14th June 1941, Page: 394, Column: 1
Eastern Transvaal Drainage Tunnel
Noticeable Features When Driving.
At the January meeting of the Chemical, Metallurgical and Mining Society of
South Africa, Mr. R. O. L'Ange presented some notes on "Driving the
Glynn's Lydenburg Drainage Tunnel." He was the official in charge, and he
said the scheme was to drain the mine by gravitation instead of pumping, and to
ensure the mine from flooding. The total footage when connected was 12,898 feet
in the main tunnel, though with deviations, side drives, winzes and raises the
total was 16,577 feet. The dimensions were 10 feet by 8 feet where concrete
lining was required and 15 feet by 8 feet in the solid formation ; the
additional width made it possible to break longer rounds.
Glynn's Lydenburg mine is situated at Sabie in the Eastern Transvaal on the
Eastern escarpment of the Drakensberg mountains. It is a heavy rainfall area.
The "Reef" occurs in the Dolomites of the Black Reef series. These
dolomites, due to the heavy rainfall, contain large quantities of water, and
during the year the tunnel was started the mine pumped no less than forty-eight
(48) tons of water for every ton of rock hoisted.
Appended are some extracts from Mr. L'Ange's paper :—
It often happened that when holes were drilled in the face water would flow
from them under such pressure that it was impossible to charge them ; indeed,
there were occasions when a charging stick could hardly be pushed into the hole
against the water pressure. In such cases it was sometimes necessary to drill
up to 40 holes in order to blast 20. Frequently it was a case of blasting only
half a dozen holes at a time, the blasting of which often cut off the water for
sufficiently long to enable a few more holes to be blasted, such was the
fractured nature of the ground. A method used to charge holes in which the
water pressure was not too great but sufficient to wash out the explosives
immediately the charging stick was withdrawn was as follows :—
The requisite number of sticks of gelignite complete with primer and fuse were
threaded on to a ¼-inch copper wire and inserted into the hole ; a wooden
plug two feet long with a hole drilled through its long axis through which the
fuse passed was then placed in the hole and driven in. Great care was necessary
to see that the hole was not fully charged and that there was ample space
between the primer and wooden plug, otherwise the driving of the wooden plug
would explode the charge. The copper wires were always recovered after the
blast, straightened and used again.
Cementation was considered, but owing to the large volumes of water and the
extent and width of the fissures (some of which were 1½ to 5 feet wide,
resembling stopes) it was deemed to be impracticable and too costly.
Electric blasting was also considered, but with the intermittent blasting
taking place throughout the day, the uncertainty of how many holes could be
blasted at a time and the very wet conditions, it was considered to be
inadvisable. Primers and fuses were waterproofed.
In some 16,000 feet of driving not one blasting accident took place in spite of
the wet conditions.
At 4,860 feet from the portal a large fissure giving off approximately five
million gallons of water per day was broken into. This was the biggest flow
experienced from one fissure. They had holed into an open chamber four feet
wide, increasing to about ten feet at its apex which was some 50 feet above the
roof of the tunnel.
Placing concrete under the wet conditions met with when water was gushing out
all over the place proved very difficult. In the method eventually adopted the
boxing was made as watertight as possible and the paper bags containing the
cement were used as packing and also tarred sacking. Pipes were put in to carry
the water through the shuttering, but it was impossible to guide all the water
through them. After piping off as much as possible the balance was allowed to
accumulate in the box and flow over the top. The concrete mixture was mixed and
put in dry, care being taken that there was always sufficient ready to keep
pace with the filling ; speed in filling was essential. As the concrete was put
in it forced the water over the top. This method may not meet with general
approval, but the hardness and good condition of the walls erected in this way
(after three years) is testimony of the efficacy of the method.
When there was only some 100 feet to go to complete the tunnel there was a
severe mud rush, 3,500 tons of mud rushing forth and sweeping everything before
it. This mud area had also been encountered in two headings from the South
Shaft which were being driven in an attempt to get down to the tunnel level. It
was decided to put up a diamond drill hole to test the formation in a direction
that offered possibilities of finding a way through. The formation proved to be
solid and a raise at 50° was put up 137 feet to meet a drive from the upper
workings, and on the 16th May, 1940, the connection was at last made, after
over five years.
The danger of the flooding of the mine has been eliminated.
Equipment.
Referring to the equipment, used Mr. L'Ange said haulage was done by a
six-ton electric storage battery locomotive fitted with Edison cells. This
loco, was put into commission in May, 1930, has hauled approximately 135,000
tons of rock besides much other material, and after four years is still in
excellent condition. It is interesting to note that this unit has been in use
for 21 hours per day for seven days a week during most of the four years and
has never been out of use for repairs since being put on the job.
Trucks were flat and of two-ton capacity mounted on ballbearing wheels on
24-inch gauge track of 45 lb. rails.
Cleaning was done by a Scraper loader which was air driven. The exhaust air
from the hoist materially assisted ventilation. The scraper was usually working
under water and the backward and forward motion set up waves which packed the
stuff like cement, making it difficult for the scraper to dig in and take its
load. To remedy this a heavy scarifier (similar to those used in road making)
was made. The scraper was hooked off and the scarifier hooked on and drawn back
and forth several times, and very effectively dug up the compacted stuff. The
scraper was then again hooked on and had no difficulty in getting its load. It
was only necessary to do this two or three times a shift.
Ventilation was provided by a 25-inch high pressure Sirocco fan with 22-inch
ventilation pipes, 34 h.p. motor. A Browett Lindley vertical type, direct drive
compressor of 1,000 cubic feet free air per minute, was provided and proved
adequate.
Passenger coaches for transporting the personnel were built.
Climax rockdrills used on the main face were 3.5-inch Drifters using
1¼-inch round steel. Jackhammers were used for odd jobs.
In the whole job there was only one fatal accident and remarkably few other
accidents, with not one duo to explosives.
Now that the work is completed, the pumps stopped and the water from the mine
added to that making in the tunnel, the total flow of the portal is 11½
million gallons per day, though in the rainy season it has reached 13 millions.
Some Comparisons.
Major J. S. Crawhall, in a contribution to the paper, said the Glynn's
Lydenburg drainage tunnel was beset with troubles from its outset, and the fact
that 503 feet of advance was made in a month of twenty-six days with only
forty-nine blasts is testimony that the crew knew how to make headway when
ground conditions improved.
In recent years some of the more important drainage tunnels that have been
driven include that of the Cerro de Pasco Copper Corporation in Peru. The
Morococha Mine, 15,000 feet above sea-level, was pumping 20 million gallons per
day and required to mine at deeper levels.
The Major had visited the Halkyn drainage tunnel in North Wales, and he
commented on the combined question of tunnel gradient and adequate drainage.
Glynn's Lyndenburg is driven on a gradient of 1 in 400, whereas the, Halkyn
tunnel gradient was 1 in 1,000, and both drained approximately the same amount
of water. On the 17,000 feet projected at Lydenburg this difference in
gradients would have meant adding a possible 25 feet of vertical depth to the
ore reserves. It may be argued that the quantity of water to be dealt with was
unknown, but a calculation on Bazin's formula shows that an unlined water
channel three feet wide by two feet deep will only carry 5½ million
gallons per day, whereas a smooth finished concrete-lined channel of the same
section will carry 20 millions per day on a gradient of 1 in 400. The question
as to whether this channel should have remained unlined during construction or
not, must therefore have been a very real one. A further point in favour of the
lined channel is that it is so much more easily cleared of silt from normal
working and from mud rushes, but the channel must necessarily be lined as the
heading advances.
The Halkyn tunnel resembles the Lydenburg tunnel in that both had to traverse
highly fissured ground, and that "vugs" filled with clay, sand and
gravel were met with from time to time, and in each case it was necessary to
make diversions from the projected course to circumvent these "vugs."
One of the most serious matters which a tunnelling contractor has to face is
the question of "overbreak," because he is invariably called upon to
fill excess excavation over the stipulated thickness of walls at his own
expense with concrete. It is common practice to drive the tunnel slightly under
than over size, and then blast off projections which are indicated by the
template carried on the "trimming carriage." Overbreak, unless it is
carefully guarded against, is the downfall of many contractors.
 |
 |
|