31st May 1941, Page: 378, Column: 2
Roof Control And Conservation Of Supports
The most direct means of conserving timber and steel supports is by maintaining
a high standard of roof control at the face and on the roads, thereby reducing
overloading, crushing, and loss of supports to an absolute minimum. With that
brief introduction Dr. J. R. Dinsdale and Mr. J. M. Hughes in
their paper on "Roof Control and the Conservation of Timber and Steel
Supports," before the South Wales Institute of Engineers, said that at a
colliery detailed observations were made in a district that was wholly
supported on timber and has since been converted to steel. The seam is 3 feet
thick and is overlain by about 6 inches of clod, the depth from the surface
being about 600 yards. The roof is a very weak shale and the floor a weak
fireclay. Thirty-three feet above the seam another seam 6 feet thick has been
worked out. The district is a double unit conveyor face 300 yards long with
three roads leading to the face, one at each end of the face, and a loading
level lined with 14 feet steel arches in the middle of the face. The face
supports are nearly 100 per cent. steel and consist of rigid steel posts and
steel straps. As the quality of packing improved, the roof conditions also
improved, and the falls were eliminated, the output for the district was
raised, and the steel losses were gradually reduced. The steel arches
supporting the three roads to the face are erected on wood "bridges"
cut from scrap timber which act as stilts and allow the arches to yield without
any appreciable distortion. Describing the cycle of operations the Authors said
:—
Each side of the double unit is advanced every other day so that the whole
double unit is turned five feet every two days, when the face is advancing at
its normal rate. The steel supports are withdrawn opposite the packs on the
afternoon shift on the side that, is being turned that day. The same night the
packing on this side of the double unit is put in and, completed. The steel
supports in the wastes on this half of the district aw withdrawn the following
afternoon, leaving only one row standing behind the conveyor.
Similarly, on the other half of the double unit the steel supports are
withdrawn opposite the packs on one afternoon. The same night the packs on this
half are put in and completed, and the next day the steel supports are
withdrawn opposite the wastes. This work is so arranged that when supports are
being withdrawn opposite the packs on one half of the district, they are being
withdrawn opposite the wastes on the other half. Exactly the same cycle is
maintained for each half of the district, but each is one day out of phase with
the other. This system enables all packs to be completed on the first night on
the side that has turned. The next night all the packers and rubbish tippers
are then able to concentrate on the other side of the double unit and complete
the packing on that side.
Three "sets" of two steel drawers are maintained on the face. One set
can withdraw the steel posts and straps opposite the packs on one half of the
district in one shift. But, since the steel posts in the wastes are not drawn
until the following afternoon, these have to stand one day longer. In
consequence, the supports in the wastes are more difficult to withdraw and four
men are required to extract the posts and straps in the wastes on one half of
the district in a shift. During these observations convergence records were
made and these showed a steady uniform rate of subsidence of the roof and the
absence of sudden changes in the rate of convergence associated with
"weights" and heavy falls. The main features of the work done in the
district to maintain good roof control and reduce the steel losses, the Authors
say, can be briefly summarised as follows :—
Good system of packing to suit the roof conditions and the packs reinforced
with about 10 trams of quarry stones every shift to enable strong corners and
walls to be built.
Building face walls of packs at least 6 inches clear of steel posts so that the
Sylvester chain can be put around posts opposite packs without disturbing pack
walls.
Keeping roadhead rippings close to face and sending these stones down the face
for packers.
Maintaining good height at roadhead for packing stones to be sent in by taking
down 2 feet 6 inches road rippings at coal face for width of road. This also
enabled the building of the roadside packs to be commenced at once from this
stone without having to wait for stones from main rippings.
Strong face posting, which was facilitated by taking down the 6 inches of clod
on top of the seam to give a better roof for colliers to strap against.
Good system of steel drawing. This was so arranged that it could be completed
every day opposite the packs on one half of the face, and opposite the wastes
on the other half. This prompt withdrawal of steel posts prevented excessive
loading and penetration of posts into the floor.
Placing steel posts on the face side of the conveyor to prevent loss in rubbish
behind conveyor.
Keeping the face straight.
Keeping the face clean by giving good clearance to colliers and packing tightly
all rubbish.
Careful check on all posts and straps sent into and out of the district.
 |
 |
|