17th November 1909
The North-East Coast
New Coaling Staiths On The Tyne
Last year's shipments of the North-Eastern Railway Company from the Tyne Docks and the Dunston staiths aggregated 7,531,963 and 3,408,750 tons of coal and coke, which were record figures. For the ten months of the present year the figures are 6,038,419
and 2,955,649 tons respectively. In order to improve the coal shipping facilities on the Tyne, and to relieve the congestion at the Dunston staiths, the North-Eastern Railway Company has recently prepared plans for the provision of new shipping berths at
West Dunston, about 1¼ mile westward of the present Dunston staiths. At present it is proposed to provide only three shipping places at West Dunston, with a frontage to the river of about 1,700ft., but arrangements are being made to admit of this
accommodation being doubled, and of the construction of a basin 500ft. wide by 1,700ft. long. There will be a distance of about 120ft. between berths. There will be an auxiliary electrical conveying belt, somewhat similar to those now in use at Tyne Dock
and Dunston. The new staiths will be built of timber work, on a gradient of 1 in 80, the highest spout being 53ft. at h.w.o.s.t., and the lowest spout 43ft. at h.w.o.s.t. There will be a depth alongside of 26ft. at l.w.o.s.t. Access to the staiths will
be given from a nest of sidings to be established northward of the Derwenthaugh branch, and as at present arranged there will be provided standage of about 2,700 yards. The laden traffic, after passing through these sidings, will be worked onto the
staiths at a gradient of 1 in 100, this railway being carried over the approach lines to the sidings by means of two bridges. The empty wagons will be worked from the staiths by means of gravitation, and there will be a separate set of sidings of 1,700
yards length for the storage of the empty wagons. The scheme is expected to take about two years to complete, and to involve an outlay of about £110,000.
The work will be carried out to the plans and under the direction of Mr. Charles A. Harrison, the chief engineer of the North-Eastern Railway Company, and tenders are expected to be invited in the course of the next few weeks.
 |
 |
|