27th August 1927, Page: 33, Column: 1
Air Lift Pumping
E. J. Gealy describes (Coal Age) unusual methods employed to
reopen the Neilson mine of the Shamokin Coal Co., in the city of Shamokin, Pa.
For many years the property has been idle and the water had risen in the shaft
to within about 30 feet of the ground level. The officials of the company
decided that the best way to start unwatering the mine was by means of an air
lift pumping system. On November 9th, 1924, one air lift was started. It
consisted of a 190 ft. column line of 10 in. wrought iron pipe supported in the
old mine shaft. This length of pipe was considered sufficiently long to obtain
satisfactory submergence, although the shaft was 1,200 ft. deep and the
vertical depth of the water was greater than this because of the basins in the
steeply pitching beds. In December another similar air lift was installed in
the shaft and the two lifts were kept in operation as much of the time as
possible. The air lifts were stopped only when it became necessary to add extra
lengths of pipes to maintain sufficient submergence to obtain satisfactory
results. In the air compressor house two large compressors driven by 2,300 volt
synchronous motors supplied the air. Suitable control valves were placed in the
air lines so that the quantity of air could be regulated or stopped whenever it
was necessary.
Several novel features were incorporated in the design and operation of the
lifts by B. C. Osier, superintendent of the mine. The foot piece was
constructed out of a straight 5 ft. section of 10 in. pipe drilled full of
¼ in. holes except near each end. Around the perforated part of the pipe a
short section of 12 in. pipe was welded in such a manner as to form a jacket or
chamber. At diametrically opposite points in this outer pipe connections were
made to the air line. An additional part of the foot piece was a 3 in. bronze
nozzle also connected to the 1 in. air line. Thus the construction of the foot
piece was such that a large volume of air broken up into many fine streams had
easy access into the eduction pipe.
The air lift discharge lines were made of three different size pipes. When the
air lifts were stopped from pumping directly to the outside surface they
consisted of a lower section of 10 in. pipe 200 ft. long to which was attached
another 200 ft. section of 11 in. pipe and at the top was still another section
of 12 in. pipe about 240 ft. long. To accomplish adjustments to depth all extra
sections of pipe were added to the top and the whole eduction pipe was
suspended on 7/8 in. steel hoisting cables. For support at the top of the
shaft, two rope clamps 10 in. long were attached to each rope and the weight of
the pipes was supported on a yoke or cross member which in turn rested on heavy
beams. Each rope extended over the head frame on to a reel from which it was
unrolled as required.
During the period between November 9th, 1924, and February 10th, 1925, one or
the other or both of the air lifts were in almost continuous operation. On
February 10th, when the lifts were stopped from pumping to the outside surface,
the eduction pipes were 640 ft. long and the water had been lowered about 475
ft. This indicates that the water level dropped at the rate of about 4½
ft. every 24 hours. It has also been estimated that during part of the time
5,000 gallons per minute was pumped and a total of about 335,000,000 gallons
was raised to the surface. Best results were obtained when the submergence was
about 200 ft. and the lift about 100 ft. Averaged over the whole range of
operation, the cost of raising the water was slightly over 6.5 c. per 1,000
gallons.
Since February 19th two 1,000 gallons per minute pumps have been set up in the
No. 12 level and the air lift discharges to these units which in turn relay the
water to the surface. In time, two more centrifugal pumps will be installed and
the water relayed to them by the air lift. In this manner it is intended to
carry the unwatering plan until the air lift system will be impracticable for
further use here.
 |
 |
|
Names mentioned in this article
|
 |
 |
| Name | Age | Occupation | Notes |
| Gealy, E. J. | | | |
| Osier, B. C. | | | |