3rd December 1874
Ravenglass and Eskdale Railway
Engineer's Report, 25th November, 1874
I beg to report that I visited the works on the 18th, 19th, 20th, and 21st inst. The road is nearly all formed to Nabb Gill, with the exception of the portion through Edward Sharpe's land, which is not as yet in the hands of the contractor, and is the
cause of delaying the completion of the formation of this portion, a length of about half a mile.
The high level tip is built up to the level of the wall plates for carrying the cross beams. I am of opinion it will be necessary to place two 5-feet diameter turntables at the end of it for transferring the empty trucks on to the down line as they are
discharged into the Furness trucks.
The girders and flooring for the low level section of the bridge at Ravenglass are in place.
The "King of Prussia" Bridge is open to the public.
The contractor's locomotive is working between Ravenglass and three miles fourteen chains, which is half-way between Murthwaite and Walk Mill, the permanent way being laid up to this point.
The contractor has a strong gang of platelayers at work (about forty) and all the necessary permanent way materials. I anticipate, if the weather is favourable and the locomotive kept in working order, that the road will be laid as far as Hollowstones
Bridge in about a fortnight. The ore could then be carried over the line from this point and transhipped into the Furness trucks by using Mr. Oliver's branch line to the goods siding at Ravenglass station, until such time as the high level tip is
complete and the Furness siding alongside.
A very short space of time would be occupied in laying the permanent way on to the "King of Prussia" Bridge, the distance being only 59 chains, or three-quarters of a mile. The ore could then be run from the "King of Prussia" Bridge.
A temporary shoot on the side of the bridge would enable carts to tip direct into our trucks.
On Saturday last 200 tons of rails, 2,040 fish plates, 2,000 sleepers, and one truck of fencing, arrived at Ravenglass, so that there is now every prospect of the line being rapidly completed as far as 5¾ miles, i.e. up to Edward Sharpe's land.
Newspaper transcript kindly provided by
West Cumbria Mines Research.
 |
 |
|
Names mentioned in this article
|
 |
 |
| Name | Age | Occupation | Notes |
| Oliver, — | | | |
| Sharpe, Edward | | Land Owner | |