Logo Museum
Museum
Friends of Durham Mining Museum
Events Calendar
e-Books and Books for sale
Photograph Gallery
Document Archive
Main Document Archive
Newspaper Articles
Articles by date
Articles by colliery
Personal name index
Local Record Extracts
D.M.A. Document Archive
Transactions of I.M.E.
Miners' Welfare
N.C.B. Archive
The Colliery Engineer
The Colliery Guardian
Mine & Quarry Engineering
Mining Journal
The Science and Art of Mining
Coal Magazine
Coal News
Coke and Gas
Master Name Index
What's new in the site
Mining
Mining History
Colliery Index
Colliery Maps
Company Overviews
Who's Who
Mineral Information
Managers Certificates
Educational Material
Bibliography
Statistics
Workers/Employee Lists
Notes for Family Historians
War Service information
Disasters
Disaster Reports
Names of those killed
Disasters in the 1700s
Disasters in the 1800s
Disasters in the 1900s
Memorials
Awards for Gallantry
On this day ...

Links to other sites of interest
Industrial Heritage Days Out
Former www.pitwork.net web site

Index to site

Contact and address details

Share Page with Social Media

Share on Facebook

Share with Reddit

Share on Delicious


 Newspaper Articles Index Newspaper Articles 

25th January 1941, Page: 231, Column: 1

Roof Caving

A paper prepared by Mr. J. R. Jenkins, B.Sc, for the South Staffordshire and Warwickshire Institute of Mining and published in the Transactions of the Institute of Engineers, on "Some Notes on the Science of Roof Caving and its Practice on Longwall Machine Faces," had for its purpose to suggest that where geological and other conditions are suitable a system of strip packing and caving of intervening wastes, or of complete caving without strip packs, does more to bring about requirements than any other known system of longwall roof control. Briefly, this system requires the building of substantial strip packs, spaced wide enough apart to induce the immediate roof to collapse or cave in the wastes, behind a row of rigid supports set as near the face as possible. These supports form a "breaker row," and should be placed immediately behind the conveyor. If caving is effected between waste packs, the system is called "semi-caving" ; the term "complete caving" is applied when conditions allow it to be done along the whole length of face from road-side pack to road-side pack. A breaker row can be composed of stout wooden props, releasable steel props, or rigid chocks.

Roof control depends mainly on substantial systematic and uniform support of the "controllable area" (the area of subsiding roof in the wastes behind the face conveyors). The more efficient the packing or the greater the support offered by the fallen material in the wastes, the less will be the movement and the greater will be the control of the main body of roof. The downward movement of the superincumbent mass of strata must be considered irresistible; and it is only capable of being controlled by the solid coal, the packs and the debris fallen in the wastes. The function of the temporary face supports, therefore, is to control a comparatively small thickness of nether roof and to reinforce its self-supporting capacity. In short, the method of roof caving employs forces induced by ruining in the roof strata to pack the wastes, giving results which far exceed those of the most expert packer.

Experience has shown that the best results from caving from the safety and economic standpoints are obtained when the length of sub-cantilever is limited to a specified maximum span. Although no hard-and-fast rule can be applied, this is usually 12 to 13 feet with massive rock roofs and 14 to 15 feet with more yielding materials, such as shales and coals. With caving, as with other systems of roof control, however rigid is made the breaker row, a limited minimum degree of controlled subsidence will always take place.

Chocking Systems.

In the light of some points passed in review Mr. Jenkins concludes that under suitable conditions the most rigid temporary face support can be gained by the use of steel props and bars with hardwood lids in conjunction with systematically spaced hardwood chocks. Sufficiently thick lids must be provided to enable the props to permit the same height reduction as the chocks, thereby subjecting the roof to a uniform support. The chocks must be set directly between roof and floor and driven up tightly by double-wedging with long hardwood wedges, in order to relieve the steel props of excessive weight and facilitate their withdrawal.

Chock pieces should be of the largest cross-sectional dimensions consistent with ease of handling. Chocking systems should be so devised that the chocks fit in between the props and bars of the existing propping system, and they must be spaced sufficiently close together to prevent crushing of the hardwood pieces. A chock built of 5-inch section oak will theoretically support 200 tons before failure, whereas one built of 6-inch oak will carry 288 tons. In general practice, therefore, 6-inch square oak pieces are used 1½ to 4 feet in length, a chock spacing of 4½ to 9-foot centres serving the majority of conditions. If there is a dirt band in the seam, chocks are generally set a little wider apart to allow adequate spaces between them for the dirt to be gobbed. A mechanical chock-release device should always be incorporated in such chocks to facilitate rapid and safe withdrawal. Recent developments in the practice of the caving system have followed from the effective employment of such devices.

As broken material occupies more space than solid material, caving of the wastes results in their becoming completely filled with fallen debris. Upon this caved material the higher beds above the nether roof subside. Shale roofs in deep mines will break up along planes of induced cleavage into suitably-sized fragments.

General Conclusions.

In his general statement of conclusions arrived at Mr. Jenkins says :—

With a longwall machine face advancing uniformly on a time cycle basis there is a sort of pressure arch in the immediate roof strata at right angles to the face. Its front abutment is well in advance over the solid coal, and the consolidated packs in the settled area behind the face form its back abutment. The downward movement of the superincumbent strata must be considered irresistible and capable of control only by the solid coal, the packs, and the debris fallen in the wastes.

With controlled and systematic roof caving the Immediate roof is broken down in the wastes by beam action, and as broken material occupies 25 to 50 per cent. more space than solid stone, wastes become completely filled. This consolidated fallen debris offers a substantial and uniform support to the higher beds, and in cases where strip packs are built gives additional support in the intervening wastes. This system brings about effective roof control, as the movement of the higher beds over the controllable area is greatly reduced. Only a small ledge or sub-cantilever of nether roof requires to be carried over the working area, and such a substantial support is offered to the higher beds that they are able to span relatively unbroken between the two abutments, this bridging effect serving to "protect" the sub-cantilever. With roof caving the function of the temporary face supports is to control a comparatively small sub-cantilever and to provide a sufficiently rigid fulcrum against which the. immediate roof can be broken.

Roof caving is the oldest method of roof control. The modern technique of controlled caving has been evolved through experience to meet the changed conditions of intensive longwall machine mining. The introduction of such materials as hardwood and steel allows the rigidity of face supports to be increased well within their load carrying capacity and the use of mechanical chock release devices now ensures that the drawing off operation can be effected as rapidly as any other operation in the 24-hour cycle.

Roof caving can be applied to the majority of seams in this country with a marked improvement in safety and economy of working. Like any system of roof control, its application is limited, and certain roofs are so difficult to control that efficient mechanical solid packing may be the only solution. This method also applies to special cases, as when mining under waterlogged ground or under built-up areas at shallow depths. Good conditions at the coal face can be made by the methods of working and roof control employed, and it would appear that roof caving is most likely to provide better conditions than any other system.


Names mentioned in this article

 

 Name  Age  Occupation  Notes 
Jenkins, J. R.      


 

mail
Mail:
Webmaster
Back
Back
Home
Home
Open Government Licence   Contains public sector information licensed under the Open Government Licence v3.0.

Copyright © 1999-2024 by The Durham Mining Museum and its contributors
Registered Charity No: 1110608
Page last updated: 28 Nov 2022

Privacy Policy
 
Terms & Conditions
 
Search
Search
Print
Print