Australia's Mechanised Colliery
System of Loading
The first Australian coal mine to be completely mechanised was
the Wallarah Colliery, situated at Catherine Hill Bay, New South
Wales, under the management of Mr. William Hudson. The
change-over took place in June last year, and all coal is now
undercut by machines — arcwall and shortwall respectively.
After being shot down the coal is handled by Mayor and Coulson
underground Joy loaders, which are of the crawler type.
The coal seam is 6 feet 6 inches thick, worked in 10-yard bords
specially to allow two sets of lines with ample room in the centre
of the roads for convenient travelling in and out of the coal-cutters
and Joy loaders. In practice, the cutting machines undercut
the coal on the bottom for a depth of 6 feet to 7 feet. This
operation is followed by drilling the shot-holes with electric
drilling machines; the holes are then loaded with the required
amount of explosive and fired by the shot-firer.
The system of loading has been planned, as pointed out in the
CHEMICAL ENGINEERING AND MINING REVIEW, so as to need little
modification for production up to 1,300 tons of coal per day. The
loader enters the bord along the centre of the road and operates
at the centre of the coal face. A good supply of empty skips is
drawn along and stationed on one side of the road, the loader meanwhile
filling skips on the opposite side. As each skip is filed it is
immediately replaced by an empty skip run from the opposite
side of the road on rails by the aid of steel turntables. When
the loader is operating, the two gathering-arms, working alternately,
sweep the coal on to a conveyor which carries and delivers
it into a skip. Each gathering-arm is driven by independent
gears on either side of the foot sprocket of the conveyor chain,
strain being prevented by the slipping clutch of the conveyor,
which has a universally jointed centre-drive chain running over
both front and rear, thus allowing slewing of the rear conveyor
as required to suit the position of the skip. The chain is driven
through a multiple disc clutch which protects the mechanism
from severe overload. The rear conveyor can be swung through
45 degrees relative to the centre line of the conveyor head and
ramp, and can be raised or lowered to suit different heights.
The operation of the loader is simplified by the convenient grouping
of all levers at one point.
 |
 |
|