9th January 1932, Page: 194, Column: 1 Shaft Sinking By The Cementation ProcessBy R. J. Detchon, Assoc.I.M.E* Method to be Adopted. At the sinking where the writer gained his experience, it was found that the strata overlying the coal seams to be worked consisted mainly of fissured sandstone, interspersed with strong grey metal, and seggar after the first of the coal seams was reached. It was correctly estimated that water at increasing pressure would be met with as the sinking progressed, and it was decided that the cementation process should be applied. As, however, old workings of one of the shallower seams had to be passed through, the ordinary method of sinking Was adopted until these were enclosed behind the shaft walls. The shafts, two in number, were to be 13 feet in diameter finished. The cementation process proved very efficient in checking and sealing off the accumulation of water, and during the entire sinking no pumping appliance was necessary in the actual sinking. The water that did find its way to the pit bottom was easily dealt with by winding to bank in the sinking kibble. After the week-end or holiday periods, or when sinking had been temporarily suspended due to walling or cementation operations, a water barrel of 800 gallons capacity, which was self-filling and self-emptying, was used. A pump was ultimately installed in the inset of the first seam reached, at a depth of just below 40 fathoms. This was a small Mackey double-acting ram pump of 13 gallons per minute capacity, which pumped from a large wood tank, placed in the inset, to which tank the water was piped from the water rings and any rain water from the surface. This tank was always empty excepting when the pump was stopped for repairs or lubrication, or when the power was off; thus the leakage from the 40 fathoms of shaft wall was under 13 gallons per minute — a credit to the cementation process. After the water-bearing strata were passed the sinking proceeded rapidly in the ordinary method, and cementation only applied to seal off slight feeders in the side walls. Actual Sinking. As the shafts had been sunk through the overlying boulder clay to the stone-head prior to the erection of the permanent headgear, the sinking contractor commenced his work there. The very first operation is the drilling of the sump shot-holes and the firing of the first round of shots. In a shaft of this size three centre holes, termed "King Holes," are drilled as near as may be 6' apart at the top, forming as it were the corners of an equilateral triangle with sides 6' long. These holes are drilled so as to be nearly touching each other at the bottom to lift as it were a centre core of the rock and relieve the outer ring of sumpers. The ether sump shots are drilled roughly in the form of a circle and about 4 feet apart, the diameter of this outer circle of shot-holes being approximately 10 feet. This circle of holes usually contains about 8 or 9 sumping holes, and with the three "King holes" makes 11 to 12 sumpers. While the drilling of the sump is in operation, two men are drilling, two are supplying water to the drill holes, and the rest of the men are employed filling water into the kibble, hacking up loose bottom, or dressing back the side walls where necessary, the chargeman placing his men to the best advantage. When the drilling of the sump is nearing completion, the necessary primers are being made, usually by the master sinker, in a place set apart at the surface for the purpose. The sump having been drilled, all gear is loaded into the kibble and sent to bank, and the charge- man or master sinker charges the holes. When all the holes have been charged the chargeman couples up the wires of the detonators in series by wire saved from previous shots, or specially provided, and when all are coupled up the men are sent to bank and the kibble brought back to its steadying mark. The man assisting the chargeman gets into the kibble and then the chargeman couples up the extreme wires of the "series circuit" to the permanent shot-firing cables. Immediately the leads are coupled up the chargeman mounts into the kibble, which he steadies, and then calls to be drawn to bank. The shots having been fired, the chargeman, accompanied by not more than two sinkers, and having two safety-lamps, is lowered slowly into the shaft, and, during his descent, the electric lamp, which has been wound up out of danger from flying debris, is slowly lowered so that the chargeman can examine the shaft in good light. During the examination all loose stones are removed from the side wall, water rings, and the deals, and rings of the temporary lining, and any fallen or loose deals or wedges, properly installed. On arrival at the shaft bottom all get out, and whilst the chargeman is hanging the safety-lamps in a place of safety, "usually one of the rings of the temporary lining," and releasing the rapper rope or wire, the two sinkers are preparing a dumping place for the kibble well away from the vicinity of the usual steadying mark. The debris is filled into the kibble from all sides, and one of the first rules a beginner has to learn is never to put his hand on the edge or lip of the kibble. No stone is broken that can safely be sent up in the kibble without danger of damaging the couple or doors at the shaft top, and also no kibble is filled to a greater capacity than 6. inches from the top. Big stones are broken up by means of hammer and rod point, and, in rare cases, shots are fired in really big hard rocks. In the congested space of the pit each man must work with due regard to the safety of those in the immediate vicinity. When using hammer or pick the stroke of the tool must be straight up and down, and not over the shoulder, or the men behind may suffer. The number of sinkers employed was 8 or 10 per shift in each shaft, and when all were at work the space at the shaft bottom was somewhat limited. An accurate check on the number of kibbles of water and stone drawn per shift is kept by the banksman so that the master sinker can deduce the following information: The respective performance of each individual shift; the quantity of water making in the shaft; the quantity of debris excavated, and the approximate rate of descent. A good round of sump shots usually yields 60 to 70 kibbles of stone, the kibble holding roughly one ton of stone. Alignment of Shaft. The operation is as follows: The kibble is sent to the surface with the order written on the side for the "line bucket" and clay, this bucket being a large outsize pail kept for the purpose. The "centre stick," or radius rod, is sent down securely fastened to the winding chain. This "centre stick" is a special rod 2 inches diameter and 9 feet long, armoured with steel ferrules at each end, and graduated in feet, and, at the extreme ends, every 3 inches. The shaft sides having been marked all round, the line is wound to the surface and the kibble again lowered. The drilling machines are now sent down and the drilling of the canch holes commenced. Each hole is set away by the chargeman, or responsible driller, at the point marked as being the correct radius, and the hole is kept as nearly truly vertical as possible. After the firing of the canches work is resumed immediately the examination has been completed. Almost immediately after the commencement of the filling of the canch debris, two or more men are set aside to install another ring of temporary lining. The first ring must be well installed as it forms the anchor for the other rings. The next ring is slung by 4' 1" square hook bolts to the one above and so forth. There are 2 feet of overlap as the deals are 6 feet long, the bottom of the deals always being secured by the ring of deals below. The Cementation Process. After passing through old workings of one of the shallower seams, during which work was temporarily suspended due to stythe from the old workings, it was found that the presence of water at pressure Was to be met with, and it was decided to proceed under the protection of the cementation process. The method of application is as follows : Boreholes were put down near the edge of the shaft and as truly vertical as possible, approximately 100 deep. The boreholes, four in number, formed as it were a square within the shaft, being an equal distance apart, and within 2 feet of the shaft side. These holes 2½ inches diameter were bored with a Meco compressed-air patent boring machine. The boreholes are put down fairly rapidly by means of the air machine, and, with any good fortune, a hole could be bored the required 100 feet in one shift of eight hours. The holes are set away in a specially prepared place right on the bed-rock so that when water is reached the tops of the holes may be sealed off by inserting a short length of 2-inch pipe, say 2' 6" to 3'; this pipe is inserted with the screwed end upwards, and dry soft wood plugs, or wedges, are forced in around the circumference of the pipe between the pipe and the stone. These wedges swell on becoming wet, and a very effective seal is obtained ; the water now runs up the pipe and pours over into the shaft. A 2-inch valve which has first been turned to "full open" is now screwed on to the pipe-end, and when securely tightened down, the valve is closed; this hole is now ready for the injection of liquid cement. Whilst the boring is in progress a blacksmith is kept in each shift to sharpen the cutting chisels, as these require to be very sharp and strictly to gauge. When one hole is bored cementation of that hole is done immediately in the following manner : A 2' bore 3" diameter special armoured hogger, or "hose," is attached from the 2" pipe on the borehole to an Evans' Cornish steam pump, the hogger being attached to the delivery side of the pump. The suction side of the pump is coupled to the cement-mixing barrel, also with 2" bore (3" armoured hose). The mixing barrel is now filled with water and cement in the proportion of 95 of water to 5 of cement, or 19 to 1, to form an intimately mixed liquid cement. The stirring appliance (rotary) of the mixing barrel is now vigorously worked, and when the mixture is ready the inlet valve between the barrel and pump is opened and the pump set away. The cementation pump used was an Evans Cornish pump, with 9" diameter air cylinder and 12" stroke, with 2" ram double-acting at the cement or water end. It was fitted with ball valves, and was capable of developing l,6001b. per square inch. A pressure gauge was used and was most important to guide the attendants as to the happenings inside the borehole. During the cementation of the shallower ground the pressure of cementation is kept to a figure below the pressure due to the head of water at the shaft depth, otherwise the liquid cement may be pumped through some crevice to bank and so wasted. When each of the four holes has either become sufficiently charged with liquid cement, or has refused to take any more of the fluid, it can be safely assumed that the stone, to the depth of the borehole, can he safely sunk through without undue fear of an inrush of water in dangerous quantity. Any bidden feeders of water are usually tapped when drilling the sump holes. Installation of Walling Crib, Etc. Alter a new length, of say 15 fathoms, of ground has been sunk through, sinking is temporarily suspended and shaft walling commenced. When it is not deemed necessary to install a water ring, an oak walling crib is installed. The crib, which is in segments with lap joints for nailing the joints together, is assembled roughly and laid on its bed temporarily. It is now centred in the following manner: The centre line is lowered into the shaft and the necessary weight attached. When the line is duly steadied the centre stick, or measuring rod, is used on the crib, and the position of the latter so manoeuvred, by moving it about entire with a pinch bar, that its inner circumference is 6' 6" from the centre line in any direction radiused from the centre line; leaving the centre line in the shaft, a long straight-edge is brought into operation to level the crib. The crib is levelled by raising and packing the low portions in all directions, and when the straight-edge has been used in numerous directions across the shaft the crib assumes a dead level position. It is now time to again check the crib for centre adjustment, and the crib having been accurately fixed, the line and level are withdrawn and side-lines slung down to the lower crib from the one above. The crib is cemented into the position by filling in all round with concrete. When this has partially set the side-lines are installed. The crib having been duly centred and built in, and the side-lines, some 16 in number properly installed, the actual walling is carried out without delay. As the walling proceeds any projecting stone which might cause the width of the wall or lining to be seriously diminished is removed by the two sinkers in charge of unloading the material, and, if sufficient to load a kibble, sent to the surface, small quantities of debris being shovelled past the cradle into the sump. There are usually three, sometimes four, bricklayers employed in a shaft of these dimensions, and when each has gone round the shaft four or five times with a tier of bricks it is time for another lilt of the cradle. The complete ring is tested for centre adjustment and level in precisely the same manner as that applied to the bricking crib, any deficiency in level being overcome by either bending the dowels down by hammering them with a heavy hammer, or the ring is raised and packing put under the ring and on the dowels. Any large holes between the back of the ring and the shaft side are filled up with corrugated sheeting or sheet iron so that the concrete might not escape. The dowels are now knocked back flush with the water ring and the bricking commenced. The first tier of bricks are kept 6' back from the front circumference of the ring which, of course, is 13 feet diameter, and to get back to the normal dimensions the tiers of bricks are each stepped forward ½" (called "withering ") until the 13 feet diameter is reached. Cementation of Side Walls. The cementation of the side walls is carried out immediately a section of bricking is completed. The cementation appliances, viz., cementation pump, mixing barrel, hoggers, drilling machines, etc., are all assembled on the cradle at the foot of the lowest section of brickwork and here a commencement is made. Drill holes are put into the shaft side wherever water is issuing or a suspicion of dampness exists ; usually water comes freely from these holes into which 1" pipes are inserted and 2" valves attached through adapter ferrules. The cementation pump is now attached to the lowest of these holes and injection begins. The pump soon finds the weak spots of the wall and liquid cement oozes freely from any holes; these are stopped off by inserting dry soft wood wedges, and sometimes wads of cotton waste are inserted before the wedge to check the flow of cement. As the cement content rises up behind the side walls short ladders are used in the wedging and plugging operations, and frequently one drill hole will do for the cementation of ten feet of walling. New holes are drilled, but always below the point where the highest leakage of cement was detected, and the operation is continued raising the cradle when necessary and taking infinite care to ensure that no ground is missed and no section of walling left uncemented. The first seam of coal met with in the sinking, to which an inset was required, occurred just near the bottom of the water-hearing strata. Below the water-bearing strata the shaft diameter was reduced to 14' 6" in the "big," being the 13' finished plus 9" side walls, the lining of concrete having been discontinued. Work now proceeded very rapidly and several coal seams passed through. * Summary of paper prepared for the October meeting of the Associates and Students' Section of the North of England Institute of Mining and Mechanical Engineers.
|
|||||||||||||||
![]() |
||||||||
|
Mail: Webmaster |
Back |
Home |
Copyright © 1999-2024 by The Durham Mining Museum and its contributors Registered Charity No: 1110608 Page last updated: 28 Nov 2022
|
Search |
|
|||