June, 1954 Threlkeld Quarry — Part 2Concluding the description, started last month, of this quarry of the Keswick Granite Co. Ltd., details are now given relating to the tertiary crushing facilities, and the screening and coating plant.Stone from the secondary crushers enters the tertiary crusher building at the top where it is fed on to the main selection screen shown in Fig. 13. This is a single-deck Broadbent screen, the vibrating action being obtained by driving it by a 12½ h.p. Crompton Parkinson motor through an eccentric bearing. Five products are made by this screen, these being +4 in. (the rejects passing over the screen), 4 in.—2¼ in., 2¼ in. —1½ in., 1½ in.—¾ in. and—¾ in. The +4 in. material is fed via an enclosed chute to a 21 in. by 10 in. Broadbent jaw crusher, driven through seven v-belts by a 35 h.p. G.E.C. motor. Discharge from this crusher is passed to a conveyor belt which transfers the stone back to the 24 in. belt running from the secondary crushers, thus recirculating it to the main selection screen. The four undersize portions from the feed screen are all passed by gravity to storage in hoppers each of 10 tons capacity. The —¾ in. product is drawn on to an 18 in. collecting conveyor; this belt runs beneath all four of these hoppers and feeds the 4 ft. Symons fine bowl cone crusher, seen in Fig. 12. This machine was supplied by Fraser and Chalmers Engineering Works who manufactured under licence from Nordberg Manufacturing Company, and is driven through seven v-belts by a 100 h.p. Crompton Parkinson Klosd electric motor. Both the 1½ in.—¾ in. and the 2¼ in. — 1½ in. sizes can be directed into one of three possible routes from this point of the circuit. They may be loaded direct from the hoppers into road transport for sale ; they may be fed on to the feed belt to the cone crusher; or they may be directed to a conveyor belt transferring them to a rotary screen located in the lower portion of the screening tower building. The 4 in.—2¼ in. may either be loaded into road vehicles or sent to the Symons crusher. It will be noted, therefore, that the plant layout has been designed to give great flexibility in that provision is made for all stone to be put through the cone crusher should the varying demand encountered in this industry call for the whole quarry production to be available in the fine sizes, either dry or macadamised. Discharge from the cone crusher, which may be adjusted to give any size from 1½ in. down according to the demand prevailing at the time, is on to a 24 in. wide conveyor belt fitted with a self-loading adjuster and driven by a 15 h.p. electric motor manufactured by the Milo Engineering Works. It is conveyed, at the 17 deg. gradient that is standard on all belts at this plant, to the screening tower. Screen house In this building final grading of the feed from the cone crusher is achieved by the use of three Sherwen magnetic vibrating double-deck screens, supplied by Fraser and Chalmers Engineering Works, and of the type shown in Fig. 14. The initial screen is of 10 ft. by 4 ft. size; this is set to reject the in. rock which is diverted by a chute on to a conveyor belt and returned to the cone crusher. Below this screen are located two 8 ft. by 4 ft. screens of the same type, enabling grading of the feed into ¾ in.—5/8 in., 5/8 in.—½ in., ½ in. — 3/8 in., 3/8 in. — in., ¼ in. ¼ in. — 1/8 in., and 1/8 in. — dust. These products are delivered by gravity to six of the eight 30-ton storage hoppers. The remaining two hoppers are for the stone which has been conveyed direct from the 2¼ in. — 1½ in. and 1½ in. — ¾ in. storage bins under the main selective screen in the tertiary crushing house. These two sizes are conveyed to a rotary screen from which 2¼ in. — 1¼ in. and 1¼ in. — ¾ in. products are made and passed to the storage hoppers. Both screen and feed conveyor are driven by a 15 h.p. Higgs electric motor by means of flat belting. Thus it may be observed from a reference to the plant flowsheet (which was shown on page 196 of our May issue) that dry stone storage is available in this screening house for the six chipping sizes and the two sizes between ¾ in. and 2¼ in. that have not passed the Symons cone crusher. The chipping sizes may be loaded from these hoppers to road transport for sale, or directed to the macadamising plant as required. In the former instance, provision has been made both for the direct loading of individual sizes to vehicles (when a full load of a particular sized stone is needed) and for the delivery of a vehicle load containing mixed sizes to a customer's specification. Seen on the left in Fig. 17 is the conveyor running beneath the six chipping size hoppers, and on to which the required percentages of the individual sizes to make up any specified mix are supplied by chute. This conveyor feeds a chute serving a vehicle loading station at a lower elevation. Coating plant At the present time, the plant operates with a macadamising capacity of 40 tons per hour from two mixers, but as it is appreciated that demand for this product will inevitably increase in the future, a further 30 tons per hour coating plant is in the process of installation. This will place the company in an excellent position for supplying Barber-Greene carpeting machines, and will also serve as a stand-by for a heavy demand for coated stone that may occur in the future. Dry stone from the eight storage hoppers below the screens is graded on to a 20 in. conveyor belt which transports the stone to a chute feeding a 5 ft. diameter by 40 ft. long rotary dryer, supplied by W. A. Hiscox Limited, Derby. Running at between 8 to 10 r.p.m., this dryer, seen in Fig. 18, is fired by a diesel fuel flame, and the stone, heated to the required temperature by means of adjusting this flame, takes 4¼ minutes to traverse the length of the machine. A G.E.C. 60 h.p. electric motor, at present drawing only 35 h.p., is responsible for providing power for driving the dryer, the grading conveyor from the hoppers, a compressor for supplying air to the dryer flame, and a high-speed exhauster fan for extracting dust and smoke from the dryer through a 20 in. diameter pipe. Dried and heated stone is passed from the end of the dryer to a Broadbent elevator, comprising steel buckets mounted on an endless rubber conveyor, and driven by a Higgs 15 h.p. electric motor through four v-belts. This bucket elevator feeds a four compartment storage hopper, located above the mixing installation, via a quarry-built box chute which is readily movable by hand thus enabling stone to be directed to the desired compartment by individual sizes. From this four-way bunker, the stone is passed to a 40-cwt. batch-weighing hopper supplied by Win. Hodgson and Sons Limited, Manchester, and from which 20-cwt. batches of stone are weighed before admission to the mixers. The present installation comprises two 27 cu. ft. Hiscox mixers, each of which is powered by a G.E.C. 30 h.p. electric motor. After mixing, the coated stone is loaded directly to road vehicles, drawn up immediately below the mixer discharge. Fig. 19 depicts one of the mixers and shows the pipelines carrying the binder to the measuring tray prior to addition to the mixer. Binder is circulated from two 3,000-gallon capacity, electrically-heated, thermostatically controlled storage tanks supplied by the Clarmac Engineering Co. Ltd. One of these contains tar, while the other is used for bitumen. The tar is obtained from the coke ovens at Lowca, West Cumberland, of United Coke and Chemicals Co. Ltd. It is brought in by road tanker, arrives at the correct temperature and is transferred either direct to the Clarmac plant or to a lagged storage tank located adjacent to the coating plant building. With the handling of bitumens, however, the company is not so favourably served as the quarry site is out of the area served by the road tanker fleet. Bitumen, of which two brands are currently used — Liquaphalt from Berry Wiggins & Co. Ltd., and Shelphalt from Shell-Mex & B.P. Limited — arrives in rail-tank cars, generally of 3,000 gallon capacity, which are brought up on the company siding alongside a special building provided for the unloading and storage of this commodity. Inside this building, lagged storage tanks providing a total capacity of 8,000 gallons of bitumen are located. A flexible coupling is used for connecting to the rail car, the contents of which are then pumped, with compressed air assistance, to storage. The pump installed for this purpose is of Stothert and Pitt manufacture and is driven by a 1 h.p. Brook electric motor; the compressor is powered by a 4 h.p. Brook motor. A vertical steam boiler is used on those occasions when steam heating of the storage tanks may be necessary to reduce the viscosity of the bitumen. For transport from these tanks to the Clarmac plant, which is a distance of some 1,000 ft. away, the quarry employs its own road tanker. The new coating plant at present being installed will employ almost identical equipment to that already in use, and it is understood that a 100 h.p. electric motor is to be used for driving dryer, elevators and mixers. Concrete storage bins are being constructed for the dry sized stone for this coating plant extension and the transfer of stone from the screening house storage to these hoppers will be by conveyor belt. Stockpile An extensive stockpile, part of which is visible in Fig. 20, is maintained on that section of the company's property that lies between the plant and the railway line. The sloping contours of the countryside lend themselves to the favourable formation of piles in terraces. Graded stone of all sizes is stocked according to demand, transport from the screen house hoppers being performed by the two works and stocking lorries, both Ford Thames 5-tonners. Reclamation from the stockpiles is undertaken by two machines. Fig. 22 shows the Smith Rodley 3/12, powered by a Fowler 3-cylinder diesel engine and equipped with a 5/8 cu. yd. bucket. The second machine is a new Muir-Hill overhead loader which has recently been installed replacing an older model of the same manufacture (E. Boydell and Co. Ltd.), which had given the company good service. Mention has already been made of the company's railway siding, and when required, stone may be despatched from the quarry in standard railway wagons. The desired material is drawn from the hoppers into the works and stocking lorries, taken down to the siding and tipped into chutes feeding the rail trucks. Electrical Power for the quarry operations comes from the North-Western Electricity Board's grid. Supplied at 11,000 V, it is fed to a 500 kVA transformer and brought down to 400/440 V at the company's substation and this voltage is used for all electric drive motors throughout the whole plant ; a view of the inside of this station, showing part of the switchgear supplied by George Ellison Limited, is shown in Fig. 23. All the major electrical installation work at the plant was performed by the N.W. Electricity Board, while minor work and all routine maintenance are carried out by the quarry electrical staff. A point of interest in the operation of the plant is the Klaxon system of signalling whereby the whole plant can be controlled from any one point, and any directions such as the re-routing of stone in the plant circuit may be quickly relayed by these means. Working in conjunction with this form of control are colour signal lights. At the time of our visit, a new Metrovick 750 kVA, 3-phase, 50-cycle transformer was noted awaiting future installation for providing a larger transformed capacity should this be found necessary when the new tar plant is brought into operation. The present average electrical load approximates to 450 amps at 440 volts. Compressed air Compressed air for the quarry face operations and other purposes throughout the plant is supplied by a type XVH-2X two-stage machine supplied in 1938 by Ingersoll-Rand Co. Ltd. Operated at 500 r.p.m., this machine delivers 543 cu. ft. of free air per min. at a pressure of 90 lb. per sq. in. through a 4 in. line to two vertical receivers 4 ft. in diameter by 10 ft. high ; it is driven through eight v-belts by a 100 h.p. G.E.C. slip-ring induction motor. Fig. 24 shows the installation and illustrates the general arrangement of the machine. The vertical, low pressure, cylinder has a bore of 13½ in. with an 8 in. stroke, while the horizontal, high pressure cylinder uses a bore and stroke of 8 in. Compressed air is led to the quarry through a 3 in. diameter pipeline, while a 2 in. line is provided at the top of the working face. Air from here is led to the machines by 1 in. air hose, and at any one time four drills on the face and two on pop-holing may be operating. Delivery points are also provided throughout the plant for pneumatic equipment. In this category may be mentioned an Ingersoll-Rand sump pump used for emptying conveyor sumps, the Climax steel sharpener in the blacksmith's shop and pneumatic spray painting equipment. Production Average production from the quarry during the peak season reaches 500 tons per day, of which 40 per cent, is in the form of coated stone. Main sales are to the Cumberland County Council and local authorities and a distribution of markets may be taken as roughly half to road construction and maintenance programmes and half to building and contracting work. Apart from the company's own road haulage fleet, hired transport is often called in to deal with peak demands and building contractors are found generally to prefer collecting their own stone requirements. All outgoing vehicles are directed to the company's weighbridge, which is equipped with a 20-ton Pooley dial weighing machine. The total labour strength comprises 68 men, which includes eight administrative personnel; of this overall figure, 30 are truck drivers, five quarrymen, five excavator operators, two men on secondary blasting, while the plant, including the coating section, is operated by seven men. Labour relations between men and management are good; the majority of the labour force is domiciled in the 40 houses owned by the company and located on the quarry site, although some men who live at Keswick are collected by truck every day. The shifts worked during the summer months are 7.30 a.m. to 4.30 p.m. on weekdays, and 7.30 am. to noon on Saturdays. General Under Town and Country Planning, the company has many commitments, located as the quarry is in one of the more beautiful parts of the country. In order to make the operations blend in with the surrounding scenery one stipulation that is required is that all plant buildings be painted green and the exteriors maintained in good condition. Another activity under this broad heading is the planting of beech and sycamore trees to screen the dirt tip. Depressions in the ground are filled in, after which the area is seeded and planted wherever practicable. A plantation of fir trees has been put in to the east of the plant with the intention of providing in the future a screen to operations. Adequate repair and maintenance facilities are provided for the servicing personnel. The fitting shop is equipped with a normal complement of lathes, drills and other power tools; both gas and electric welding equipment is available, the latter being a Murex portable set. In the garage, two fitters are employed for maintaining the truck fleet including all repair work up to engine changes, and it was noted that the company operates its own breakdown vehicle. Stores are kept individually by departments. Acknowledgments We would like to take this opportunity of thanking Mr. I. Harvey Davies, M.I.Min.E., Director and General Manager of the Keswick Granite Co. Ltd. for permitting us to view and describe this interesting plant, and Mr. T. Graham, his assistant, who was good enough to devote his time to showing us the property and supplying much of the information contained in this article. Drawings and Photographs accompanying the article
Article reproduced from a copy of the magazine held at National Mining Museum Scotland, Newtongrange, Midlothian.
|
![]() |
||||||||
|
Mail: Webmaster |
Back |
Home |
Copyright © 1999-2024 by The Durham Mining Museum and its contributors Registered Charity No: 1110608 Page last updated: 17 Jan 2023
|
Search |
|
|||