Logo Museum
Museum
Friends of Durham Mining Museum
Events Calendar
e-Books and Books for sale
Photograph Gallery
Document Archive
Main Document Archive
Newspaper Articles
Articles by date
Articles by colliery
Personal name index
Local Record Extracts
D.M.A. Document Archive
Transactions of I.M.E.
Miners' Welfare
N.C.B. Archive
The Colliery Engineer
The Colliery Guardian
Mine & Quarry Engineering
Mining Journal
The Science and Art of Mining
Coal Magazine
Coal News
Coke and Gas
Master Name Index
What's new in the site
Mining
Mining History
Colliery Index
Colliery Maps
Company Overviews
Who's Who
Mineral Information
Managers Certificates
Educational Material
Bibliography
Statistics
Workers/Employee Lists
Notes for Family Historians
War Service information
Disasters
Disaster Reports
Names of those killed
Disasters in the 1700s
Disasters in the 1800s
Disasters in the 1900s
Memorials
Awards for Gallantry
On this day ...

Links to other sites of interest
Industrial Heritage Days Out
Former www.pitwork.net web site

Index to site

Contact and address details

Share Page with Social Media

Share on Facebook

Share with Reddit

Share on Delicious


 Newspaper Articles Index Newspaper Articles 

19th April 1941, Page: 326, Column: 1

Metal Mine Development

Occasional extracts from U.S. Bureau of Mines Bulletin 419, a document of 500 pp. with 156 illustrations. Issued through the Superintendent of Documents, Washington, 60 cents net.

By Chas. F. Jackson and J. H. Hedges.

The term "mine development" is employed to designate the operations involved in preparing a mine for ore extraction. These operations include tunnelling, sinking, crosscutting, drifting, and raising.

In most mines, both exploration and development continue after ore extraction by stoping has begun and often nearly to the end of the life of the mine. Although exploration and development operations are similar, the emphasis is placed on ore finding in the former, whereas in the latter operations are directed mainly toward preparation for economical extraction and removal of the ore from the mine.

Factors to be Considered.

Among the important factors to be considered in planning mine development for economical operation are the following :—

1. Location of the main extraction opening.

2. Shaft vs. adit or tunnel development and inclined vs. vertical shafts.

3. Time required to prepare for production and anticipated maximum rate of production.

4. Level interval.

5. Level-development plans and their adaptation to the physical characteristics of the deposits and to the stoping method to be employed.

6. Life expectancy of the mine, total tonnage to be mined, and comparative costs of different development schemes.

The main opening is usually a permanent one that will be utilised throughout the life of the mine. It should, therefore, be so situated relative to the ore bodies that it will not be disturbed by ground movement caused by ore extraction and with a view to low maintenance cost.

The best position for the main opening should be determined from a consideration of the topography, the position of the mill site or point of loading ore for shipment, the feasibility of constructing a surface plant consisting of hoist house, shops, change house, and other buildings near the opening, the "centre of gravity" of the known ore, both in plan and vertically, the position of the deepest ore, and the position and adequacy of existing openings.

With shaft development, it is almost universally the practice to sink, develop, and start sloping in stages of one or a few levels at a time as new ore faces are required to maintain production and as ore continuity at greater depth is proved or indicated.

With adit development, a similar plan may be followed by driving a number of successively longer adits at successively lower elevations. When those can be driven on the vein instead of across the strike, development by this method has obvious advantages. When they must be driven in waste, the time involved in reaching the ore, the cost of so much dead work, and the uncertainties regarding persistence of the ore bodies at horizons corresponding to the elevations of the adits may minimise or eliminate entirely the advantages of adit development.

Shaft Operations.

As far as shaft operations per se are concerned, vertical shafts usually are preferred to inclined shafts. Inclined shafts must be longer to reach the same depth, hoisting speed is ordinarily slower, wear on hoisting ropes is greater, and there are usually rope idlers to install and keep in repair. In bad ground, vertical shafts usually are easier to maintain.

The size (cross-sectional dimensions) of a shaft or main haulage adit will be governed to a large extent by the anticipated rate of production. Minimum size limits are established by practical considerations even for very small production rates.

Since the main operating shaft is often the main intake airway it should be of cross-sectional area great enough to pass at moderate velocities the amount of air required to ventilate the workings adequately. This is especially important in hot, deep mines. Sometimes auxiliary shafts are provided for intake or exhaust airways.

Shafts — Size and Capacity.

The first consideration in determining the size of a shaft is the duty to be required of it. This includes the hoisting of ore and waste and the hoisting and lowering of miners, timber, rails, explosives, drill steel and drilling equipment, and other materials and supplies. If the ore hoist also handles men and materials, the time available for hoisting ore obviously is reduced. The time required for these other duties depends on a number of factors. Thus, some mines use large amounts of timber for ground support, whereas others require very little ; some use proportionately much greater quantities of drill steel than others ; some shafts have to handle large quantities of waste for stope filling while others have little or no waste to handle. In some mines, especially those operating on a large number of levels, service demands for transferring bosses from one level to another and handling equipment consume a large amount of time. In such instances it is usually economical to make the shaft large enough to accommodate a separate man and service cage, unless the production is so small that a single hoist can handle it easily and perform service duties as well. Where large amounts of mine timber must be handled through the shaft, it may be desirable to provide a separate long cage upon which loaded timber trucks can be run with the timbers lying flat. The long cage is convenient, also, for handling drill-steel trucks with the steel lying flat.

The capacity of a shaft of a given size is usually greater when skips are employed for ore and waste than when cages are used ; the net load and the ratio of net load to total load is greater, and less time usually is required for loading and dumping. Even when the ore hoist is not used for service work, it is seldom that hoisting can be conducted full time, especially if pockets of considerable capacity are not provided at each hoisting level. The provision of storage pockets of ample capacity, with measuring hoppers for loading the skips, materially promotes maximum utilisation of time and shortens the hoisting cycle, hence increases the capacity of the shaft.

Hoisting in cars on cages has advantages under certain limited conditions, notably in leasing operations where the production from each of a number of sets of leasers must be kept separate from that of the others.

Equipment.

The usual equipment for sinking at metal mines may be grouped roughly under eight classifications — drilling, blasting, mucking, hoisting, pumping, ventilation, power plant, and miscellaneous equipment, not including general shops and necessary building structures.

Drilling equipment comprises air compressors, rock drills and accessories such as hose and fittings, drill steel and steel-sharpening or grinding equipment, air and water pipes, and manifolds or headers. Rock drills for shaft work usually are of the hand-hold or "plugger" type weighing 35 to 80 pounds, although heavier machines mounted on cross bars sometimes are employed for drilling very hard ground in long narrow shafts. Modern practice calls for hollow drill steel and wet drilling, using conventional types of forged bits or detachable bits.

In the larger shafts, whore several drills are operated at a time, air hose, line-oilers, and water-hose connections to the drills usually are attached to a manifold or header. In the largest shafts there may be separate air and water headers. The header is connected to the air and drilling-water pipes in the shaft by heavy hose. It is usually raised and lowered quickly after and before drilling operations by a tugger hoist mounted on the shaft timbers 30 to 50 feet or more above the bottom of the shaft, or by chain blocks, or it may be hoisted to the surface when not in use. Those headers may be made up of pipes and fittings, or of pipes, fittings, and special castings assembled in a variety of ways. Some headers are also provided with hooks on which to hang the rock drills.

Although fuse and caps are still employed for blasting in small shafts, modern practice requires electric blasting for greater safety, for reducing the number of miss-fires, and for more precise timing of the order in which the holes will go. Electric blasting necessitates the use of either blasting machines or switches and wiring for connection to a power circuit. With blasting machines the leg wires of the detonators are connected in series, and with power-circuit firing they are connected in parallel.

Under miscellaneous equipment may be listed that required for framing shaft timber, for pouring concrete linings (concrete mixer, steel or wooden forms, and pipe, hose, or buckets for lowering concrete), and equipment for special shaft-sinking jobs. The latter category includes equipment for sinking through quicksand by the shield method or by the caisson method under air pressure, equipment for sealing off heavy flows of water in fractured rock by the cementation process, and that required for employing the freezing process. Contracting companies making a speciality of the caisson method or the freezing process are usually employed for such work.

The shield method has been used for sinking short distances through wet sand. The shoe with trailing plates extending upward and overlapping the last regular shaft set is jacked ahead and the sand is excavated inside. This shoe extends around the shaft on all four sides, the members being rigidly bolted together.

In the cementation process, quick-setting cement or cement and sand are forced by means of a plunger pump through pipes inserted in holes drilled outward from the shaft into the fractured ground.

Occasionally a stiff-leg derrick with hoist and clamshell or orange-peel bucket has been used for sinking through overburden to bedrock.


Names mentioned in this article

 

 Name  Age  Occupation  Notes 
Hedges, J. H.    U.S. Bureau of Mines  
Jackson, Chas. F.    U.S. Bureau of Mines  


 

mail
Mail:
Webmaster
Back
Back
Home
Home
Open Government Licence   Contains public sector information licensed under the Open Government Licence v3.0.

Copyright © 1999-2024 by The Durham Mining Museum and its contributors
Registered Charity No: 1110608
Page last updated: 28 Nov 2022

Privacy Policy
 
Terms & Conditions
 
Search
Search
Print
Print