Museum Entrance Museum
Museum
Friends of Durham Mining Museum
Events Calendar
e-Books and Books for sale
Photograph Gallery
Document Archive
Main Document Archive
Newspaper Articles
Local Record Extracts
D.M.A. Document Archive
Transactions of I.M.E.
Miners' Welfare
N.C.B. Archive
The Colliery Engineer
The Colliery Engineer - Main Index
The Colliery Engineer - Subject Index
The Colliery Guardian
Mine & Quarry Engineering
Mining Journal
The Science and Art of Mining
Coal Magazine
Coal News
Coke and Gas
Master Name Index
What's new in the site
Mining
Mining History
Colliery Index
Colliery Maps
Company Overviews
Who's Who
Mineral Information
Managers Certificates
Educational Material
Bibliography
Statistics
Workers/Employee Lists
Notes for Family Historians
War Service information
Disasters
Disaster Reports
Names of those killed
Disasters in the 1700s
Disasters in the 1800s
Disasters in the 1900s
Memorials
Awards for Gallantry
On this day ...

Links to other sites of interest
Industrial Heritage Days Out
Former www.pitwork.net web site

Index to site

Contact and address details

Share Page with Social Media

Share on Facebook

Share with Reddit

Share on Delicious

Title Prev Page Return to Index Next Page Title
 
 Colliery Engineering June, 1958 

Temporary lining

The shaft sides are supported by a temporary lining consisting of corrugated sheets, backing deals, wedges and skeleton rings. The skeleton rings are supported on hangers from the ring above, and the segments are joined together by curved fishplates;. the first ring in a new section of temporary lining is held by hangers from the lowest section of permanent lining.

After the skeleton ring is in position, the corrugated sheeting and backing deals are placed behind it with the sheeting next to the shaft wall. Wedges are then driven in between the deals and the ring to make the whole rigid. The rings are placed at intervals of 4 ft.

Verticality is maintained by a centre-line which was positioned after the first 60 ft. had been sunk. It was at this stage that the National Coal Board established the shaft centre and built check points on concrete bases some distance from the shaft.

The centre line itself consists of a multi-stranded wire 1/8 in. in diameter passing through a brass bush at the shaft top. As two hoppits are in use, no centre arm is required; and the centre line is taken round an 8 in. diameter pulley after passing through the brass bush. The line is raised and lowered by a small Holman air-winch.

By using the centre line it was also possible to check the survey of the pilot hole and the accuracy of the borehole instrument was thus verified.

At a depth of 306 ft., freezing tubes No. 23 and 8 were exposed whilst cutting out a wedge for No. 5 length. Measurements were taken from the centre of these tubes to the centre line, and the actual position of the tubes agreed with those determined by the Gebhardt instrument. If an error had occurred in the plotting of these holes, they might easily have been damaged by shotfiring which would have led to a serious loss of brine. The danger in this case was overcome by shutting-off the two tubes at the surface.

Mucking

As stated previously, double-hoppit winding is employed. The hoppits have a capacity of 19 cubic yards and the suspension bow is mounted at the top instead of in the conventional position on the sides. This method of suspension greatly facilitates mechanical mucking as the bow can be lowered down the side of the hoppit, out of the way.

For the first two weeks, mechanical mucking was carried out by a grab slung from the walling scaffold and, although the results were reasonably successful, it was felt that the large diameter of the excavation (30 ft.) and the non-uniform fragmentation of the debris in the frozen ground were not altogether suitable for this type of mucker. An Eimco Rocker-shovel was then installed and has proved to be very satisfactory.

At the time of writing, the shovel was able to load the dirt faster than the winding engine could cope with it, and in the frozen ground the output was increased from 23 cubic yards to 53 cubic yards per manshift underground.

The Eimco shovel installed at Wearmouth is basically a standard compressed-air 621 Rocker-shovel. This machine is specially designed for manoeuvrability and ease of operation when working in confined spaces. It is constructed of alloy steel and the two 12½ h.p. traction motors give a thrust of over 4,000 lb. The traction motors are independently controlled, thus allowing the machine to spin turn, if necessary. The four slinging holes on the machine, for raising it out of the shaft during shotfiring, etc., are mounted directly above its centre of gravity; this reduces any tendency to swing in the shaft. One of the main features of the machine is the ten-second loading cycle which results in it being able to cope with up to three tons of dirt per minute.

A brief specification of the 621 shovel is given below —

Overall width 30 in.
Overall width without platform 54 in.
Overall length, bucket withdrawn 33 in.
Overall length, bucket extended 93 in.
Overall height, bucket lowered 34 in.
Headroom 96 — 102 in.
Discharge height 58 — 66 in.
Discharge distance 21 — 27 in.
Hull projection 7 in.
Air pressure range 50 — 125 lb. per sq. in.
Air hose 1½ — 2 in.
Complete loading cycle 10 sec.
Bucket capacity, approx. 1/3 cubic yard
Weight 7,800 lb.
Air consumption 300 — 400 cu. ft. per min.
No. of air motors 3

The bucket on the Eimco shovel at Wearmouth is specially designed so that as the machine moves forward, it automatically digs below track level; this digging action is assisted by two bucket teeth welded to the bottom.

Fig. 14 shows the rocker shovel at work in the shaft bottom. The hoppits are positioned approximately on descending; the shovel moves forward into the muck, picks up a load and then reverses with the bucket in the carrying position. The machine manoeuvres up to the hoppit, and the cycle is completed with the bucket discharging overhead into the hoppit.

The machine has a higher gear ratio in the track gear train to make it more powerful when digging and the upper deck gear train which controls the bucket movement is also higher than standard for the same reason.

When originally installed, the machine had flat-track shoes but these were later modified to give a full grouser track with the result that better traction was obtained.

By using the Eimco shovel for mechanical mucking in the shaft-bottom instead of hand mucking, it has been estimated that there has been a saving of 8-10 men per shift.

This modified machine for shaft mucking duties was the outcome of considerable experimental work carried out by the manufacturers.

(To be continued)

Drawings and Photographs accompanying the article

 

Prev Page Return to Top of Page Next Page

Article reproduced from a copy of the magazine held at National Mining Museum Scotland, Newtongrange, Midlothian.

 

mail
Mail:
Webmaster
Back
Back
Home
Home
Open Government Licence   Contains public sector information licensed under the Open Government Licence v3.0.

Copyright © 1999-2024 by The Durham Mining Museum and its contributors
Registered Charity No: 1110608
Page last updated: 17 Jan 2023

Privacy Policy
 
Terms & Conditions
 
Search
Search
Print
Print