Logo Museum
Museum
Friends of Durham Mining Museum
Events Calendar
e-Books and Books for sale
Photograph Gallery
Document Archive
Main Document Archive
Newspaper Articles
Articles by date
Articles by colliery
Personal name index
Local Record Extracts
D.M.A. Document Archive
Transactions of I.M.E.
Miners' Welfare
N.C.B. Archive
The Colliery Engineer
The Colliery Guardian
Mine & Quarry Engineering
Mining Journal
The Science and Art of Mining
Coal Magazine
Coal News
Coke and Gas
Master Name Index
What's new in the site
Mining
Mining History
Colliery Index
Colliery Maps
Company Overviews
Who's Who
Mineral Information
Managers Certificates
Educational Material
Bibliography
Statistics
Workers/Employee Lists
Notes for Family Historians
War Service information
Disasters
Disaster Reports
Names of those killed
Disasters in the 1700s
Disasters in the 1800s
Disasters in the 1900s
Memorials
Awards for Gallantry
On this day ...

Links to other sites of interest
Industrial Heritage Days Out
Former www.pitwork.net web site

Index to site

Contact and address details

Share Page with Social Media

Share on Facebook

Share with Reddit

Share on Delicious


 Newspaper Articles Index Newspaper Articles 

14th June 1941, Page: 394, Column: 1

Eastern Transvaal Drainage Tunnel

Noticeable Features When Driving.

At the January meeting of the Chemical, Metallurgical and Mining Society of South Africa, Mr. R. O. L'Ange presented some notes on "Driving the Glynn's Lydenburg Drainage Tunnel." He was the official in charge, and he said the scheme was to drain the mine by gravitation instead of pumping, and to ensure the mine from flooding. The total footage when connected was 12,898 feet in the main tunnel, though with deviations, side drives, winzes and raises the total was 16,577 feet. The dimensions were 10 feet by 8 feet where concrete lining was required and 15 feet by 8 feet in the solid formation ; the additional width made it possible to break longer rounds.

Glynn's Lydenburg mine is situated at Sabie in the Eastern Transvaal on the Eastern escarpment of the Drakensberg mountains. It is a heavy rainfall area. The "Reef" occurs in the Dolomites of the Black Reef series. These dolomites, due to the heavy rainfall, contain large quantities of water, and during the year the tunnel was started the mine pumped no less than forty-eight (48) tons of water for every ton of rock hoisted.

Appended are some extracts from Mr. L'Ange's paper :—

It often happened that when holes were drilled in the face water would flow from them under such pressure that it was impossible to charge them ; indeed, there were occasions when a charging stick could hardly be pushed into the hole against the water pressure. In such cases it was sometimes necessary to drill up to 40 holes in order to blast 20. Frequently it was a case of blasting only half a dozen holes at a time, the blasting of which often cut off the water for sufficiently long to enable a few more holes to be blasted, such was the fractured nature of the ground. A method used to charge holes in which the water pressure was not too great but sufficient to wash out the explosives immediately the charging stick was withdrawn was as follows :—

The requisite number of sticks of gelignite complete with primer and fuse were threaded on to a ¼-inch copper wire and inserted into the hole ; a wooden plug two feet long with a hole drilled through its long axis through which the fuse passed was then placed in the hole and driven in. Great care was necessary to see that the hole was not fully charged and that there was ample space between the primer and wooden plug, otherwise the driving of the wooden plug would explode the charge. The copper wires were always recovered after the blast, straightened and used again.

Cementation was considered, but owing to the large volumes of water and the extent and width of the fissures (some of which were 1½ to 5 feet wide, resembling stopes) it was deemed to be impracticable and too costly.

Electric blasting was also considered, but with the intermittent blasting taking place throughout the day, the uncertainty of how many holes could be blasted at a time and the very wet conditions, it was considered to be inadvisable. Primers and fuses were waterproofed.

In some 16,000 feet of driving not one blasting accident took place in spite of the wet conditions.

At 4,860 feet from the portal a large fissure giving off approximately five million gallons of water per day was broken into. This was the biggest flow experienced from one fissure. They had holed into an open chamber four feet wide, increasing to about ten feet at its apex which was some 50 feet above the roof of the tunnel.

Placing concrete under the wet conditions met with when water was gushing out all over the place proved very difficult. In the method eventually adopted the boxing was made as watertight as possible and the paper bags containing the cement were used as packing and also tarred sacking. Pipes were put in to carry the water through the shuttering, but it was impossible to guide all the water through them. After piping off as much as possible the balance was allowed to accumulate in the box and flow over the top. The concrete mixture was mixed and put in dry, care being taken that there was always sufficient ready to keep pace with the filling ; speed in filling was essential. As the concrete was put in it forced the water over the top. This method may not meet with general approval, but the hardness and good condition of the walls erected in this way (after three years) is testimony of the efficacy of the method.

When there was only some 100 feet to go to complete the tunnel there was a severe mud rush, 3,500 tons of mud rushing forth and sweeping everything before it. This mud area had also been encountered in two headings from the South Shaft which were being driven in an attempt to get down to the tunnel level. It was decided to put up a diamond drill hole to test the formation in a direction that offered possibilities of finding a way through. The formation proved to be solid and a raise at 50° was put up 137 feet to meet a drive from the upper workings, and on the 16th May, 1940, the connection was at last made, after over five years.

The danger of the flooding of the mine has been eliminated.

Equipment.

Referring to the equipment, used Mr. L'Ange said haulage was done by a six-ton electric storage battery locomotive fitted with Edison cells. This loco, was put into commission in May, 1930, has hauled approximately 135,000 tons of rock besides much other material, and after four years is still in excellent condition. It is interesting to note that this unit has been in use for 21 hours per day for seven days a week during most of the four years and has never been out of use for repairs since being put on the job.

Trucks were flat and of two-ton capacity mounted on ballbearing wheels on 24-inch gauge track of 45 lb. rails.

Cleaning was done by a Scraper loader which was air driven. The exhaust air from the hoist materially assisted ventilation. The scraper was usually working under water and the backward and forward motion set up waves which packed the stuff like cement, making it difficult for the scraper to dig in and take its load. To remedy this a heavy scarifier (similar to those used in road making) was made. The scraper was hooked off and the scarifier hooked on and drawn back and forth several times, and very effectively dug up the compacted stuff. The scraper was then again hooked on and had no difficulty in getting its load. It was only necessary to do this two or three times a shift.

Ventilation was provided by a 25-inch high pressure Sirocco fan with 22-inch ventilation pipes, 34 h.p. motor. A Browett Lindley vertical type, direct drive compressor of 1,000 cubic feet free air per minute, was provided and proved adequate.

Passenger coaches for transporting the personnel were built.

Climax rockdrills used on the main face were 3.5-inch Drifters using 1¼-inch round steel. Jackhammers were used for odd jobs.

In the whole job there was only one fatal accident and remarkably few other accidents, with not one duo to explosives.

Now that the work is completed, the pumps stopped and the water from the mine added to that making in the tunnel, the total flow of the portal is 11½ million gallons per day, though in the rainy season it has reached 13 millions.

Some Comparisons.

Major J. S. Crawhall, in a contribution to the paper, said the Glynn's Lydenburg drainage tunnel was beset with troubles from its outset, and the fact that 503 feet of advance was made in a month of twenty-six days with only forty-nine blasts is testimony that the crew knew how to make headway when ground conditions improved.

In recent years some of the more important drainage tunnels that have been driven include that of the Cerro de Pasco Copper Corporation in Peru. The Morococha Mine, 15,000 feet above sea-level, was pumping 20 million gallons per day and required to mine at deeper levels.

The Major had visited the Halkyn drainage tunnel in North Wales, and he commented on the combined question of tunnel gradient and adequate drainage. Glynn's Lyndenburg is driven on a gradient of 1 in 400, whereas the, Halkyn tunnel gradient was 1 in 1,000, and both drained approximately the same amount of water. On the 17,000 feet projected at Lydenburg this difference in gradients would have meant adding a possible 25 feet of vertical depth to the ore reserves. It may be argued that the quantity of water to be dealt with was unknown, but a calculation on Bazin's formula shows that an unlined water channel three feet wide by two feet deep will only carry 5½ million gallons per day, whereas a smooth finished concrete-lined channel of the same section will carry 20 millions per day on a gradient of 1 in 400. The question as to whether this channel should have remained unlined during construction or not, must therefore have been a very real one. A further point in favour of the lined channel is that it is so much more easily cleared of silt from normal working and from mud rushes, but the channel must necessarily be lined as the heading advances.

The Halkyn tunnel resembles the Lydenburg tunnel in that both had to traverse highly fissured ground, and that "vugs" filled with clay, sand and gravel were met with from time to time, and in each case it was necessary to make diversions from the projected course to circumvent these "vugs."

One of the most serious matters which a tunnelling contractor has to face is the question of "overbreak," because he is invariably called upon to fill excess excavation over the stipulated thickness of walls at his own expense with concrete. It is common practice to drive the tunnel slightly under than over size, and then blast off projections which are indicated by the template carried on the "trimming carriage." Overbreak, unless it is carefully guarded against, is the downfall of many contractors.


Names mentioned in this article

 

 Name  Age  Occupation  Notes 
Crawhall, Major J. S.      
L'Ange, R. O.      


 

mail
Mail:
Webmaster
Back
Back
Home
Home
Open Government Licence   Contains public sector information licensed under the Open Government Licence v3.0.

Copyright © 1999-2024 by The Durham Mining Museum and its contributors
Registered Charity No: 1110608
Page last updated: 28 Nov 2022

Privacy Policy
 
Terms & Conditions
 
Search
Search
Print
Print