7th May 1936, Page: 3, Column: 5
Full Production Shortly
Retorts Lighted At Seaham Coal-Oil Works
Retorts at the new carbonisation
battery at Seaham Harbour Coal Oil
Works were lighted up to-day when the
works were visited by Lord Eldon,
Chairman of the Company, and
Mr. A. Fisher, the company's consulting
engineer.
The old carbonisation battery had
just been put into operation when it
was severely damaged by a fire which
broke out on the night of December 13.
It has been rebuilt with many improvements
according to practical experience
gained by the engineers on this section.
The Sunderland Echo understands
that the plant will shortly be in full
production.
A large chemical treatment plant is
in course of erection and will be ready
in about a month's time. Construction
work being now completed, the men
who have been engaged on construction
will be put on the battery, and the company
at present have as many men as
they require.
 |
 |
|