Sites in Production at July 1991
Tonnages given are latest estimate of Contract Tonnage.
Completion date is estimated cessation of coaling.
Central West Region
Brown Lees, south of Kidsgrove: 1.62m tonnes, 149 hectares. Production started 1988 and will be completed 1996. Contractors: The Miller Group Ltd.
Coalfield North, south west of Coalville, Leics: 8.2m tonnes, 182 hectares. Production started 1982 and will be completed 1992. Contractors: C. P. Holdings Ltd.
High Lane, near Newcastle under Lyme, Staffs: 3.1m tonnes, 265 hectares. Production started 1987 and will be completed in 1994. Contractors: Crouch Mining Ltd.
Horsefield, near Essington, Wolverhampton: 0.19m tonnes, 144 hectares. Production started 1991 and will be completed 1992. Contractor: A. F. Budge (Mining) Ltd.
Lounge, east of Ashby de la Zouch, Leics: 4.8m tonnes, 231 hectares. Production started 1986 and will be completed 1991. Contractors: A. F. Budge (Mining) Ltd.
Moira Pottery, Leicestershire (principally a clay site): 0.2m tonnes, 13 hectares. Production started 1989 and will be completed 1993. Contractors: A. F. Budge (Mining) Ltd.
Symon, Lawley, Shropshire: 0.52 tonnes, 71 hectares. Production started in 1991 and will be completed 1993. Contractors: Clay Colliery Co.