17th June 1939, Page: 392, Column: 2
Cost Of Coal Treatment
Discussing "Modern Tendencies in Coal Preparation" before
the South Wales Institute of Engineers Mr. W. A. T. McCarthy,
A.M.I.Mech.E., on the question of cost of coal treatment said:
The over-all cost of handling, screening and washing the output
of a colliery is very variable. However, as an indication as to
what might be expected, the writer has prepared a cost for the
following hypothetical plant, based on his experience in South
Wales. An output of 8,000 tons per week has been assumed,
with a peak output of 1,500 tons per day. The large and cobbles
(35 per cent. of the output) were to be screened and hand picked,
while all the coal below say 3 inches would be washed. Provision
is to be made for breaking either the whole or part of the large coal
to cobble size; the broken coal would, however, not be washed
but would be classified and loaded dry.
The cost of installing, operating and maintaining the screening
plant (including creepers) worked out to 3.04d. per ton.
The washery would be capable of dealing with 65 per cent.
of 1,500 tons per day of seven hours, i.e., 915 tons per day, say
150 tons per hour to allow for the peak hourly throughput.
Provision would be made for de-dusting the coal prior to washing
and loading belts would be provided for the nut sizes. Washing
cost per ton 4.90d.
The total cost of handling and treating the coal in such a plant
is, therefore, of the order of 8d. per ton. These figures do not,
of course, take into account the loss of vend due to the rejection
of high ash material in the screening plant and washery, which
represents by far the biggest item of all. In order to predetermine
the total cost of treatment the physical constitution of the coal
should be investigated by the usual float and sink determinations,
when the yield for any particular quality of washed coal can be
quickly and easily determined.
 |
 |
|