"No. 1 drift has been driven by four men 6fms, 4ft, 8in, at £2 and £2 5s per fathom. The ground is still soft for driving, and the lode is of a very promising character. I have no doubt whatever but what the lode in this drift will
soon become productive.
"Side vein in No. 1 drift has been driven by one man and one boy 3fms, 1ft, 6in., at £3 per fathom. No change in the lode since last reported on.
"Intermediate drift has been driven 2fms, 4in by four men at £6 per fathom, through a good load of ore.
"The new drift, driving south of rise to meet the intermediate drift, has been driven 1fm, 10in., at £4 per fathom (these drifts have been holed to each other), and have cross-cut the lode 3ft., at £6 per fathom, by two men, where I find
the lode to be fully 10ft. wide, and will yield 30 tons of ore per fathom.
"The rise in back of No. 2 drift has been put up 2fms, 4ft, by six men, at £6 per fathom. The lode is about the same as last reported on.
"No. 3 drift has been driven 1fm, 4ft, 4in, by two men, at £3 per fathom. The ground is a little easier for driving, and the lode is improving.
"No. 4 drift has been driven by six men 5fms, 3in, at £6 and £7 per fathom. I think by our measurements, we are now under the point that the old men had in No. 3 drift above, where they met with so much ore. The lode here has greatly
improved, and will now yield 20 tons of ore per fathom.
"I took a sample of ore last night for analysis, a report of which you shall have in a few days. The lode is improving every foot we go through it.
"No. 5 drift has been driven by six and four men 2gms, 1ft, 10in, at £10 10s and £12 per fathom. The ground is a little easier for driving, and the lode is improving. I shall be able to report more fully on this in my next.
"No. 2 drift at Ban Garth has been driven 1fm, 3ft, 3in, by one man and one boy, at £7 per fathom.
"No changes in lode worthy of notice since last reported on.
"The day men have been engaged in tramming out and sending down ore, and extending the incline road to meet the railway.
"Carriers commenced taking ore down to the Ravenglass and Eskdale Railway at 'King of Prussia' bridge on Tuesday, the 12th inst.
"Eskdale, January 13th, 1875"