air at the face of the tunnel should be carried out, so as an additional check a similar procedure of daily sampling was instituted in the New South Locomotive Tunnel, on 12th November; between that date and the explosion only one sample showed the presence of more than 0.35 per cent. of firedamp, this being a sample containing 0.5 per cent. taken on 3rd December.
After the shots had been fired, the ground was filled out by means of compressed air driven Eimco shovel loaders.
Progress during the later months of 1957 was satisfactory. Electricians were required in the tunnel on a number of occasions to attend to joints in the shot firing cable but apart from the following occasions there is no record of these visits. On the 4th December an electrician made an examination of the cable following a complaint that a round of shots could not be fired. The cable on the right hand side (facing inbye) was found to have about six joints all of which had been taped; on the left cable one bare joint was found (which was then taped up) and at about the half way mark the cable was seen to be completely severed. It was repaired and the joint was taped, after which a satisfactory test for continuity was carried out. The next day, following the receiving of a complaint that a round would not fire, another electrician was sent for, but when he arrived, the shots had gone off; an inspection of the cable disclosed three joints which required taping on the left side cable and on the right hand side there was a bad joint which required re-making and re-taping. No more repairs were needed. One length of 20 yards could not be examined because of the proximity of some tubs.