Museum Entrance Museum
Museum
Friends of Durham Mining Museum
Events Calendar
e-Books and Books for sale
Photograph Gallery
Document Archive
Main Document Archive
Newspaper Articles
Local Record Extracts
D.M.A. Document Archive
Transactions of I.M.E.
Miners' Welfare
N.C.B. Archive
The Colliery Engineer
The Colliery Guardian
Mine & Quarry Engineering
Mine & Quarry Engineering - Main Index
Mine & Quarry Engineering - Subject Index
Mining Journal
The Science and Art of Mining
Coal Magazine
Coal News
Coke and Gas
Master Name Index
What's new in the site
Mining
Mining History
Colliery Index
Colliery Maps
Company Overviews
Who's Who
Mineral Information
Managers Certificates
Educational Material
Bibliography
Statistics
Workers/Employee Lists
Notes for Family Historians
War Service information
Disasters
Disaster Reports
Names of those killed
Disasters in the 1700s
Disasters in the 1800s
Disasters in the 1900s
Memorials
Awards for Gallantry
On this day ...

Links to other sites of interest
Industrial Heritage Days Out
Former www.pitwork.net web site

Index to site

Contact and address details

Share Page with Social Media

Share on Facebook

Share with Reddit

Share on Delicious

Title Prev Page Return to Index Next Page Title
 
Masthead
May, 1954

Beckermet Mine — Part 2

In this second article we conclude the description of the operations of this West Cumberland hematite mine. Last month reference was made to the geology, shafts and mining methods.

All ore from both No. 1 and No. 2 shaft areas is concentrated for hoisting at the No. 1 shaft-bottom horizon shown in Fig. 13. Ore hoisting is also performed at the Haile Moor shaft. For shunting and marshalling duties around these two shaft bottoms, two 20/28 b.h.p. Simplex diesel locomotives supplied by Motor Rail Limited of Bedford of the type as shown in Fig. 14 are employed. These locomotives weigh 2½ tons, and are fitted with two cylinder Dorman engines, equipped with C.A.V. fuel pumps; they are often used additionally for collecting ore trains from well-ventilated headings.

Main haulage from the top of the Sheepfields dip to No. 1 shaft, a distance of 900 yards, is performed by an 8-ton 80 h.p. trolley locomotive. This electrified haulage will be extended, in the future, to areas now under development so that this system will virtually be responsible for collection from a two mile haulage road. The locomotive is manufactured by the Goodman Company of America, and was supplied by the Distington Engineering Company who were responsible, with the mines' electrical staff, for the complete trolley installation* with the exception of the B.T.H. 200 kW rectifier. The transformer and rectifier station is supplied with 3,300 volts a.c., and the supply to the single trolley wire, with negative return through the rail, is at 250 volts d.c.

A horizontal cable-reel drum holding 600 ft. of single-core cable is fitted to the locomotive thus enabling it to operate within this distance away from the trolley wire, provided the rails in the section to be traversed are bonded. When required, the cable on the drum is connected in to a socket, installed on the side of the haulage; the drum, which pays out, or takes in, cable as the locomotive proceeds, is geared to the motor so that there is never any possibility of slack cable getting under the wheels.

Ore collection from development faces and from areas not served by the trolley system, is performed by a fleet of seven B.E.V. battery locomotives, supplied by Wingrove and Rodgers Limited, Acornfield Road, Kirkby Trading Estate, near Liverpool, England.

Of these locomotives, six are of the two-motor type W.227, weighing approximately three tons and having a nominal hauling capacity of 25 tons. One of these models is seen hauling an ore train at No. 1 shaft in Fig. 16. A 2 ft. 6 in. wheelbase is used, and this locomotive will negotiate curves of 12 ft. minimum radius. The maximum speed on level track at the normal drawbar pull of 700 lb. is 4 m.p.h. Exide Ironclad batteries are fitted, of 30 cells (60 volts) giving an output of 290 amp. hrs.

The seventh B.E.V. locomotive, which is employed at Haile Moor, is the one-motor type W.217 of approximately 30 cwt. weight and capable of a haul of 10 tons with a rated drawbar pull of 300 lb. A 2 ft. wheelbase is employed, making curves of 10 ft. radius negotiable. In this case, the Exide Ironclad batteries provided are 24 cell (48 volts) and 193 amp. hrs. capacity.

A battery-charging station is located near No. 1 shaft bottom with facilities for the charging of two batteries at the same time, as duplicate equipment of the English Electric Co. Ltd., of Wolverhampton is fitted throughout. Feed for this station is at 550 volts a.c., coming from the main underground transformer sub-station located in the pump-room. Locomotive haulage has in recent years replaced rope haulage on all the main roadways. Mention should be made that this form of transport is still employed for subsidiary haulages ; for instance, in the Sheepfields area, a 50 h.p. haulage is being operated on a 1 in 10 dip, while at another dip working, a Becander 35 h.p. is being used.

It has been mentioned previously that no hoisting of ore is performed now at No. 2 shaft. All hematite won in this area is transferred to No. 1 shaft by means of a 26 in. belt conveyor 1,440 ft. long running down from the No. 2 shaft workings. The No. 2 shaft ore is brought to the head of the conveyor in the standard mine tubs, which are run on to the end-tipping hand operated tipper seen in Fig. 18. The ore falls into a chute from which it is fed by a shaking conveyor, which evens out the loading, on to the belt conveyor. At the feed end of the belt, a loose rubber flap has been installed to prevent large stones from starting to roll down the length of the conveyor. At the No. 1 shaft end, the belt feeds into mine tubs as may be seen taking place in Fig. 20. This installation handles 200 tons per shift.

Pumping

The present quantity of water being pumped from underground is 1,500 gallons per min.; at the time of our visit, we were informed that the recent sealing-off of one of the surface boreholes intersecting the workings in the Sheepfields Dip area had reduced the pumping load by some 800 g.p.m., coming from the sandstone rocks.

The main underground pumping station, located near No. 1 shaft bottom has facilities for handling a maximum volume of 3,800 g.p.m. Equipment installed comprises four centrifugal turbine pump sets delivering through rising mains of 10 in. and 8 in. diameter against a head of 1,310 ft. and discharging into a drainage level whence the water flows into the River Kirkbeck. Before the provision of these surface water-disposal arrangements, the three pumps then in use had to deliver a vertical height of 1,440 ft.

Two of the sets are Mather and Platt 8-stage Plurovane units direct-coupled to 475 h.p. MetroVick electric motors, each rated for a delivery of 800 g.p.m. The other two sets are 1,500 g.p.m. 7stage Spiroglide multi-stage units manufactured by the Harland Engineering Co. Ltd., who also made the direct-coupled 1,475 r.p.m. A.V. type slip-ring motors; the first set supplied to this mine was of 875 h.p., this being designed for the 1,440 ft. head, while the latest set, shown illustrated in the right foreground on page 204 is rated at 850 h.p.

Subsidiary electric-driven pumps are located in the Sheepfields workings; these comprise three Mather and Platt Plurovane units, two of which are supplied with 3,300 volts and are rated at 1,000 gal. per min. against a 700 ft. head and requiring 310 b.h.p. while the third set, having a capacity of 600 gal. per min., is supplied with 550 volts. These pumps were used for dewatering the mine in 1945 when No. 1 shaft became flooded, and are now operating in the Sheepfields area with two impellers removed due to the relatively light duty now required of them; they were originally installed in this section of the mine for the dewatering of the area. Other auxiliary pumps comprise a 150 gal. per min. Harland and a 200 gal. per min. Pulsometer; both of these are currently employed on drainage duties from two dip development workings.

Ventilation

The main ventilation underground is natural, No. 1 shaft being downcast, while No. 2 is the upcast shaft; mention was made in last month's article of the Haile Moor shaft wherein both upcast and downcast conditions are created by means of the concrete partition wall. Mechanical auxiliary ventilation through tubing is employed when driving long dead-end developments or when working conditions require its installation; for example, a 5,000 c.f.m. fan exhausts through 15 in. tubing from the Sheepfields workings to a T-connection that links up with air exhausted from the Robert Bridge development (utilising a 12 in. ventilation pipe) at a second 5,000 c.f.m. fan shown in the illustration at Fig. 19. This fan is a 35 in. diameter Cupola fan, type C, supplied by Davidson and Co. Ltd. of Belfast and powered through vee-belts by a 50 h.p. motor.

In the past silicosis has been a scourge in this mining field, and this fact undoubtedly has had its affect on the recruitment of labour to the mines in recent years. However, in 1932 the Beckermet Mining Co. Ltd. together with two other local mining companies formed an insurance company employing their own doctor. By introducing a medical examination for all men entering the mines, and by taking dust prevention measures underground, the management emphatically state that no man starting since that date has or will contract the disease.

Production and labour

The mine operates one production shift (6 a.m. to 2 p.m.); the 2 p.m. to 10 p.m. shift is confined to repair men while the night shift has overmen carrying out examination work. The total strength at all three shifts comprises 340 men, 250 of whom are employed underground. A figure of 78 cwt. of hematite per manshift is quoted as the mine average per face worker at Beckermet Nos. 1 and 2 shafts and 110 cwt. per man-shift at Haile Moor.

Every job in the mine that can be conveniently placed on contract is put on a bonus system. Due to changing conditions affecting the work, rates for these jobs are reviewed fortnightly by the manager who bargains directly with the "company"; this is a term given to a group of miners, generally two or three, working a particular heading; these men are allotted a tally number, and a check is maintained on all ore loaded out by them by means of small wooden boards bearing the "company" number placed in each tub. In Fig. 20, the tub shown in the left foreground has one such tally marker showing on top of the ore load.

One of the mines management's chief difficulties is that of shortage of labour both trained and untrained, many men preferring to work in the neighbouring industrial projects. The company is, therefore, striving to make the mines as safe and clean as possible in order to attract recruits to the industry. It should be mentioned that there is a core of miners who have been with the company a number of years and we were impressed by the excellent relations that exist between management and miner.

Hoisting

The No. 1 shaft winding engine was put into service in 1914 initially as a twin-cylinder steam installation; however, during the Easter week in 1953 the hoist was converted to electric power operation by Robeys of Lincoln, England, who manufactured the original hoist and Metropolitan-Vickers Electrical Co. Ltd., who supplied the new motors. The hoist utilises a cylindro-conical drum, with diameters of 8 ft. 6 in. rising to 11 ft. The original drum and brakes are now employed with twin 475 b.h.p. induction motors, operating through reduction gearing, while the hoist employs the dynamic braking principle. Hoisting ropes used are of 1 1/8 in. diameter locked-coil construction, while the rope speed is set at 2,530 ft. per min. In the hoisting cycle, ten seconds are allowed for changing tubs (two per cage) and fifty seconds for the 1,400 ft. wind, enabling a hoisting rate of 120 tons of hematite per hour.

The No. 2 shaft hoist is the original Robey steam winder delivered in 1914. This winder is fitted with a conical drum 11 ft. by 8 ft. diameter, powered by two cylinders each of 22 in. diameter with a 40 in. stroke, supplied with steam at 150 lb. per sq. in. The steam-raising plant here, erected between 1915 and 1917, comprises three Lancashire boilers each of 8 ft. diameter and 30 ft. long, with an evaporation rate of 7,000 lb. of water per hour.

The Haile Moor winder was supplied by M. B. Wild & Co. Ltd. of Birmingham and put into service during September, 1941. Employing a single drum of 10 ft. diameter, 8 ft. in width, a rope speed of 600 ft. per min. is employed for hoisting the single-deck cages in balance. As is standard at all three shafts, 1 in. ropes are fitted, and the cage is loaded with two mine tubs. The hoist is powered by a 160 h.p., 3,300 volt Metrovick motor driving through double reduction gearing giving a total ratio of 32.7 :1. Parallel motion swung-post type brakes of 8 in. path width are fitted, operating by oil pressure. A special feature of this winder is that rope reels are fitted on the outside of the drum to permit easy adjustment of winding ropes, e.g. shortening, when necessary; one of these is visible in Fig. 23.

Electrical Supply

Power is brought into the No. 1 shaft power-house, located in the compressor-house building, at 3,300 volts from the North Western Electricity Board's 11,000 volt grid. Power is used at 3,300 volts for the surface hoists and compressors, while a shaft feeder takes the supply to the underground pumproom. All four of the main pumping sets and the two 1,000 g.p.h. Sheepfields pumps operate on 3,300 volts, while the main underground transformer station, located in the pump-room, supplies all other underground electrical installations with 550 volt a.c.

In the surface power-house, a new control panel supplied by British Thomson-Houston Co. Ltd. for the main 3,300 volt feed was in position, but not connected at the time of our visit. The total peak electrical load approximates to 2,000 kW per hour.

Compressed air

Compressed air for the pneumatic equipment underground is supplied to the working faces at an approximate pressure of 80 lb. per sq. in. No. 1 shaft carries a 10 in. air main in the pipe compartment, and this line feeds underground operations both in this area and in the No. 2 shaft workings while an extension is brought up No. 2 shaft to supply the surface equipment here; this comprises the boiler house, shops, and drill sharpening equipment. Prior to the relatively recent introduction underground of tungsten carbide steel, all mine steels, which were of the integral type, were re-sharpened here.

The compressor house, at No. 1 shaft surface, houses three two-stage vertical reciprocating compressor installations supplied by Alley and MacLellan Limited, Glasgow, which provide a total of 2,700 cu. ft. of air per min. at 85-90 lb. per sq. in. pressure. These may be seen in Fig. 22 direct-coupled to 3,300 volt electric motors. The unit shown on the right is rated at 1,500 cu. ft. of air per min. and is driven by a 350 b.h.p. Metrovick synchronous induction motor at 375 r.p.m., while the other two units supply 600 cu. ft. of air per min. each, and are powered by English Electric 130 h.p. motors operating at 488 r.p.m.; the compressor shown on the extreme left was installed in 1953 and is equipped with a built-in intercooler. Delivery is to air receivers, 6 ft. in diameter by 30 ft. in length, peak load occurring around 9 a.m., when it is found necessary to operate all three machines.

The Haile Moor workings are supplied with pneumatic power from a surface installation located at the top of that shaft. Provision is made for a total delivery of approximately 1,700 cu. ft. of free air per min. from the three units located in this compressor house. The newest installation here is an Ingersoll-Rand, two-stage air-cooled model 75-H B type 40 rated at 396 cu. ft. per min. at 100 lb. per sq. in. This unit is driven through vee-belts by a Metrovick 90 h.p. motor. Seen in Fig. 24 are the other two compressor units at Haile Moor each of which is a two-stage vertical machine delivering 600 cu. ft. of free air per min. On the left may be seen an Alley and MacLellan series 18B, size No. 6, two stage unit driven through vee-belting by a Metrovick 160 h.p. electric motor, while the compressor shown on the right in our illustration, supplied by Fullerton, Hodgart and Barclay Limited, is belt-driven from a 150 h.p. motor supplied by the Brush Electrical Company of Loughborough, England.

Surface layout

All the hematite production is shipped as broken underground (approximately 12 in. cube as a maximum size) in 16-20 ton railway wagons from the No. 1 shaft area to the Workington works of the United Steel Co. Ltd. for processing into steel by the acid Bessemer process. At both No. 1 and Haile Moor shafts, all production is hoisted in mine tubs in single deck cages, a cage load comprising two tubs giving a payload of 2 tons per wind.

At No. 1 shaft, tubs are raised to the decking level, manhandled from the cages and allowed to run to a Simplex 4 ft. 6 in. diameter single-tub tippler, manufactured by John Wood and Sons Limited, Wigan. The empty tubs are returned to the other side of the shaft, by means of a creeper. The ore falls from the tippled tub on to a chute feeding a shaking conveyor that evens out the flow on to a 48 in. wide conveyor supplied by Blantyre Engineering Co. Ltd. of Scotland. The belting was manufactured by the Dunlop Rubber Co. Ltd., while the conveyor is driven through Radicon gearing by a 10 h.p. Metrovick electric motor. This belt, also serving the function of an inspection belt for mine scrap, timber, etc., transfers the ore to the building shown illustrated in Fig. 25, where it is fed to a chute in which a movable deflector plate is fitted; by this means ore is deflected into railway wagons while waste, when being handled, can be loaded into 3 cu. yd. dumpers for disposal to the rock dump. These vehicles are manufactured by Aveling-Barford Limited, and are fitted with 31 b.h.p. Fordson 4-cyl. petrol engines.

At the Haile Moor mine, the basic arrangements for handling ore and waste are somewhat similar to those previously described at No. 1 shaft. The title block on page 148 of our April issue shows the headframe and conveyor galleries, while a small idea is also given in this photograph of the extensive efforts taken by the management not only to prevent the mine buildings from being an eyesore to the surrounding countryside, but to provide a pleasing layout of lawns, flower beds and shrubs. This policy is considered to be well worth the effort when related to relations with both employees and local authorities. Waste rock is transferred to a second Aveling-Barford 3 cu. yd. dumper which transports it to the dump. The top of this dump is kept level, and as it is extended, soil is added and the ground seeded with grass. Thus the lawn shown on the right of the picture is continuously being extended behind the advancing rock fill.

Fig. 26 shows a general view at the decking level at this shaft, with the empties side of the shaft in the foreground. In the right background may be seen empty tubs being raised up the creeper incline, having come from the Woods of Wigan tippler shown illustrated in Fig. 27. Ore is transferred by chute and 10 h.p. shaking feeder to the main 52 in. conveyor where men are employed on inspection duties checking for scrap, and tramp iron. This belt rises 15 ft. in 120 ft. and is driven by a 10 h.p. motor through Croft reduction gearing. At the end of the belt, the ore is discharged into storage hoppers at the feed end of the aerial ropeway that transports the material 1. 2 miles to the No. 1 shaft area for loading into rail wagons.

The ropeway is a conventional bi-cable installation of British Ropeway Engineering Co. Ltd., employing a 5 in. diameter half locked coil track rope on the fulls side with a 3½ in. similar type of rope for the empties. The loading station hoppers with one of the buckets of 18 cwt. ore capacity are shown in Fig. 28.

Unfortunately local authorities would not sanction the ropeway being erected in a straight line from Haile Moor to Beckermet No. 1 shaft, and a 120 deg. angle station has had to be incorporated at a point approximately one third of the way from the loading end. A further requirement was that the empty buckets should not traverse the countryside upside down and an automatic righting device has, therefore, been supplied. A minimum figure for the spacing of the buckets is given as 60.7 yards, while a rope speed of approximately 230 ft. per min. is attained with the 5/8 in. diameter 6/7 hauling rope powered by a 10 h.p. motor through reduction gearing. The ropeway was designed to handle 80 tons of ore per hour. Fig. 29 shows the receiving end of the installation supplied by British Ropeway Engineering Co. Ltd., with storage facilities and twin chutes for loading into railway wagons.

Acknowledgments

We would like to thank the United Steel Co. Ltd. for granting permission for our visit to this interesting property; we would also like to acknowledge the help given by Mr. J. R. Gunn, mine agent and Mr. J. S. Booth, manager, who devoted time in showing us the property and supplying much of the data used in this article.

* "Trolley Locomotive Installation at Beckermet," by J. R. Gunn. Colliery Engineering. vol. XXIX. No. 342. p. 314.

Drawings and Photographs accompanying the article

 

Prev Page Return to Top of Page Next Page

Article reproduced from a copy of the magazine held at National Mining Museum Scotland, Newtongrange, Midlothian.

 

mail
Mail:
Webmaster
Back
Back
Home
Home
Open Government Licence   Contains public sector information licensed under the Open Government Licence v3.0.

Copyright © 1999-2024 by The Durham Mining Museum and its contributors
Registered Charity No: 1110608
Page last updated: 17 Jan 2023

Privacy Policy
 
Terms & Conditions
 
Search
Search
Print
Print