Logo Museum
Museum
Friends of Durham Mining Museum
Events Calendar
e-Books and Books for sale
Photograph Gallery
Document Archive
Main Document Archive
Newspaper Articles
Articles by date
Articles by colliery
Personal name index
Local Record Extracts
D.M.A. Document Archive
Transactions of I.M.E.
Miners' Welfare
N.C.B. Archive
The Colliery Engineer
The Colliery Guardian
Mine & Quarry Engineering
Mining Journal
The Science and Art of Mining
Coal Magazine
Coal News
Coke and Gas
Master Name Index
What's new in the site
Mining
Mining History
Colliery Index
Colliery Maps
Company Overviews
Who's Who
Mineral Information
Managers Certificates
Educational Material
Bibliography
Statistics
Workers/Employee Lists
Notes for Family Historians
War Service information
Disasters
Disaster Reports
Names of those killed
Disasters in the 1700s
Disasters in the 1800s
Disasters in the 1900s
Memorials
Awards for Gallantry
On this day ...

Links to other sites of interest
Industrial Heritage Days Out
Former www.pitwork.net web site

Index to site

Contact and address details

Share Page with Social Media

Share on Facebook

Share with Reddit

Share on Delicious


 Newspaper Articles Index Newspaper Articles 

4th December 1926, Page: 154, Column: 1

Screening And Washing Plant

By L. F. H. Booth, STUD.I.M.E.

Importance of Screening and Washing. — The history of the coal trade during the last two years has emphasised the importance not only of cheap production, but of putting the coal on the market in a form most suitable to the requirements of the customer. This involves : (1) Grading the coal raised from the mine so as to give the customer the size and only the size which meets his individual requirements. (2) Giving the customer the coal in a form which contains the least practicable percentage of free ash.

As is well known, for household purposes and for some manufacturing purposes, the larger sizes of coal are preferred, while for other manufacturing purposes the smaller sizes are equally suitable. Generally speaking, the more artificial are the means employed for using the coal, the smaller are the sizes which can be utilised. The older types of gas producer require larger sizes of coal than the more modern types, and for burning the small sizes of coal under boilers, forced draught and chain grate or mechanical stokers are necessary. By washing the coal at the pithead, the cost of transporting dirt is avoided. As an example of this, the average cost of the railway carriage and sea freight from Durham collieries to London may be taken' as being about 5s. 7½d. per ton in 1925, and if we assume a figure of not less than 10 per cent. as being the amount of dirt which would be removed by washing (which would be the case with many classes of Durham coal), the cost of carrying this removable dirt would be 6¾d. per ton of unwashed coal and would in many cases exceed that figure. This is not the sole advantage. For instance, the consumer, in burning coal containing ash, incurs labour costs in putting non-combustible matter under the boilers and taking it away again in the form of clinker and also loses by having to use part of the heat from the coal in heating the ash in it.

Screens and Washery. — The screening plant and Blackett washery at Deaf Hill Colliery were recently erected to take the place of an existing screening apparatus which could not deal satisfactorily with an increasing output. The screens and washery were erected by Messrs. M. Coulson and Co., Ltd. The fuel cleaned is from the Hutton, Harvey and Busty seams, which are all worked by the method of hand hewing on the longwall system. The coal is typical Durham coking coal, the largest proportion of the free dirt being naturally found in the coal from the Busty seam which contains two bands of a total thickness of 3 to 5½ inches. The normal practice followed is to treat the Harvey and Hutton coal together, and to treat the Busty seam coal separately. "Best" coal is, however, made entirely from the Hutton seam.

The tubs on leaving the shaft gravitate to a creeper which discharges them over a weigh bridge and thence to the tipplers, which are of the Simplex type, automatic in action and driven through belt and chain gearing by a 30 H.P. motor. There are three tipplers, two for coal and one for stone. The two coal tipplers deliver on to shoots connecting with the two primary screens.

The jigging screens are driven through belting and line shafting by the tippler motor and are fitted with a 3-inch perforated plate and so designed as to deliver two separate streams of coal on to the picking belts where fuel above 3 inches is cleaned. These slope upwards and are driven through friction clutches and chain gearing by a 60 H.P. motor. All hand-picked dirt is thrown down shoots adjacent to the belts and delivers on to a cross-conveyor driven through chain gearing and line shafting by the picking belt motor. The refuse is deposited upon the conveyor receiving stone from the stone tippler. The coal from the top end of the picking belt delivers on to secondary jigging screens, these being driven by the 60 H.P. picking belt motor.

When the coal gets on to the secondary jigging screens all below 3 inches is by-passed direct on to two cross-conveyors driven through line shafting and chains by a 25 H.P. motor ; all above passes over as "best." The "best" is delivered direct into twenty-ton wagons, but by a suitable slide in the jigger pan it can be directed into two Jeffrey single roll crushers driven through belting by the picking belt motor. These crushers reduce the coal to a maximum size of 3-inches and deliver on to the above-mentioned cross-conveyors which carry it into the boots of two bucket elevators driven through chain gearing by a 25 H.P. motor.

The elevators raise the coal into the centres of two rotary screens also driven by the same motor. The rotary screens produce four grades of coal : (1) All above 2 inches. (2) All above 1 and up to 2 inches. (3) All above ½ and up to 1 inch. (4) The small or duff. The duff does not pass through the washer, but is delivered on to band conveyors each driven by belting from the washer barrel motors and delivering into twenty-ton bunkers to be drawn off later into wagons. The remaining three grades of coal which we may call trebles, nuts and peas come down shoots, delivering into the Blackett washers, one barrel for each grade. These washers, six in number, consist essentially of an inclined barrel inside which is a spiral flange. The barrels are rotated slowly by two 25 H.P. motors, via line shafting and chains, three barrels to each motor. Raw coal mixed with water is admitted near the upper end of the barrel and flows over the top of the spiral flanges. The stone, by virtue of its higher density, sinks through the coal and is caught by the rotating spiral flange which carries it up-hill while the coal is floated down to be discharged at the lower end.

The above-mentioned shoots extend a distance of 10 feet into the barrels, which are each 30 feet long and 4 feet in diameter. At the point where the shoot enters the barrel a 3-inch diameter pipe delivers a stream of water which flushes the raw coal into the washer.

An auxiliary water supply meets the dirt coming up the barrel just before it is discharged, agitating it and freeing any coal that may have become buried and carried up the barrel with the stone or dirt.

The motion of the barrels is in a clockwise direction at a speed of 11 r.p.m. caused by two friction rollers 14 inches diameter working on rings fitted round the outside of the barrel, one near the top end and the other near the bottom. Similar idle rollers work on these rings on the opposite side of the barrel to the driving force. Dog clutches are fitted to each barrel near the top end to allow any barrel to be stopped or started independently of the rest. The arrangement has the effect of screening or conveying the dirt to the top end of the barrel whence it is discharged into a scraper conveyor running under the washer house floor and delivering into a hopper at the opposite end of the building to the silt well. The washed coal, on the other hand, is floated down to the bottom end of the barrel and discharged into storage bunkers. These are of 21 tons capacity. At the bottom of the storage bunkers are two drainage valves which allow any moisture that may remain in the coal to pass off before the washed product is delivered into 20-ton wagons.

In order to free the washed product of the maximum amount of moisture and also to recover the fine coal or silt held in suspension in the water, the bottom 4 feet 9 inches of the barrel is constructed of ¼ inch square iron mesh and fixed inside is a right hand spiral which assists the washed coal to pass over the top of the mesh into the storage bunkers. The water and silt in suspension drain together through this mesh and deliver into an open wooden trough clamped underneath the floor and are conveyed by 7-inch diameter pipes into a silt well situated at one end of the washery building. A scraper conveyor is working in the silt well driven through chains by the pumps motor. This raises the silt for discharge into twenty-ton wagons ; any water taken up by the scraper is drained through a fine iron mesh half way up the incline and conducted back into the well. By this method no settling tanks are necessary and the labour cost of digging the silt out is avoided.

Water Supply. — The water supply is obtained from the colliery pond which is connected to the silt well by a 7-inch pipe range. Circulation through the plant is carried out by two 8-inch centrifugal pumps, driven through belting by an 85 H.P. motor, the pump and motor being situated immediately above the silt well. Each has a capacity of 1,000 gallons p.m. with a total head of 53 feet.

Housing of the Plant. — The heapstead and screening plant are in one building. The structure is of steel and the walls and roof corrugated asbestos. The lighting has been carefully studied and is in accordance with the best modern factory practice. The washery building main walls are in brickwork with intermediate supports of steel stanchions, the framing of the floors are roll steel joists, and the floors reinforced concrete. The roof is formed by corrugated asbestos carried on steel principals and lighting is by numerous wall windows in steel frames.

Labour. — The labour employed on the combined plant consisting of the screen and washery with auxiliary plant and the aerial ropeway for removing the dross consists of nineteen man per shift of whom nine are employed on the washery, nine on the screens, etc., and one on the ropeway. The plant nominally works 17 hours per day for five days per week.

Output. — In a typical five-day week immediately preceding the coal stoppage, the screening plant dealt with an average tonnage per day of raw coal including the "bests" or coal over 3 inches, of 1,235 tons, or excluding the "bests," a tonnage of 907 tons per day. Of this 907 tons, 295 tons were duff, or under ½-inch, leaving a balance of 612 tons per day, or 36 tons per hour, dealt with by the washery.

* From paper on "Screening and Washing Plant at Deaf Hill Colliery," presented for discussion at the November meeting of the Associates and Students' section of the North of England Institute of Mining and Mechanical Engineers.


Names mentioned in this article

 

 Name  Age  Occupation  Notes 
Booth, L. F. H.    Mining Engineer  



Links to Collieries/Mines mentioned in this article

 

Deaf Hill Colliery  Deaf Hill Colliery


 

mail
Mail:
Webmaster
Back
Back
Home
Home
Open Government Licence   Contains public sector information licensed under the Open Government Licence v3.0.

Copyright © 1999-2024 by The Durham Mining Museum and its contributors
Registered Charity No: 1110608
Page last updated: 28 Nov 2022

Privacy Policy
 
Terms & Conditions
 
Search
Search
Print
Print