Logo Museum
Museum
Friends of Durham Mining Museum
Events Calendar
e-Books and Books for sale
Photograph Gallery
Document Archive
Main Document Archive
Newspaper Articles
Articles by date
Articles by colliery
Personal name index
Local Record Extracts
D.M.A. Document Archive
Transactions of I.M.E.
Miners' Welfare
N.C.B. Archive
The Colliery Engineer
The Colliery Guardian
Mine & Quarry Engineering
Mining Journal
The Science and Art of Mining
Coal Magazine
Coal News
Coke and Gas
Master Name Index
What's new in the site
Mining
Mining History
Colliery Index
Colliery Maps
Company Overviews
Who's Who
Mineral Information
Managers Certificates
Educational Material
Bibliography
Statistics
Workers/Employee Lists
Notes for Family Historians
War Service information
Disasters
Disaster Reports
Names of those killed
Disasters in the 1700s
Disasters in the 1800s
Disasters in the 1900s
Memorials
Awards for Gallantry
On this day ...

Links to other sites of interest
Industrial Heritage Days Out
Former www.pitwork.net web site

Index to site

Contact and address details

Share Page with Social Media

Share on Facebook

Share with Reddit

Share on Delicious


 Newspaper Articles Index Newspaper Articles 

16th June 1928, Page: 380, Column: 1

Shaft Sinking Notes

By H. A. Kee.

[At the March meeting at Quebec of the Canadian Institute of Mining and Metallurgy, Mr. H. A. Kee gave a description of the "Sinking Operation at McIntyre No. 11 Shaft, Porcupine District, Northern Ontario," from which the following general notes are culled.]

In the sinking operation in connection with the development of the McIntyre Porcupine mine, the slogan was "Safety First for Pleasant and Efficient Workmanship," and this general policy made it possible to sink and timber 2,123 feet during the first year without a serious accident. The excavation is broken 7 feet by 24 feet properly across, or at right angles to, the general strike of the formation, which is sheared basalt and quartz porphyry. The schistosity is practically vertical, with slightly southerly dip and an easterly rake approximating 55 degrees. Sinking commenced on 2nd February, 1925, at a point 62 feet below the surface, and was continued three shifts per day until 5th March, 1927. At the end of that period, 400 rounds had been removed, and the shaft had reached a point 4,133 feet below the collar. The timbering was complete and included 23 sets of bearer timbers (four pieces 1" x 24" x 20"). In the same interval 19 stations had been cut and timbered, and 600 feet of cross-cutting completed, with an average of 16.3 men per shift working below the collar.

In 31 days 280 feet of timbering and 250 feet of sinking was completed by 17.9 men per shift below collar ; 8,500 tons of rock (5.1 tons per man-shift) and over 1,500 tons of water (1 ton per man-shift) were removed ; while approximately 165,000 board feet of timber (100 board feet per man-shift) were placed and 19,250 feet (11.8 feet per man-shift) drilled.

The best work accomplished by 18 men per shift over an 8-day period was 72 feet of sinking completely timbered, and the shortest period taken for a 10-foot completed advance was 22½ hours by 18 men per shift. The best mucking done was 174 tons of rock delivered at surface in six hours by 19 men (9.2 tons per man), and in the best 8-hour timbering shift, 18 men permanently placed and blocked complete 13,200 board feet of shaft sets and outer lining (733 board feet per man).

Suggestive safety first signs were conspicuously placed at the entrance to buildings and shaft, so that all men before starting to work appreciated the determination to guard against accident. The foreman in charge selected the men by their general appearance and experience. Each man employed underground was sold a two-foot rule, and was held responsible for the correctness of every measurement taken. Each man before going on shift received a daily card which he recorded in and out through a punch-clock system installed in the charge-house building. A first-aid room and captain's office were attached to the same building. Throughout the operation, approximately 10 per cent. of the men who worked below the collar had had no previous shaft experience, but their desire to learn soon made them efficient men. The average remuneration, to all men working below the collar of shaft for the two-year period, approximated 7.98 dols. per shift, while all surface workmen were paid the district schedule plus a bonus equal to half the bonus paid to shaft men.

Each man before leaving the charge house, both going on and coming off shift, was inspected and properly treated by a first-aid officer. It was found that only a small percentage of compensation cases was due to infection directly traceable to shaft-work abrasions, and that compensation cases were traceable to blood infection which was indicated by irritations due to general living conditions over which the officers of the Company had no control. When a man was suspected of blood infection, his case was recorded and watched closely ; then, if he developed definite blood infection he was sent to a doctor who applied serum treatment. While he was off duty taking treatments which readily cleared up the trouble, other employees were not unnecessarily exposed to infection. By such close observation, infection was reduced to a minimum. In this connection it may be of interest to record that infections from skin abrasions were also improved by the use of castor oil and one-half of one per cent, lysol with ¼ ounce of oil of peppermint per gallon of oil. Shaft-men twice a day before going down rubbed a coating of this oil into their hands and wrists, which softened the cuticle, thus retaining circulation and the natural oils in the skin and minimising the danger of infection.

A blasting shield was constructed of 10-inch I-beam with compartments the same size as shaft timber sets. The end two compartments, or two-thirds of the shield, were covered with ½-inch boiler plate 40 per cent. perforated, to relieve concussion strains, and these plates were reinforced by 60-pound T-rail. The two centre compartments, one-third of the shield area, were left open for hoisting, but completely covered with perforated steel doors while blasting was in progress. This shield was suspended directly under the last timber set and hung from rock bolts about ten feet above. This prevented the timber from breaking and, what was more important, eliminated displacement of timber from vertical lines and proper position as determined by accurately measuring from four plumb lines on skip or west side wall and end plates, and two plumb lines on east side wall and end plates. This shield while in place directly under the permanent sets, was used as a platform from which the safety-first man directed such operations as scaling and the placing of drill lines. While timbering and cutting hitches, this shield was carried by four 3-ton spur gear chain blocks, one in each corner, the shield being suspended as a staging on which work was safely and conveniently accomplished.

Twelve to fourteen machines were used to drill off approximately 770 feet in 66 holes. This operation required less than two hours of actual drilling time and required about two feet of drilling per ton of rock broken. Usually short easing holes and first cut holes were blasted and mucked out fairly clean. The second step in the operation was the blasting of the long cuts and bench holes, leaving only light end-holes with two or three centre sump holes which were drilled while bench was being cleaned out before the third blasting was done. The third blasting being completed, the bottom was cleaned up, and water and air used to thoroughly wash every crevice and corner, thus guarding against the possibility of later drilling into powder while machines were running in a dense fog of air-exhaust and water.

All blasting was electrically done in parallel series from the mine captain's office, after everyone had returned to surface. Underground lighting and blasting connections were carried through separate transformers, both of which were separate from surface lighting system. To make this blasting system as safe as possible, the key to the explosive supply was hung back of the underground lighting switch-gear. As a result, before explosives could be procured all underground currents were cut off. After holes were loaded and connections tested underground, all the men came to the surface. No. 1 blasting switch was put in to connect the transformer lines and then the second and final contact with the underground blasting line was made to detonate charge.

A reversible exhaust blower rotary fan of 10,000-cubic-feet capacity, driven by 75 horse-power alternating 3-phase motor, was installed. Immediately after blasting, the exhaust fan was run for 14 to 20 minutes, then reversed, and fresh air blown through the 20-inch gas line installed in the service-way compartment. This fresh air blowing into the shaft at the rate of 3,500 to 5,000 cubic feet per minute, in combination with an even distribution of shaft water spraying over the entire shaft area at the rate of 5 to 7 gallons per minute, kept the atmosphere and the working temperature at approximately 60 to 62 degrees Fahr.


Names mentioned in this article

 

 Name  Age  Occupation  Notes 
Kee, H. A.      


 

mail
Mail:
Webmaster
Back
Back
Home
Home
Open Government Licence   Contains public sector information licensed under the Open Government Licence v3.0.

Copyright © 1999-2024 by The Durham Mining Museum and its contributors
Registered Charity No: 1110608
Page last updated: 28 Nov 2022

Privacy Policy
 
Terms & Conditions
 
Search
Search
Print
Print