An inrush of water, though not from old workings, took place on the 20th May, at Deaf Hill Colliery, County Durham.
The management proposed winning a new area of coal in the Harvey Seam and to do this were driving two headings before drifting through the Butterknowle Dyke. One of the headings had reached a point about 15 yards from the fault. On the 20th May a deputy went into this heading to make an inspection before the workmen came in, and found that a feeder of water estimated to be about 600 gallons per minute was coming from the roof at the face of the heading. The water was directed into some dip workings. Part of the water passed to a collecting dam from where it was conveyed to the shaft by three ranges of pipes, the diameters of which were 4, 5 and 6 inches respectively. It was soon found that the capacity of these pipes was insufficient for the quantity of water given off and the dip workings then became flooded. Ultimately the water passed through some old goaf into the Busty Seam workings, which afforded standage for a considerable time. With a view to increasing the capacity of the standage a 6-feet wood dam was built in the drift between the Harvey and Busty Seams. Unfortunately this dam was not proof against the pressure of water and, as a result, the water came through in large quantities and the saving of the mine was entirely dependent on the pumps.
Efforts were then made to dam off the feeder and a brick dam was built in each of the two headings. These dams were not properly constructed and did not stop the water. About a week after the inrush two wood dams were erected, but as the same amount of skill in construction was displayed these also were of little use. By this time all the available standage in the workings was exhausted and the water was running to the shaft. The pumping arrangements were inadequate to deal with the quantity of water and the situation became very serious. About the middle of July another pair of wood dams of excellent design and material were erected, but on completion good joints had not been secured between the iron pipes through them and the wooden segments. A Durham contractor was then called in and by the 7th September he succeeded in stopping the water with two heavy cement dams. The pressure upon the dams was registered at 125 lbs.
As regards the cause of the inrush there seems no reason to doubt that the water came from the limestone series; the heading must have struck a fissure extending up into the limestone.
Source: 1919 Mines Inspectors Report (Cmd 925)