24th February 1940, Page: 268, Column: 2
Winding From Intermediate Level
When the modernisation of Wern Tarw Colliery was undertaken
recently, Mr. F. B. Kerbridge explained in a paper on "Winding
from an Intermediate Level in a Vertical Shaft," read before the
South Wales Institute of Engineers, it was desired to provide for
an output of possibly 4-500 tons per day from the Pentre seam
and 2-250 tons per day from the Six Feet seam, as compared with
200 tons and 50 tons per day respectively then being raised.
Installation of a new winding engine was necessary as part of
the complete electrification of the colliery, which bad been decided
upon, and a double drum unit by the Uskside Engineering Co.
was selected with one drum loose to provide for adjustment of
the winding ropes to enable both cages to serve either the Pentre
or Six Feet level.
In the shaft, the south side of the pit was opened up at the
Pentre level, and a separate road was made for empty trains to
provide a run through the cages. To accommodate the cages
at the Pentre level it was decided, after rejecting several alternatives,
to install a sliding stage capable of being placed across
the shaft, with suitable safeguards, and converting the landing
virtually into a pit bottom when required.
The stage itself consists essentially of four heavy R.S. joists,
suitably braced, travelling on cast-iron rollers mounted on shafts
running in roller bearings and weighted at one end to prevent
overbalance when crossing the pit. The stage is moved by
haulage ropes on drums operated by a motor-driven worm gear
with centrifugal clutch and magnetic brake. The movement of
the stage is controlled primarily from a contactor panel at the
surface placed close to the winding engineman's platform and
provided with press button starting switches for the driving motor
and an emergency stop switch. Two signal lights are mounted
on the panel to show whether the stage is withdrawn or across
the pit. The panel is energised from the surface 440-volt a.c.
system and a six-core cable is run down the shaft to the Pentre
level for the stage motor and limit switch circuits.
Mr. Kerbridge described the sequence of operations. It takes
less than three minutes to complete the operations in practice,
and no difficulty whatever has been experienced in getting the
change from one level to another made by the winders and hitchers,
who cannot, in fact, complete the operations otherwise than
correctly. Concluding his paper the Author said the rate of
winding from the Pentre level has been increased from 40 to 100
trams per hour by the installation, which has now been in operation
for eight months, during which it has given no trouble either in
operation or maintenance.
 |
 |
|