16th June 1928, Page: 380, Column: 1
Shaft Sinking Notes
By H. A. Kee.
[At the March meeting at Quebec of the Canadian Institute of Mining and
Metallurgy, Mr. H. A. Kee gave a description of the "Sinking
Operation at McIntyre No. 11 Shaft, Porcupine District, Northern Ontario,"
from which the following general notes are culled.]
In the sinking operation in connection with the development of the McIntyre
Porcupine mine, the slogan was "Safety First for Pleasant and Efficient
Workmanship," and this general policy made it possible to sink and timber
2,123 feet during the first year without a serious accident. The excavation is
broken 7 feet by 24 feet properly across, or at right angles to, the general
strike of the formation, which is sheared basalt and quartz porphyry. The
schistosity is practically vertical, with slightly southerly dip and an
easterly rake approximating 55 degrees. Sinking commenced on 2nd February,
1925, at a point 62 feet below the surface, and was continued three shifts per
day until 5th March, 1927. At the end of that period, 400 rounds had been
removed, and the shaft had reached a point 4,133 feet below the collar. The
timbering was complete and included 23 sets of bearer timbers (four pieces
1" x 24" x 20"). In the same interval 19 stations had been cut
and timbered, and 600 feet of cross-cutting completed, with an average of 16.3
men per shift working below the collar.
In 31 days 280 feet of timbering and 250 feet of sinking was completed by 17.9
men per shift below collar ; 8,500 tons of rock (5.1 tons per man-shift) and
over 1,500 tons of water (1 ton per man-shift) were removed ; while
approximately 165,000 board feet of timber (100 board feet per man-shift) were
placed and 19,250 feet (11.8 feet per man-shift) drilled.
The best work accomplished by 18 men per shift over an 8-day period was 72 feet
of sinking completely timbered, and the shortest period taken for a 10-foot
completed advance was 22½ hours by 18 men per shift. The best mucking done
was 174 tons of rock delivered at surface in six hours by 19 men (9.2 tons per
man), and in the best 8-hour timbering shift, 18 men permanently placed and
blocked complete 13,200 board feet of shaft sets and outer lining (733 board
feet per man).
Suggestive safety first signs were conspicuously placed at the entrance to
buildings and shaft, so that all men before starting to work appreciated the
determination to guard against accident. The foreman in charge selected the men
by their general appearance and experience. Each man employed underground was
sold a two-foot rule, and was held responsible for the correctness of every
measurement taken. Each man before going on shift received a daily card which
he recorded in and out through a punch-clock system installed in the
charge-house building. A first-aid room and captain's office were attached to
the same building. Throughout the operation, approximately 10 per cent. of the
men who worked below the collar had had no previous shaft experience, but their
desire to learn soon made them efficient men. The average remuneration, to all
men working below the collar of shaft for the two-year period, approximated
7.98 dols. per shift, while all surface workmen were paid the district schedule
plus a bonus equal to half the bonus paid to shaft men.
Each man before leaving the charge house, both going on and coming off shift,
was inspected and properly treated by a first-aid officer. It was found that
only a small percentage of compensation cases was due to infection directly
traceable to shaft-work abrasions, and that compensation cases were traceable
to blood infection which was indicated by irritations due to general living
conditions over which the officers of the Company had no control. When a man
was suspected of blood infection, his case was recorded and watched closely ;
then, if he developed definite blood infection he was sent to a doctor who
applied serum treatment. While he was off duty taking treatments which readily
cleared up the trouble, other employees were not unnecessarily exposed to
infection. By such close observation, infection was reduced to a minimum. In
this connection it may be of interest to record that infections from skin
abrasions were also improved by the use of castor oil and one-half of one per
cent, lysol with ¼ ounce of oil of peppermint per gallon of oil. Shaft-men
twice a day before going down rubbed a coating of this oil into their hands and
wrists, which softened the cuticle, thus retaining circulation and the natural
oils in the skin and minimising the danger of infection.
A blasting shield was constructed of 10-inch I-beam with compartments the same
size as shaft timber sets. The end two compartments, or two-thirds of the
shield, were covered with ½-inch boiler plate 40 per cent. perforated, to
relieve concussion strains, and these plates were reinforced by 60-pound
T-rail. The two centre compartments, one-third of the shield area, were left
open for hoisting, but completely covered with perforated steel doors while
blasting was in progress. This shield was suspended directly under the last
timber set and hung from rock bolts about ten feet above. This prevented the
timber from breaking and, what was more important, eliminated displacement of
timber from vertical lines and proper position as determined by accurately
measuring from four plumb lines on skip or west side wall and end plates, and
two plumb lines on east side wall and end plates. This shield while in place
directly under the permanent sets, was used as a platform from which the
safety-first man directed such operations as scaling and the placing of drill
lines. While timbering and cutting hitches, this shield was carried by four
3-ton spur gear chain blocks, one in each corner, the shield being suspended as
a staging on which work was safely and conveniently accomplished.
Twelve to fourteen machines were used to drill off approximately 770 feet in 66
holes. This operation required less than two hours of actual drilling time and
required about two feet of drilling per ton of rock broken. Usually short
easing holes and first cut holes were blasted and mucked out fairly clean. The
second step in the operation was the blasting of the long cuts and bench holes,
leaving only light end-holes with two or three centre sump holes which were
drilled while bench was being cleaned out before the third blasting was done.
The third blasting being completed, the bottom was cleaned up, and water and
air used to thoroughly wash every crevice and corner, thus guarding against the
possibility of later drilling into powder while machines were running in a
dense fog of air-exhaust and water.
All blasting was electrically done in parallel series from the mine captain's
office, after everyone had returned to surface. Underground lighting and
blasting connections were carried through separate transformers, both of which
were separate from surface lighting system. To make this blasting system as
safe as possible, the key to the explosive supply was hung back of the
underground lighting switch-gear. As a result, before explosives could be
procured all underground currents were cut off. After holes were loaded and
connections tested underground, all the men came to the surface. No. 1 blasting
switch was put in to connect the transformer lines and then the second and
final contact with the underground blasting line was made to detonate charge.
A reversible exhaust blower rotary fan of 10,000-cubic-feet capacity, driven by
75 horse-power alternating 3-phase motor, was installed. Immediately after
blasting, the exhaust fan was run for 14 to 20 minutes, then reversed, and
fresh air blown through the 20-inch gas line installed in the service-way
compartment. This fresh air blowing into the shaft at the rate of 3,500 to
5,000 cubic feet per minute, in combination with an even distribution of shaft
water spraying over the entire shaft area at the rate of 5 to 7 gallons per
minute, kept the atmosphere and the working temperature at approximately 60 to
62 degrees Fahr.
 |
 |
|
Names mentioned in this article
|
 |
 |
| Name | Age | Occupation | Notes |
| Kee, H. A. | | | |