Logo Museum
Museum
Friends of Durham Mining Museum
Events Calendar
e-Books and Books for sale
Photograph Gallery
Document Archive
Main Document Archive
Newspaper Articles
Articles by date
Articles by colliery
Personal name index
Local Record Extracts
D.M.A. Document Archive
Transactions of I.M.E.
Miners' Welfare
N.C.B. Archive
The Colliery Engineer
The Colliery Guardian
Mine & Quarry Engineering
Mining Journal
The Science and Art of Mining
Coal Magazine
Coal News
Coke and Gas
Master Name Index
What's new in the site
Mining
Mining History
Colliery Index
Colliery Maps
Company Overviews
Who's Who
Mineral Information
Managers Certificates
Educational Material
Bibliography
Statistics
Workers/Employee Lists
Notes for Family Historians
War Service information
Disasters
Disaster Reports
Names of those killed
Disasters in the 1700s
Disasters in the 1800s
Disasters in the 1900s
Memorials
Awards for Gallantry
On this day ...

Links to other sites of interest
Industrial Heritage Days Out
Former www.pitwork.net web site

Index to site

Contact and address details

Share Page with Social Media

Share on Facebook

Share with Reddit

Share on Delicious


 Newspaper Articles Index Newspaper Articles 

22nd February 1941, Page: 266, Column: 1

The Deepening Of Maypole Shafts

Extracts from paper presented at the February meeting of the Manchester Geological and Mining Society. Members of the Lancashire branch of the Colliery Managers' Association were invited to the meeting.

By Peter Gaskell.

The Maypole Colliery belongs to the Wigan Coal Corporation, Limited, and the shafts were sunk to the level of the Wigan Mines in 1895. There are two shafts, of which the No. 1 Pit is 18 feet diameter and 623 yards deep, and the No. 2 Pit 16 feet diameter and 590 yards deep ; the No. 1 Pit is the upcast shaft.

The future life of the colliery lies in the seams below the Wigan Mines, particularly the Yard and the Arley Seams which it was assumed would be found at a depth of 710 and 830 yards respectively, and, in consequence, it was decided in 1938 to deepen both shafts to the Arley Seam. It was decided to sink from an underground level in such a manner that coal winding could proceed without interruption in both shafts above. As the shafts were of different diameters the plant was designed in such a manner as to make it suitable for use at both shafts ; it was not considered practicable or desirable that both deepenings should proceed simultaneously.

Preliminary Shaft Survey.

Before definite plans were made, a survey was conducted in each shaft. To do this a plumb-line was suspended from the surface at the centre of the shaft and offsets were taken at intervals to North, South, East and West from the surface to the bottom of the shafts. This disclosed that there was an error of 8½" at the No. 1 shaft and of 14½" at the No. 2 shaft between the centre at the surface and that at the sump. The question arose as to whether the deepening should be along a vertical line from the centre of the shafts at the sump or whether an attempt should be made to sink on the existing centre line, which would mean sinking along an inclined line. To enable this to be considered, the positions of the cages at different parts of the shafts were plotted to cover each of the alternatives mentioned, and it was finally decided to deepen each shaft along a vertical line from the centre of the sump.

In the plotting a vertical section of the shaft was first drawn to show the position of the guide rods, when they were pulled over at the bottom to allow the cages to run practically central to the existing portion of the shaft. Cross-sections were then drawn which showed that with this arrangement the clearances of the cages at the Arley (or bottom) level were insufficient. It was, therefore, decided that the No. 2 Pit should be laid out for winding from the Yard Seam which would be intersected higher up the shaft where the clearances for the cages would be adequate, and that the guide rods would be taken down to the sump and anchored there by weights. In this manner one set would be available for a single deck cage, attached to a tail rope, thus providing a second outlet from the Arley to the Yard Seams.

A plotting for the No. 1 shaft showed that there was plenty of clearance for the cages at the Arley level, as, although the centres of the cages are 8' wider than those at No. 2 Pit, the amount of the shaft out of vertical was not too great, and the extra diameter of the shaft, with the same size cage, was an advantage. The guide rods, however, had to be pulled over more than was necessary on the above consideration alone owing to the existence of a bulge just above the Wigan Mines inset. This bulge is definitely known to have been caused by the flooding of the shafts after the explosion of 1908.

The plotting, even with the rods pulled over the additional amount, showed that there was ample clearance for the cages, and it was decided to use No. 1 Pit as the main winding shaft from the Arley Seam.

The error from the vertical in the shafts has been the subject of much interesting discussion. It has been said to be due to ground movement subsequent to the completion of the shafts, caused by the faulty nature of the ground and the fairly steep gradients which attain a maximum of 1 in 2½ in the vicinity of the shafts. Against this, information obtained from men who worked in the shafts when they were being sunk indicates that a portion of the shafts was sunk by the side lines alone. This shows the importance of the constant use of the centre line, not only in fixing the curbs but also during the skeleton sinking operations and whilst the bricking is being done. During the present deepening it was the rule to check from the centre line at least once every twenty-four hours whilst sinking, and at least once every shift whilst bricking. Any slight error detected at such times could be rectified immediately.

General Preliminary Considerations.

Sumps. — It was fortunate that the sumps at both the shafts were deep enough to allow for a rearrangement of the existing guide rod weights and the installation of fixed protection scaffolds. The sump at No. 1 Pit was 54 feet deep and that at No. 2 Pit 40 feet deep. The brickwork in both cases was in good condition.

The Wigan Mines mouthing at No. 1 Pit is about 100 feet deeper than that at No. 2 Pit, and this proved a great advantage in setting out the whole of the preparatory work for the deepening.

Disposal of the Debris from the Deepening. — Before the sinking commenced, large quantities of dirt had been sent down the No. 2 Pit for complete stowage in the Bickershaw 7 feet Seam. Some of this dirt came from the workings in No. 1 Pit. It was, therefore, decided that the majority of the sinking dirt should be disposed of in this manner, and a layout was planned such that the dirt from both deepenings should intermix with the normal traffic at the Wigan Mines mouthing at the No. 1 Pit and be wound thence to the surface. To enable this to be done successfully without interfering with the coal winding, it was essential that good standing-room should be provided for the dirt.

Ultimate Coal Winding Arrangements. — Since it had been decided that the No. 1 Pit would eventually be the main coal winding shaft for the bulk of the output which would be obtained from the Arley Seam, it followed that the diminishing output from the present area at both places could best be dealt with at No. 2 Pit. When the No. 1 Pit is changed over to wind from the Arley level, the No. 2 Pit will be required for some considerable time to deal with the coal from the present Wigan and Pemberton Seams. To enable this to be done expeditiously a tunnel is being driven connecting the Wigan to the Pemberton Seams so that all the coal can be wound from one level.

General Winding Layout for the Sinkings. — This was the same at both shafts and comprised a winding engine-house constructed just below the sump of the existing shaft with a decking level some 45-50 feet below. The distance of 45-50 feet provided clearance for the detaching hook, chase chains, etc., when the hoppit was at its highest point above the tipping doors.

Deepening of No. 2 Pit.

The decision to deepen No. 2 Pit first was made after the arrangement of tunnels, engine-houses and decking levels had been planned, full advantage being taken of the difference in levels of the bottom of the two pits.

Fast Scaffold. — A fast scaffold was built at a distance of 3 feet from the bottom ring of the sump. This was made sufficiently strong to protect the workmen underneath it when the sinking commenced, and sufficiently airtight to prevent the air short-circuiting to the other pit. At a later date 50 tubs of clay was tamped tightly over this scaffold.

The girders of the scaffold were installed in a definite position relative to the centre line of the shaft, and parallel to centre line of the cage, so that lines could be fixed from them to set out all the mouthings below. When the preparatory sinking was completed a centre line machine was fixed below the decking doors, and set in position from points on the scaffold girders above. By setting the girders thus a useful check was provided throughout the deepening.

From the back of No. 1 Pit a tunnel was driven, rising so as to gain 45 feet when it connected with the No. 2 shaft. The final connection to the shaft was the level engine-house, and this was constructed of 14' X 14' arches with brickwork in between. The top of this engine-house, when the connection was made, was just below the cast-iron bricking ring at the sump. The entrance to this engine-house was at the back and consisted of the rising tunnel previously mentioned, which was supported by 10' x 7' steel arches.

When the engine-house was completed the ground in front of it in the shaft was taken out to form the first stage of the deepening. This was supported with temporary sinking rings and backing deals, the former being held in position across the open end of the engine-house by a framework of strong balks.

The excavation of this ground was continued for a distance of 5 feet below the floor of the engine-house, at which point a concrete crib, was put in position. The length was then bricked up to the old sump. During the course of this brickwork the entrance to the engine-house was secured and preparations were made for the girder frames for the winding and the scaffold rope pulleys, and for the girder framework to carry the bell for the detaching hook.

A further 28 feet was then sunk from this level, the dirt being removed by casting it from scaffold to scaffold because neither the temporary nor permanent winding engine was yet in position. This was the extent of the sinking from the engine-house level, and it was left supported by the temporary supports until such time as a connection could be made to it from below.

The capstan engine for operating the bricking scaffold was compressed-air driven, with two 8' cylinders and 12' stroke. The two drums were each 3 feet diameter and were driven through bevel and worm gearing. Each drum was fitted with a strong band brake and the whole machine was self-contained on a channel iron frame.

The arrangements for dealing with the debris and the water wound from the shafts may be of particular interest because the method of tipping the debris on to a chute formed by sloping doors as commonly used on the surface in modern sinkings was employed, as far as the writer is aware, for the first time at a sinking from an underground level.

The arrangement consisted of a timber frame fitted with flat hinged doors at the landing level. These doors were operated by weights attached to ropes passing over pulleys at each side of the inset. Sliding hinged rails were fitted to take a bogie carrying the hoppit. On the frame vertical posts were erected which carried the frame for the inverted "V"-shaped tipping doors and platforms above. The ends of this top frame were also securely fastened to channel iron girders into the inset walls at each side of the shaft. The "V"-shaped doors were operated by shafts and levers fitted with balance weights. The door on the discharge side was fitted with plates to form a chute which delivered the debris to another chute which was used as a hopper from which the boxes were filled. The hinged chute was fitted with ropes so that it could be lifted out of the way when bricking was being done to allow for the passage of materials.

It should be noted that although the decking plant was first erected in the 16 feet diameter shaft, it was so constructed that it could be adapted later for the sinking of the 18 feet diameter shaft.

The bricking scaffold was constructed of 12" x 5" and 8" x 6" rolled steel joists, made into a frame and covered with 4" planks. Doors were arranged in the centre for the passage of the hoppit. It was suspended on two sets of chains and ropes ; the latter served as guide rods for the rider. The scaffold was constructed so that by slight modification it could be adapted for the larger diameter at No. 1 Pit.

Deepening of No. 1 Shaft.

As in No. 2 Pit the first operation was to build a fast scaffold near to the sump, but in this case four rectangular openings were left through it for ventilation purposes. In general the arrangements were similar to those adopted at the No. 2 shaft. The engine-house was constructed to the same drawings used at the No. 2 shaft, the only difference being that the entrance was at the front where previously it had been at the back.

Construction of Mouthing. — As in all other cases where mouthings were to be constructed, the ground in the vicinity of the mouthing was excavated to an increased diameter to allow the brickwork to be increased from 9 inches to 2 feet in thickness. This enabled the entrance to the mouthing to be formed by erecting four steel arches and the compound girders for the mouthing during the process of bricking.

"C" Tunnel Continued. — When this length had been completed the men were transferred back to "C" tunnel which was then driven forward at a continued dip of 1 in 2¼ for a length which enabled a level connection to be made to the position where the inset had already been formed in the shaft. As previously the inset was made on both sides of the shaft, but in this case the length used for storage purposes and for the accommodation of the balance weights for the shaft doors was 21 feet deep. The facilities provided by having this storage space at both decking levels more than compensated for the expenditure involved.

After the completion of this part of the work, the sinking was continued for a further 21 feet, and left on the temporary supports so that the tipping plant could be erected clear of shots when the sinking proper was commenced, giving a total depth of 36 feet below the new decking level at "C" tunnel.

Change-over from No. 2 to No. 1 Pit. — This involved the change from a hoppit to a single-deck cage and the substitution of a 150 h.p. winding engine for the 250 h.p. winder at No. 2 Pit and the transference of the 250 h.p. winder and the complete chute and decking tipping arrangements from No. 2 Pit to No. 1 Pit.

The top doors of the chute and all the material connected with this structure were first dismantled and removed to the bottom of "C" tunnel. A "flat" was then formed in "C" tunnel opposite to the entrance to the engine-house to enable the heavy plant to be transferred from the steep tunnel to the level entrance. In this way the erection of the tipping plant and winding engine could proceed simultaneously.

The transference of the 250 h.p. winders from No. 2 Pit was delayed sufficiently long to enable them to be utilised in the installation of four guide rods. These guide rods were for the single-deck cage which was used whilst driving the new tunnels in the deepened portion of the shaft. The winders and capstan engines were then dismantled and removed to No. 1 Pit. This work was facilitated because the entrance to the No. 2 engine-house was at the back whilst that of the No. 1 engine-house was at the front, thus each part of the gear as it was dismantled could immediately be removed and assembled in its correct position in the new engine-house.

The complete change-over including the installation of the guide rods was completed in eleven days and the deepening of this shaft was then commenced. The bricking scaffold was adapted to suit the 18' diameter shaft and installed when the first length was ready for bricking.

Whilst the contractors were deepening the No. 1 Pit, two levels were driven in the Yard and the Arley Seams to make contact with the No. 1 Pit as it was sunk. These connections served for ventilating purposes.

Conclusion.

The whole of the work proceeded according to plan and would have been completed to schedule if labour difficulties due to the war had not arisen during the latter months. The shortage of sinkers at one period caused the sinking time to be reduced from three to two shifts per day.

At both pits provision was made for ample standing room for boxes, and the importance of this cannot be too greatly stressed. If an underground sinking is to proceed successfully the stocking of materials is also important; the backing deals, for example, were placed on girders fixed across the roadways in suitable positions. Provision was also made to have an ample water supply for concrete mixing and a small compressed-air concrete mixer was provided at the decking levels when the curbs were being put in position.

In conclusion I would like to express my thanks to the Wigan Coal Corporation, Limited, for permission to read this paper and to the various members of the staff who have helped in its preparation.


Names mentioned in this article

 

 Name  Age  Occupation  Notes 
Gaskell, Peter      


 

mail
Mail:
Webmaster
Back
Back
Home
Home
Open Government Licence   Contains public sector information licensed under the Open Government Licence v3.0.

Copyright © 1999-2024 by The Durham Mining Museum and its contributors
Registered Charity No: 1110608
Page last updated: 28 Nov 2022

Privacy Policy
 
Terms & Conditions
 
Search
Search
Print
Print