Museum Entrance Museum
Museum
Friends of Durham Mining Museum
Events Calendar
e-Books and Books for sale
Photograph Gallery
Document Archive
Main Document Archive
Newspaper Articles
Local Record Extracts
D.M.A. Document Archive
Transactions of I.M.E.
Miners' Welfare
N.C.B. Archive
The Colliery Engineer
The Colliery Engineer - Main Index
The Colliery Engineer - Subject Index
The Colliery Guardian
Mine & Quarry Engineering
Mining Journal
The Science and Art of Mining
Coal Magazine
Coal News
Coke and Gas
Master Name Index
What's new in the site
Mining
Mining History
Colliery Index
Colliery Maps
Company Overviews
Who's Who
Mineral Information
Managers Certificates
Educational Material
Bibliography
Statistics
Workers/Employee Lists
Notes for Family Historians
War Service information
Disasters
Disaster Reports
Names of those killed
Disasters in the 1700s
Disasters in the 1800s
Disasters in the 1900s
Memorials
Awards for Gallantry
On this day ...

Links to other sites of interest
Industrial Heritage Days Out
Former www.pitwork.net web site

Index to site

Contact and address details

Share Page with Social Media

Share on Facebook

Share with Reddit

Share on Delicious

Title Prev Page Return to Index Next Page Title
 
Masthead
April, 1958

Durham Coalfield Reconstruction

Excellent progress continues to be made with the reconstruction programme in the Durham coalfield. The programme, though costly, is vitally necessary to maintain output in a coalfield where many collieries are 80 to 100 years old, and where nearly half the seams are less than 2 ft. 6 in. thick.

Broadly speaking, a major reconstruction is one in which capital expenditure exceeds £250,000, and during the past year the following major reconstructions were substantially completed: Wardley-Usworth, Boldon, Herrington, Horden, Fishburn, and Beamish Mary, while the following are expected to be completed this year: Clockburn-Marley Hill, Easington and Thornley.

In addition, major reconstructions are in progress at Wearmouth, Westoe, Seaham, Dawdon, Vane Tempest, Hawthorn, Elemore, Silksworth, Shotton, East Hetton, Thrislington, Dean and Chapter, Handen Hold, Morrison Busty and Ryhope.

Considerable progress has been made with the Hawthorn combined mine, the largest scheme in the coalfield and one of the largest in the country. The combined output of three pits-Murton, Eppleton and Elemore-is to be concentrated at a new shaft which has been sunk more than half of its ultimate depth of 1,500 ft. Moving towards it at various levels from the three pits are large tunnels, five miles of which were driven in the last 12 months. The surface pattern, too, is now clear with the coke oven plant well advanced, the coal preparation building nearing completion, and the laying of railway sidings proceeding satisfactorily.

At many Durham collieries existing winding and haulage capacity prevents any increase in output until extensive reconstruction takes place. The reconstruction, usually involving new haulage roads and shaft bottoms, results in the diversion of existing winding capacity to deal with the stone produced, and also of manpower to drive the new roads. The colliery's output cannot, therefore, increase until the reconstruction is complete and until the men employed in this work are redeployed to the face.

As well as reconstruction schemes, there is a mechanisation programme, and at the end of 1957 coal output power-loaded in the Durham Division amounted to 17 per cent. of the output, compared with 11.5 per cent. the previous year. Various types of new machines were introduced and in North-West Durham a new type of scraper box is giving good results in seams less than 2 ft. thick. In other areas a multi-jib cutter loader enables very thin seams (16 to 24 inches) to be worked more efficiently.

Efforts, too, are proceeding with the aim of producing more large coal. These measures include the ploughing of prepared coal, as well as new forms of shot-firing. Pulsed infusion blasting is now in use at many collieries in the Division.

The use of steel supports, particularly hydraulic supports, on coalfaces has been substantially increased during the year. More than 100,000 hydraulic supports are now in everyday use in the coalfield.

A new type of machine has been introduced into the Division for the withdrawing of steel supports, mainly arched girders in disused roadways.

 

Prev Page Return to Top of Page Next Page

Article reproduced from a copy of the magazine held at National Mining Museum Scotland, Newtongrange, Midlothian.

 

mail
Mail:
Webmaster
Back
Back
Home
Home
Open Government Licence   Contains public sector information licensed under the Open Government Licence v3.0.

Copyright © 1999-2024 by The Durham Mining Museum and its contributors
Registered Charity No: 1110608
Page last updated: 17 Jan 2023

Privacy Policy
 
Terms & Conditions
 
Search
Search
Print
Print