Museum Entrance Museum
Museum
Friends of Durham Mining Museum
Events Calendar
e-Books and Books for sale
Photograph Gallery
Document Archive
Main Document Archive
Newspaper Articles
Local Record Extracts
D.M.A. Document Archive
Transactions of I.M.E.
Miners' Welfare
N.C.B. Archive
The Colliery Engineer
The Colliery Guardian
Mine & Quarry Engineering
Mine & Quarry Engineering - Main Index
Mine & Quarry Engineering - Subject Index
Mining Journal
The Science and Art of Mining
Coal Magazine
Coal News
Coke and Gas
Master Name Index
What's new in the site
Mining
Mining History
Colliery Index
Colliery Maps
Company Overviews
Who's Who
Mineral Information
Managers Certificates
Educational Material
Bibliography
Statistics
Workers/Employee Lists
Notes for Family Historians
War Service information
Disasters
Disaster Reports
Names of those killed
Disasters in the 1700s
Disasters in the 1800s
Disasters in the 1900s
Memorials
Awards for Gallantry
On this day ...

Links to other sites of interest
Industrial Heritage Days Out
Former www.pitwork.net web site

Index to site

Contact and address details

Share Page with Social Media

Share on Facebook

Share with Reddit

Share on Delicious

Title Prev Page Return to Index Next Page Title
 
Masthead
June, 1955

Greenside Mine

By C. Connor, M.B.E., A.M.I.M.M.
details are given of recent developments at this famous Westmorland lead property, operated by Greenside Mines Limited

An article by the author appeared in the November and December, 1951, issues of this journal under the title "Greenside Mine, Mining and Milling Practice." As this lead mine is a very old and well established property, it is considered that it would be of particular interest to readers to have information on those events which have taken place both underground and on surface since 1951.

The material in this article is treated under four specific headings, these being (a) exploration, (b) new developments in mining practice, (c) mine safety, and (d) experiments in growing vegetation on the tailings dump.

Exploration

During recent years the company has carried out a very progressive and successful exploratory programme by putting in 7 ft. by 7 ft. drifts along the northern extension of the vein, by crosscutting and by diamond drilling. By far the most satisfactory results have been obtained by the first two methods.

The programme was started in 1947 and has resulted in over 300,000 tons of new ore being found. Table I below shows the development footage and the tons of ore milled for each year during the last eight years. The 1954 figures are from January to November 13. The total development footage during the period was 11,882 ft. and 188,345 tons have been milled.

An extensive diamond drilling programme was carried out from the lowest levels in the mine by drilling inclined holes to intersect the vein in virgin ground at various depths. Unfortunately the information obtained from these bore holes did not justify capital expenditure in this direction. Another major diamond drilling programme took place in the Glencoyne Level 150 ft. below the surface, and the only practical means of reaching this level is by way of the Glencoyne Valley which rises steeply from 480 ft. O.D. to 1,866 ft. O.D. over rough and boggy ground for a distance of 2½ miles.

The equipment used for this work was a diesel engine driving a d.c. generator to provide the motive power for the drill. The total weight of the power unit and the diamond drill was three tons. The equipment was transported by road to the foot of the valley, and a steel sledge was built in the engineering shops on which was mounted a small hoist. The hoist with the exception of the reduction gear was also built on the mine, and the gear ratio between the drive and the hoist drum was so large that it gave the hoist immense power. The diesel engine was direct-coupled to the hoist through a clutch taken from a Morris 16 h.p. car, and with 200 ft. of 5/8 in. rope coiling on to the drum it was made possible to move at a slow speed all the equipment up to the level and back.

In the Glencoyne Level holes were drilled horizontally to the west to intersect a branch vein which had been mined on the lower levels. The vein at this horizon was found to be barren.

New developments in mining practice

Until March, 1954, most of the rock drills in use at Greenside were the heavy automatic feed machines of American manufacture. Due to the effect of devaluation on the purchase of spares, these machines, now obsolete, became very difficult and costly to maintain. Also a considerable amount of trouble was experienced in the mine by drill steel breakage. The steel in use contained 0.7 per cent, carbon and was drilling on average 50.0 ft. into hard rock before breaking. Between January, I 949, and December, 1951, 6,740 ft. of hexagon steel was cut into lengths to make conventional mine drill steel, and each steel drilled 3.0 ft. before being brought to surface for re-sharpening. This amount of steel was used for supplying eight drilling machines per 8-hr. day over the period.

It was therefore decided in February, 1952, to carry out tests with the combination of a light machine, pusher leg, and hard-metal tipped drill steel to decide if drilling efficiency could be maintained or improved at lower cost by the purchase of this type of equipment. The Atlas Diesel Co. Ltd. were consulted and advised the use of their RH 656-2W rock drill, BMK.61-A2 pusher leg and Sandvik Coromant tungsten-carbide tipped drill steel. The results of the tests, which were carried out over a period of twelve months, proved that it would be possible to improve drilling efficiency at a lower maintenance cost. On the strength of this it was decided in March, 1954, to scrap existing heavy drilling equipment and change over completely to the Atlas equipment.

The use of these lightweight rock drills, combined with a pneumatic pusher and hard metal tipped drill steel has been found in practice to have given the following advantages

(a) It has eliminated the setting up and taking down of heavy bars and clamps, and the handling of great quantities of drill steel to and from the working faces. The drillers are in fact drilling 70-80 per cent, of their working shift against 50 per cent, under the old method. The tonnage broken per machine shift has therefore been increased from 21.0 to 28.0 tons in stoping widths between 5.0 and 6.0 ft. In stoping widths above 12.0 ft. this figure has been increased from 51.0 to 70.0 tons.

It is also interesting to note that the rate of driving a 7 ft. x 7 ft. drift with two men and an Eimco loader has been increased from 60.0 ft. per month to 95.0 ft. over the same period. The crew are in fact breaking 10 rounds in an 11-day fortnight against six under the old method. The nature of the rock in which this driving takes place is hard and abrasive.

(b) It was only necessary to purchase one type of machine, the RH 656-2W. With the use of a counterweight it is being used for drilling sinking holes as in underhand stoping, with the BMT. 63A Raising Feed the same machine is also used to drill rising holes as in overhand stoping, and with the BMK. 61-A2 Pusher Leg it is employed for breast stoping and drifting ; thus, it is possible to obtain the best utilisation of the drilling equipment on hand, and, by standardisation, reduce the cost connected with its maintenance.

(c) The lightweight equipment has improved the working conditions of the drillers.

All these points in our opinion combine to make this light drilling equipment superior in performance to the conventional heavier equipment. It gives higher output, which effects a saving in wages, initial cost, compressed air consumption and rock drill upkeep.

On the drill sharpening side there is also a big saving. Prior to 1954 drill steels were transported to surface for the forging of sharp cross bits on the drilling end of the steels. To carry out this operation it was necessary to employ labour to carry the steel in and out of the mine and a skilled drill sharpener for tempering the steel ; to have on hand a compressor producing 200 to 300 cu. ft. of air per minute at 100 lb. per sq. in., an oil furnace for heating and subsequently tempering the steel and a large drill sharpening machine for forging on the sharp edges. With all the care and experience of the drill sharpener, there were occasions when batches of drill steel were taken into the mine that had been tempered either too soft or too hard, with the result that drilled rounds were left uncompleted at the end of a shift because of this defect.

Today, drill sharpening is carried out underground near the working face with an Atlas type LSB.62 drill steel grinder. The machine is operated by the drill doctor, who has ample time to carry out this work as it averages out at two hours per day; this eliminates the use of drill transporters and the surface drill sharpener. The grinder is worked off the underground compressed air system, which in effect also provides a saving of electricity and crude oil that was used in the surface sharpening shop.

Mine safety

There is in being at the mine a Safety Committee consisting of a foreman and one employee from each department, the secretary of the miners' union, and the mine accountant who acts as secretary to the committee. The function of the committee is to provide in every department measures for the safety of the mine employees, and is doing this very successfully by acting on suggestions, and by abolishing any dangerous and irregular practices which may from time to time be reported to it.

It has been possible with the help of the committee to compile a book of safety rules for, the welfare of the workers, which are additional to and not in substitution of any of the rules contained in the Government Regulations. With the committee's sanction it was also possible to add a warning at the end of the book to the effect that any person who breaks the rules is a danger to himself and his fellow workmen, and if after reasonable warning the rules continue to be broken disciplinary action could be taken against the offender. This safety code is a condition of employment which is acknowledged by the employee's signature on a special form.

Medical examination.

All the employees are clinically examined annually at the mine, and are conveyed to Whitehaven every three years-a distance of sixty miles-for radiological examination when a lung X-ray negative is taken.

First aid.

The mine possess a first aid team of nine persons, each being proficient in the application of first aid up to the St. John Ambulance Association medallion standard. Practices are held every two weeks and the St. John Ambulance first aid examination is taken every year. There is on surface a first aid room supplied with hot and cold water and fully equipped with stretchers, oxygen reviving apparatus and medical dressings.

The first aid equipment underground is kept in tubular containers 8 ft. long by 10 in. diameter, manufactured from 16 gauge mild steel by E. C. Theedham Limited, of Dudley. These are partitioned 12 in. from one end to make a compartment for first aid dressings. This compartment also contains a welded-in morphia safe which is fitted with a Yale type lock. The other end contains a stretcher and blankets. There are hinged lids each end with rubber sealing rings and special type locking catches.

Underground fires.

The mine has experienced in its history an underground fire when a considerable amount of carbon monoxide was generated. To reduce the risk of a recurrence the following precautions have been taken

(a) Smoking is not allowed when travelling or working in the shafts.

(b) Miners' acetylene naked flame lamps have been replaced by Oldham miners' electric automatic cap lamps type G.M. with armoured lens glasses, Brytal reflectors fitted with 1 amp. main bulb and also a pilot bulb.

(c) Steel is replacing timber wherever possible for the support of travelling ways and in shaft construction.

(d) The introduction of daily pre-shift inspection.

(e) The organisation of a mine rescue team.

The introduction of daily pre-shift inspection.

A pre-shift inspection commences one hour before the start of a shift after the underground workings have been unoccupied for 15 hours, and is carried out as far as the lowest workings in the mine by a foreman and timberman with a Siebe Gorman CO detector and P.S. Tubes. This will ensure that the mine atmosphere is normal before the shift re-enters, in which case it is considered that should any fire occur while the mine is occupied it will be of a minor nature and will be confined to one part of the mine where it can be extinguished before its dangerous products pollute the whole of the ventilation system. However, to meet the circumstances of a small fire taking place in the underground workings, the decision was taken to organise and equip a mine rescue and fire fighting team which could be called upon to act in such an emergency.

Drawings and Photographs accompanying the article

 

Prev Page Return to Top of Page Next Page

Article reproduced from a copy of the magazine held at National Mining Museum Scotland, Newtongrange, Midlothian.

 

mail
Mail:
Webmaster
Back
Back
Home
Home
Open Government Licence   Contains public sector information licensed under the Open Government Licence v3.0.

Copyright © 1999-2024 by The Durham Mining Museum and its contributors
Registered Charity No: 1110608
Page last updated: 17 Jan 2023

Privacy Policy
 
Terms & Conditions
 
Search
Search
Print
Print