22nd February 1941, Page: 266, Column: 1
The Deepening Of Maypole Shafts
Extracts from paper presented at the February meeting of the Manchester
Geological and Mining Society. Members of the Lancashire branch of the Colliery
Managers' Association were invited to the meeting.
By Peter Gaskell.
The Maypole Colliery belongs to the Wigan Coal Corporation, Limited, and the
shafts were sunk to the level of the Wigan Mines in 1895. There are two shafts,
of which the No. 1 Pit is 18 feet diameter and 623 yards deep, and the No. 2
Pit 16 feet diameter and 590 yards deep ; the No. 1 Pit is the upcast shaft.
The future life of the colliery lies in the seams below the Wigan Mines,
particularly the Yard and the Arley Seams which it was assumed would be found
at a depth of 710 and 830 yards respectively, and, in consequence, it was
decided in 1938 to deepen both shafts to the Arley Seam. It was decided to sink
from an underground level in such a manner that coal winding could proceed
without interruption in both shafts above. As the shafts were of different
diameters the plant was designed in such a manner as to make it suitable for
use at both shafts ; it was not considered practicable or desirable that both
deepenings should proceed simultaneously.
Preliminary Shaft Survey.
Before definite plans were made, a survey was conducted in each shaft. To do
this a plumb-line was suspended from the surface at the centre of the shaft and
offsets were taken at intervals to North, South, East and West from the surface
to the bottom of the shafts. This disclosed that there was an error of
8½" at the No. 1 shaft and of 14½" at the No. 2 shaft
between the centre at the surface and that at the sump. The question arose as
to whether the deepening should be along a vertical line from the centre of the
shafts at the sump or whether an attempt should be made to sink on the existing
centre line, which would mean sinking along an inclined line. To enable this to
be considered, the positions of the cages at different parts of the shafts were
plotted to cover each of the alternatives mentioned, and it was finally decided
to deepen each shaft along a vertical line from the centre of the sump.
In the plotting a vertical section of the shaft was first drawn to show the
position of the guide rods, when they were pulled over at the bottom to allow
the cages to run practically central to the existing portion of the shaft.
Cross-sections were then drawn which showed that with this arrangement the
clearances of the cages at the Arley (or bottom) level were insufficient. It
was, therefore, decided that the No. 2 Pit should be laid out for winding from
the Yard Seam which would be intersected higher up the shaft where the
clearances for the cages would be adequate, and that the guide rods would be
taken down to the sump and anchored there by weights. In this manner one set
would be available for a single deck cage, attached to a tail rope, thus
providing a second outlet from the Arley to the Yard Seams.
A plotting for the No. 1 shaft showed that there was plenty of clearance for
the cages at the Arley level, as, although the centres of the cages are 8'
wider than those at No. 2 Pit, the amount of the shaft out of vertical was not
too great, and the extra diameter of the shaft, with the same size cage, was an
advantage. The guide rods, however, had to be pulled over more than was
necessary on the above consideration alone owing to the existence of a bulge
just above the Wigan Mines inset. This bulge is definitely known to have been
caused by the flooding of the shafts after the explosion of 1908.
The plotting, even with the rods pulled over the additional amount, showed that
there was ample clearance for the cages, and it was decided to use No. 1 Pit as
the main winding shaft from the Arley Seam.
The error from the vertical in the shafts has been the subject of much
interesting discussion. It has been said to be due to ground movement
subsequent to the completion of the shafts, caused by the faulty nature of the
ground and the fairly steep gradients which attain a maximum of 1 in 2½ in
the vicinity of the shafts. Against this, information obtained from men who
worked in the shafts when they were being sunk indicates that a portion of the
shafts was sunk by the side lines alone. This shows the importance of the
constant use of the centre line, not only in fixing the curbs but also during
the skeleton sinking operations and whilst the bricking is being done. During
the present deepening it was the rule to check from the centre line at least
once every twenty-four hours whilst sinking, and at least once every shift
whilst bricking. Any slight error detected at such times could be rectified
immediately.
General Preliminary Considerations.
Sumps. — It was fortunate that the sumps at both the shafts were
deep enough to allow for a rearrangement of the existing guide rod weights and
the installation of fixed protection scaffolds. The sump at No. 1 Pit was 54
feet deep and that at No. 2 Pit 40 feet deep. The brickwork in both cases was
in good condition.
The Wigan Mines mouthing at No. 1 Pit is about 100 feet deeper than that at No.
2 Pit, and this proved a great advantage in setting out the whole of the
preparatory work for the deepening.
Disposal of the Debris from the Deepening. — Before the sinking
commenced, large quantities of dirt had been sent down the No. 2 Pit for
complete stowage in the Bickershaw 7 feet Seam. Some of this dirt came from the
workings in No. 1 Pit. It was, therefore, decided that the majority of the
sinking dirt should be disposed of in this manner, and a layout was planned
such that the dirt from both deepenings should intermix with the normal traffic
at the Wigan Mines mouthing at the No. 1 Pit and be wound thence to the
surface. To enable this to be done successfully without interfering with the
coal winding, it was essential that good standing-room should be provided for
the dirt.
Ultimate Coal Winding Arrangements. — Since it had been decided
that the No. 1 Pit would eventually be the main coal winding shaft for the bulk
of the output which would be obtained from the Arley Seam, it followed that the
diminishing output from the present area at both places could best be dealt
with at No. 2 Pit. When the No. 1 Pit is changed over to wind from the Arley
level, the No. 2 Pit will be required for some considerable time to deal with
the coal from the present Wigan and Pemberton Seams. To enable this to be done
expeditiously a tunnel is being driven connecting the Wigan to the Pemberton
Seams so that all the coal can be wound from one level.
General Winding Layout for the Sinkings. — This was the same at
both shafts and comprised a winding engine-house constructed just below the
sump of the existing shaft with a decking level some 45-50 feet below. The
distance of 45-50 feet provided clearance for the detaching hook, chase chains,
etc., when the hoppit was at its highest point above the tipping doors.
Deepening of No. 2 Pit.
The decision to deepen No. 2 Pit first was made after the arrangement of
tunnels, engine-houses and decking levels had been planned, full advantage
being taken of the difference in levels of the bottom of the two pits.
Fast Scaffold. — A fast scaffold was built at a distance of 3 feet
from the bottom ring of the sump. This was made sufficiently strong to protect
the workmen underneath it when the sinking commenced, and sufficiently airtight
to prevent the air short-circuiting to the other pit. At a later date 50 tubs
of clay was tamped tightly over this scaffold.
The girders of the scaffold were installed in a definite position relative to
the centre line of the shaft, and parallel to centre line of the cage, so that
lines could be fixed from them to set out all the mouthings below. When the
preparatory sinking was completed a centre line machine was fixed below the
decking doors, and set in position from points on the scaffold girders above.
By setting the girders thus a useful check was provided throughout the
deepening.
From the back of No. 1 Pit a tunnel was driven, rising so as to gain 45 feet
when it connected with the No. 2 shaft. The final connection to the shaft was
the level engine-house, and this was constructed of 14' X 14' arches with
brickwork in between. The top of this engine-house, when the connection was
made, was just below the cast-iron bricking ring at the sump. The entrance to
this engine-house was at the back and consisted of the rising tunnel previously
mentioned, which was supported by 10' x 7' steel arches.
When the engine-house was completed the ground in front of it in the shaft was
taken out to form the first stage of the deepening. This was supported with
temporary sinking rings and backing deals, the former being held in position
across the open end of the engine-house by a framework of strong balks.
The excavation of this ground was continued for a distance of 5 feet below the
floor of the engine-house, at which point a concrete crib, was put in position.
The length was then bricked up to the old sump. During the course of this
brickwork the entrance to the engine-house was secured and preparations were
made for the girder frames for the winding and the scaffold rope pulleys, and
for the girder framework to carry the bell for the detaching hook.
A further 28 feet was then sunk from this level, the dirt being removed by
casting it from scaffold to scaffold because neither the temporary nor
permanent winding engine was yet in position. This was the extent of the
sinking from the engine-house level, and it was left supported by the temporary
supports until such time as a connection could be made to it from below.
The capstan engine for operating the bricking scaffold was compressed-air
driven, with two 8' cylinders and 12' stroke. The two drums were each 3 feet
diameter and were driven through bevel and worm gearing. Each drum was fitted
with a strong band brake and the whole machine was self-contained on a channel
iron frame.
The arrangements for dealing with the debris and the water wound from the
shafts may be of particular interest because the method of tipping the debris
on to a chute formed by sloping doors as commonly used on the surface in modern
sinkings was employed, as far as the writer is aware, for the first time at a
sinking from an underground level.
The arrangement consisted of a timber frame fitted with flat hinged doors at
the landing level. These doors were operated by weights attached to ropes
passing over pulleys at each side of the inset. Sliding hinged rails were
fitted to take a bogie carrying the hoppit. On the frame vertical posts were
erected which carried the frame for the inverted "V"-shaped tipping
doors and platforms above. The ends of this top frame were also securely
fastened to channel iron girders into the inset walls at each side of the
shaft. The "V"-shaped doors were operated by shafts and levers fitted
with balance weights. The door on the discharge side was fitted with plates to
form a chute which delivered the debris to another chute which was used as a
hopper from which the boxes were filled. The hinged chute was fitted with ropes
so that it could be lifted out of the way when bricking was being done to allow
for the passage of materials.
It should be noted that although the decking plant was first erected in the 16
feet diameter shaft, it was so constructed that it could be adapted later for
the sinking of the 18 feet diameter shaft.
The bricking scaffold was constructed of 12" x 5" and 8" x
6" rolled steel joists, made into a frame and covered with 4" planks.
Doors were arranged in the centre for the passage of the hoppit. It was
suspended on two sets of chains and ropes ; the latter served as guide rods for
the rider. The scaffold was constructed so that by slight modification it could
be adapted for the larger diameter at No. 1 Pit.
Deepening of No. 1 Shaft.
As in No. 2 Pit the first operation was to build a fast scaffold near to the
sump, but in this case four rectangular openings were left through it for
ventilation purposes. In general the arrangements were similar to those adopted
at the No. 2 shaft. The engine-house was constructed to the same drawings used
at the No. 2 shaft, the only difference being that the entrance was at the
front where previously it had been at the back.
Construction of Mouthing. — As in all other cases where mouthings
were to be constructed, the ground in the vicinity of the mouthing was
excavated to an increased diameter to allow the brickwork to be increased from
9 inches to 2 feet in thickness. This enabled the entrance to the mouthing to
be formed by erecting four steel arches and the compound girders for the
mouthing during the process of bricking.
"C" Tunnel Continued. — When this length had been
completed the men were transferred back to "C" tunnel which was then
driven forward at a continued dip of 1 in 2¼ for a length which enabled a
level connection to be made to the position where the inset had already been
formed in the shaft. As previously the inset was made on both sides of the
shaft, but in this case the length used for storage purposes and for the
accommodation of the balance weights for the shaft doors was 21 feet deep. The
facilities provided by having this storage space at both decking levels more
than compensated for the expenditure involved.
After the completion of this part of the work, the sinking was continued for a
further 21 feet, and left on the temporary supports so that the tipping plant
could be erected clear of shots when the sinking proper was commenced, giving a
total depth of 36 feet below the new decking level at "C" tunnel.
Change-over from No. 2 to No. 1 Pit. — This involved the change
from a hoppit to a single-deck cage and the substitution of a 150 h.p. winding
engine for the 250 h.p. winder at No. 2 Pit and the transference of the 250
h.p. winder and the complete chute and decking tipping arrangements from No. 2
Pit to No. 1 Pit.
The top doors of the chute and all the material connected with this structure
were first dismantled and removed to the bottom of "C" tunnel. A
"flat" was then formed in "C" tunnel opposite to the
entrance to the engine-house to enable the heavy plant to be transferred from
the steep tunnel to the level entrance. In this way the erection of the tipping
plant and winding engine could proceed simultaneously.
The transference of the 250 h.p. winders from No. 2 Pit was delayed
sufficiently long to enable them to be utilised in the installation of four
guide rods. These guide rods were for the single-deck cage which was used
whilst driving the new tunnels in the deepened portion of the shaft. The
winders and capstan engines were then dismantled and removed to No. 1 Pit. This
work was facilitated because the entrance to the No. 2 engine-house was at the
back whilst that of the No. 1 engine-house was at the front, thus each part of
the gear as it was dismantled could immediately be removed and assembled in its
correct position in the new engine-house.
The complete change-over including the installation of the guide rods was
completed in eleven days and the deepening of this shaft was then commenced.
The bricking scaffold was adapted to suit the 18' diameter shaft and installed
when the first length was ready for bricking.
Whilst the contractors were deepening the No. 1 Pit, two levels were driven in
the Yard and the Arley Seams to make contact with the No. 1 Pit as it was sunk.
These connections served for ventilating purposes.
Conclusion.
The whole of the work proceeded according to plan and would have been completed
to schedule if labour difficulties due to the war had not arisen during the
latter months. The shortage of sinkers at one period caused the sinking time to
be reduced from three to two shifts per day.
At both pits provision was made for ample standing room for boxes, and the
importance of this cannot be too greatly stressed. If an underground sinking is
to proceed successfully the stocking of materials is also important; the
backing deals, for example, were placed on girders fixed across the roadways in
suitable positions. Provision was also made to have an ample water supply for
concrete mixing and a small compressed-air concrete mixer was provided at the
decking levels when the curbs were being put in position.
In conclusion I would like to express my thanks to the Wigan Coal Corporation,
Limited, for permission to read this paper and to the various members of the
staff who have helped in its preparation.
 |
 |
|