The Cwm coking plant
We conclude our account of the planning and construction of the National Coal Board’s new works near Pontypridd, together with a detailed description of the complete undertaking.
The byproduct plant can handle 700,000 cu. ft. of gas an hour at N.T.P. in a single stream up to the outlet of the benzole scrubbers, from which point part of the gas goes to heat the ovens, the remainder being either purified and delivered to the Wales Gas Board grid or sent to the power station boilers.
The main plant units are: primary condensers — tar catch tank — deposit, decanting and storage tanks with tar and liquor pumps — liquor spray pumps — exhausters — electro-detarrers — ammonia absorbers and evaporative sulphate plant — final coolers — benzole scrubbers and crude benzole recovery plant. The units for the purified gas stream are: purifier boosters, tray purifiers, relief gasholder, compressors, aftercooler.
There are four vertical water-tube primary condensers (one a standby) on an elevated platform, the space below being enclosed to form a pump house. Each condenser has 25,000 sq. ft. of cooling surface, and the gas temperature is reduced to 35°C on the outlet. The ascension pipe spray liquor and condensate from the gas are trapped off the foul main before the primary condensers and flow to a duplex mechanical tar catch tank, where solid matter is strained off and removed by scraper conveyors. Condensate from the primary condenser seal pots also flows into this tank. The two spray liquor pumps (one electrically driven, the other a turbine-driven standby) draw their supply from the tar catch tank. Surplus tar and liquor overflow from the catch tank to the low-level deposit tank and are pumped to the decanting tank, whence they flow by gravity to storage tanks. Tar for disposal is pumped to road or rail wagons. Liquor is pumped to the sulphate plant still for ammonia recovery.
The two Richardsons Westgarth / Brown Boveri turbine-driven exhausters (one a standby) take steam at 120 lb. per sq. in. and 600°F, the exhaust at 25 lb. per sq. in. being used as process steam on the sulphate and benzole plants.
There are three electro-detarrers in parallel, any two of which can handle the entire gas stream, though with slightly reduced tar fog removal efficiency, while the third is being serviced.
Ammonia recovery is by the evaporative system. There are two bubble hood absorbers, one being a standby; the make of ammonium sulphate solution is handled by either of two single-effect evaporators, the magma being discharged through a settling cone to either of two Krauss Maffei continuous centrifuges. Each evaporator can take 25 gallons of liquor a minute, and the calandria are heated by process steam from the exhausters; the evaporators are fitted with jet condensers giving a vacuum of 27 in. of mercury. Salt is conveyed from the centrifuges to a rotary louvre dryer, which delivers to a batch weigher discharging 2-cwt. batches into a pit; the salt is transferred from the pit to stock by a pneumatic conveying system, which also reclaims salt from stock and transfers it direct into rail wagons.
The liquor made on the plant is pumped to a castiron liquor still, where free ammonia is recovered and delivered to the gas main before the absorbers. Effluent liquor is treated by the biological plant described later.
From the absorbers the gas passes to two secondary cooling towers of lift, diameter with heights of 87 ft. and 105 ft. respectively. In the first tower the gas is cooled to 37°C. by direct contact with water circulated over a timber grid packing, the outlet gas temperature being regulated by a temperature - actuated controller on the water supply in order to prevent naphthalene deposits in this section. From the top of the first tower the gas passes to the bottom of the second, which is a naphthalene removal section with board packing over which benzolised wash oil circulates. The gas passes up from this section into the final cooling section for cooling by direct contact with water.
Water for the final coolers is recirculated over a separate water cooling tower. The wash oil passes to the crude benzole plant for naphthalene and benzole recovery.
Benzole is recovered from the gas in three tower scrubbers in series. The towers. 10 ft. in diameter and 102 ft. high, are filled with board-on-edge packing, over which gas oil circulates counter-current to the gas.
Crude benzole is recovered from the wash oil in a conventional stripping plant, the stripped oil being cooled and returned to the scrubbers. Part of the oil passes through a steam-heated regeneration unit, which completely distills it and removes the heavy fraction; this unit enables the wash oil viscosity to be controlled. The crude benzole plant is built in the open on an elevated platform, beneath which is the pump and instrument house.
Gas control system
At the outlet of the benzole scrubbers the gas stream divides, part returning to the ovens for heating and the remainder being either delivered to the gas grid or burned in the power station. This arrangement is based on the seasonal demand of the Wales Gas Board, but minor daily and hourly variations also occur, and an overall control system embodying the necessary protective devices is installed to cope with these variations without waste and to prevent supply failures. This system is operated from the power station and is shown diagrammatically in Fig. 14.
During normal working the gas surplus to the demands of the coke ovens and the Gas Board is burned in the power station; the supply is hand-controlled at the boilers, using the information given by the gasholder level recorders and flowmeters installed in the power station. The gas flow to the purifiers is controlled from the power station by a remotely-operated butterfly valve on the outlet of the purifier boosters. Safety devices are installed to cope with the following abnormal conditions:
(1) Both gasholders in use
(a) Production of unpurifled gas exceeds consumption:—
The unpurified gasholder rises. When 2 ft. from the full position a trigger switch opens a magnetic cock on the bleeder governor, and the gas released through the stack is automatically ignited. When the gasholder falls by 6 ft. the trigger switch closes the bleed governor.
(b) Consumption of unpurified gas exceeds production:—
The unpurified gasholder falls. When 6 ft. from the empty position a trigger switch sounds an alarm in the power station; if the fall continues the purifier boosters trip out when the holder is 3 ft. from the empty position.
(c) Production of purified gas exceeds delivery by compressors to gas grid:
The purified gasholder rises, unwinding a cable from a drum. When the holder is 20 ft. from the full position a cam operated by the drum begins to open a valve passing gas to the diaphragm motor of the second butterfly valve on the outlet of the purifier boosters; the butterfly valve begins to close, shutting completely when the holder is 6 ft. from the full position, whereupon an alarm sounds in the power station and is repeated in the compressor house.
(d) Compression of purified gas exceeds production:—
The purified gasholder falls, and when 10 ft. from the empty position a trigger switch sounds an alarm in the compressor house, which is repeated in the power station. When 5 ft. from the empty position the holder operates a second switch to stop all the compressor motors. If this fails, the grounding of the holder operates a governor across the compressors and maintains a pressure of 4 in. water gauge in the inlet main by bleeding gas back from the highpressure main.
The alarms in the compressor house are both audible and visible, and are duplicated in the compressor room and motor room.
(2) One or both gasholders out of use
With the unpurified gasholder out of use, additional protection is afforded by maintaining a pressure of 7 in. water gauge in the unpurified gas main and by releasing surplus gas (e.g. at reversals) to the gas bleeder by an impulse line from the unpurified gas main to a governor controlling the gas supply to the second butterfly valve in this main.
With the purified gasholder out of use, a similar safeguard is provided by an impulse from the outlet of the purifiers to the diaphragm motor supply governor.
Excess pressure in the main after the compressors is prevented by a normal pressure release governor between compressor outlet and inlet.
Gas purification
The gas leaving the benzole scrubbers is washed for naphthalene removal before passing to the purifier boosters. The washer is of the static ring-packed type, using gas oil which is regenerated in a stripping plant alongside the washer. There is provision for installing a second washer if the volume of gas to be purified should increase at a future date.
The purifier boosters are Rateau-type turbo fans driven through speed-increasing gears by flameproof electric motors. Each fan can handle 10 million cu. ft. a day of unpurified coke-oven gas and can produce a pressure differential of 25 in. water gauge.
The purifiers are a five-box stream of deep tray boxes, each box holding 24 trays and having six lids, six inlets and four outlets. Each tray has two layers of oxide, and the gas flow is split upwards and downwards. The gas stream has an indirect steam gas heater on the inlet and smaller heaters on the main inlet to each box, to which there is also a direct steam connection. An air heater and blower are provided, with separate connections to each box.
Trays are handled in and out of the boxes by a Goliath crane running on a gantry, which extends far enough at the end to allow for stacking discharged trays and picking up freshly loaded ones. There is a covered oxide store, and space is reserved for future extension of the purifiers if required.
The gasholders are two-lift spiral guided holders in steel tanks above ground, their capacities being respectively 250,000 cu. ft. of unpurified gas and 1 million cu. ft. of purified gas.
There are five Bryan Donkin piston-type compressors, which can deliver gas at 25 lb. per sq. in.; they are driven through wall boxes by electric motors in a separate room. Three are fixed-speed machines, each with a capacity of 4 million cu. ft. of gas a day at N.T.P., and two are variable-speed machines, each with a capacity of 2 million cu. ft. of gas a day at N.T.P. Gas to the compressors is measured by a Holmes Connersville meter in the compressor house, and two indirect coolers remove the heat of compression from the gas before it goes to the grid.
Adjacent to the compressor house is a calorimeter room with a Fairweather recording calorimeter and accommodation for the gas examiner.
Effluent treatment
The bacteriological effluent treatment system (which, as already mentioned, was the reason for the Glamorgan River Board’s permission to discharge effluent into the Cwm brook) was first described in 1954 by Barritt, Cunningworth and Forlin. The plant at Cwm can treat 36,000 gallons of effluent a day and is based on the smaller unit installed earlier at Coedely.
Built mainly of reinforced concrete, the plant consists essentially of four reaction tanks and four settling tanks in parallel. Each reaction tank is approximately 32 ft. long by 12 ft. wide by 18 ft. high and is divided into eight passes; each pyramidal settling tank is approximately 12 ft. square by 18 ft. deep. A measuring tank feeds the pumped effluent into the reaction tanks, where compressed air is introduced by diffusers on the tank floors, the foam thus produced being removed by water sprays. A tank is provided for initial preparation of bacteria. Sludge is pumped from the bottom of the settling tanks and recirculated to the reaction tanks; a tank is included for sludge conditioning by heating and aeration.
Nutrient solution is pumped from a mixing tank into the toxic effluent collecting sump. Treated effluent overflows to drain from the top of the settling tanks.
Other services include a laboratory and switchroom in a separate building.
Water supply system
The major problem of water supply was described in the first part of this article, and the system was diagrammatically shown in Fig. 2.
At the south end of the plant a week’s supply can be held in a 7½-million gallon reservoir comprising two 3¾-million gallon circular reinforced concrete ponds, with three electrically-driven 30,000 gallons an hour pumps to pump water up to the high-level reservoir adjacent to the colliery. Supplies are also received from other sources as described earlier.
Internal supply for the coke-oven plant is derived from the high-level reservoir through a main connected to the power station and compressor house cooling towers, the water treatment plant and the hydrant main on the by-product plant.
The main water cooling tower on the byproduct plant supplies the primary condensers, crude benzole plant and naphthalene oil regeneration unit. Water from the pond of this cooling tower gravitates to the sulphate plant cooling tower serving the jet condensers and thence to the secondary gas cooler tower; blowdown from this latter tower supplies the coke quenching station by gravity. Make-up water is taken from the main leading from the high-level reservoir to the main byproducts cooling tower.
The byproduct plant and power station cooling towers are natural-draught wooden towers on concrete basins, an induced-draught tower being used for the gas coolers at the compressor house. Cooling water for the gas compressor cylinder jackets circulates in a closed system, being cooled in a tubular heat exchanger by water from the compressor house cooling tower.
Circulating pumps, duplicated for security, are housed near the appropriate cooling towers; the standby pump for the main byproduct plant cooling tower is steam driven.
Steam supply system
Pass-out steam from the power station turboalternators meets the demands of the coke ovens and byproduct plant; reducing valves and desuperheaters in the power station are used when the turbines are not running.
The coking plant uses two steam ranges, one at 120 lb. per sq. in. and 650°F, the other at 25 lb. per sq. in. and 550°F. The higher pressure serves the exhausters, standby spray liquor and water-circulating pumps, benzolised oil heater on the benzole plant, and steam injectors on the coke-oven ascension pipes. Back-pressure steam from the exhauster turbines. supplemented by a second pass-out on the power station turbo-alternators, supplies the users of 25 lb. per sq. in. steam, which include the sulphate and benzole plants, naphthalene oil regeneration unit, purifier heating. gasholder anti-freeze devices, and space heating. Steam at 25 lb. per sq. in. is also supplied to the colliery.
The 120 lb. per sq. in. main is a ring main from power station to exhauster house and back, with branches to users outside the exhauster house; the 25 lb. per sq. in. main is also a ring main. Steam supply is thus secured as far as possible against all interruptions.
Power station
Fuel handling plant. This plant can handle 96 tons of coal and 188 tons of coke a day. Coal or coke is discharged by a wagon tippler into a receiving hopper, from which it gravitates to either skip of a dual balanced skip hoist; the hoist discharges to a balance hopper, from which the fuel gravitates to a tripper conveyor distributing to the boiler bunkers. The reinforced concrete bunkers form an integral part of the boiler house concrete framework and have a capacity of 40 tons of coke and 80 tons of coal per bunker; the coke sections are lined with 2 in. thick tiles.
Water treatment plant. The water treatment plant supplies 6,000 gallons an hour continuously from the high-level reservoir, providing boiler feed water, two small supplies to the coking plant, make-up for the compressor cooling water, and water for the exhauster turbine oil coolers. The small surplus of soft water available during normal operation is fed to the cooling tower as part of the make-up. Water treatment comprises lime treatment to remove temporary hardness, filtration to remove suspended matter, acid dosing to remove excess bicarbonate, degassing to remove free carbon dioxide, alkali dosing to correct the pH value, and base exchange softening to remove residual hardness.
Water conditioning equipment is installed to add phosphate and sulphite.
There is one grid basket type deaerator, which can handle up to 115,000 lb. an hour of feed water.
There are three storage tanks for reserve filtered water, soft water and treated water respectively.
Feed pumps. There are three feed pumps, each with an output of 115,000 lb. an hour with a water inlet temperature of 250&def;F. Two of the pumps are electrically driven; the third is turbine driven and starts automatically if the feed line pressure falls below a predetermined figure.
Boiler plant. There are three tn-drum boiler units with water-cooled combustion chambers, each unit being complete with superheater and non-contact desuperheater, economiser, sootblowers, draught equipment, grit collector, mechanical stoker, gas burners in each side wall, and panels and instruments. The boilers are designed for alternative firing by sandwich-fired coal and coke, or by coke, or by coke-oven gas.
| Steaming conditions | |
| Steam pressure | 425 lb. per sq. in. |
| Steam temperature | 810°F |
| Feed water temperature at economiser inlet | 250°F |
| Continuous maximum rating | 50,000 lb. an hour |
Each superheater is of the two-pass controlled pendant type; the desuperheater forms an integral part of the superheater and consists of a number of coils below water-level in the front steam drum. Final steam temperature is manually controlled from the boiler panel through Lockheed equipment.
The economisers have cast-iron gilled tubes arranged in two tiers for easy cleaning and maintenance. Water-washing equipment is provided.
Each boiler has one forced-draught and one induced-draught fan, together with one secondary air fan to supply air to the nozzles in the front and rear arches above the stoker. One aerodynamic dust collector with booster fan is installed between each economiser and induced-draught fan.
The single-grate mechanical stokers are driven through self-contained gear by variable-speed ac. commutator motors, and each stoker is fed from overhead fuel bunkers by two mild steel rubber-lined chutes, one for coal and one for coke. One multinozzle gas burner is installed in each combustion chamber side wall. The external surfaces of combustion chamber and superheater tubes are cleaned by sootblowers.
The outlet of the induced-draught fan of each boiler is connected to a mild steel chimney 100 ft. high and 4 ft. 6in. diameter inside steelwork, lined internally with 2 in. thickness of Gunite.
Pressure reducing and desuperheating equipment. Two automatic electrically-controlled valves, each of 40,000 lb. an hour capacity, reduce steam pressure from 400 to 130 lb. per sq. in. and one valve of 15,000 lb. an hour capacity reduces from 130 to 25 lb. per sq. in. There are two spray-type desuperheaters with automatic control, each of which can desuperheat 40,000 lb. an hour of steam at 130 lb. per sq. in. from 810° to 450°F.
This equipment is used when the turbo-alternators are shut down.
Instruments and control equipment. Each boiler has its own instrument control panel with all necessary integrating and recording instruments, remote control for forced-draught and induced-draught fan output, and superheat temperature control. A central recording panel carries instruments to meter the flow of water and steam to ancillary equipment.
Ash and dust handling plant. A submerged ash conveyor in the boiler house basement receives the ash from each stoker ash hopper and delivers it to a balance hopper, whence it gravitates via a filling device to a skip hoist, which deposits it in a concrete ash bunker spanning one of the railway tracks. Dust collected in the hoppers below the dust collector gravitates into a Redler conveyor, which transfers it to a second Redler conveyor for discharge on to the rising portion of the submerged ash conveyor.
Turbo-alternators. There are two G.E.C. double pass-out turbo-alternators with condensing plant. The turbines are of standard multi-stage impulse type, designed for normal operation with steam at 400 lb. per sq. in. and 800°F at the turbine stop valve, first pass-out pressure 130 lb. per sq. in., second pass-out pressure 25 lb. per sq. in., condenser vacuum 28 in. Hg (Bar. 30 in. Hg)
Each turbine is provided with one surface-type condenser designed to condense 69,000 lb. an hour of exhaust steam. The condensers operate at a vacuum of 28 in. Hg (Bar. 30 in. Hg) when supplied with water at a recooled temperature of 80°F from the cooling tower. One steam air ejector and one extraction pump are provided for each condenser. There are two circulating water pumps, either of which can be used with either condenser.
A combined turbine gauge board and valve desk is mounted alongside each machine.
The direct-coupled alternators are of the revolving field and stationary armature type and are air-cooled on a closed circuit with water-cooled air-coolers. They generate at 11 kV, 3 phase, 50 cycles, with maximum output of 8,000 kW at 08 power factor. An automatic voltage regulator is provided for each alternator.
Cooling tower. One natural-draught cooling tower is installed, the tower, water distribution system and concrete tank being divided into two equal sections, either of which can be isolated for cleaning and maintenance.
Electrical supplies. The electric power output can be connected either to the main colliery supply, which is taken from the South Wales Electricity Board at a 33,000-volt colliery substation, or to the N.C.B. 33,000-volt network in the South Wales area.
The S.W.E.B. supply is transformed down to 11,000 volts at the colliery, whence duplicate feeders run to an 11,000-volt switchboard at the power station, to which are also connected the power station alternators and an 11,000 / 33,000-volt transformer feeder to the N.C.B. system. Section switches segregate the supplies for normal running conditions. Duplicate supplies to substations on the coke-oven plant are taken from a 3,300-volt switchboard in the power station, which in turn is fed from the power station 11,000-volt switchboard by duplicate transformers.
The whole system is interlocked to ensure safety and correct sequence of operation, and special arrangements give maximum security of supplies to the coking plant. If the supply from the colliery substation fails, supplies are automatically switched to the power station or, if the generators are not running, to the N.C.B. system. When supplies are being received normally from the colliery installation and power is being exported from the power station to the N.C.B. system, the 11,000-volt section switch between the two systems cannot be closed. Switchgear ratings have been carefully chosen so that any fault conditions arising under normal or emergency working conditions can be safely dealt with.
The power station has conventional auxiliary electrical equipment, supplied at 3,300 and 550 volts.
The 3.3 kV substations on the coking plant are located at the detarrers, compressor house and hammer mills; the first two have duplicate feeders direct from the power station, and the third is supplied by duplicate feeders from the detarrer substation. The three substations provide direct supplies at 3.3 kV to motors above 150 h.p. and to transformers to 550 V for the various switchboards. The motors on 3.3 kV comprise those driving the hammer mills, spray liquor pump and gas compressors. All others take 550-V 3-phase current supplied by duplicate transformers at the substations; the 550-V system is arranged in several ring main sections, thus ensuring an alternative route for supplies, both for ease of maintenance and for use in case of breakdown.
The 550-V switchboards supply by transformers single-phase current at 250-V for lighting, at 110-V for small power tools, and at 25-V for inspection lamps, the two latter supplies having the centre point earthed.
A special safety feature on the oven battery is the installation of stop-pushes at intervals along the tracks of all oven machines; any one of these, when pushed, isolates the corresponding trolley wires. The stop-pushes for ram and coke guide are on the side Motors platform handrails, those for the charger car are at suitable points on the oven tops, and those for the coke loco are at track level.
Buildings, amenities and civil engineering
Reinforced concrete retaining walls are used throughout the terraced site. One wall along the ram track, rising from 3 ft. to 7 ft. in height, supports the main road through the plant, and a second 7 ft. high wall supports the terrace on which the benzole scrubbers stand.
The roads throughout the site and the drains for surface water, soil and plant effluent were constructed and laid by the N.C.B. to designs by Simon-Carves, who also prepared track layout drawings.
The buildings generally are reinforced concrete frames with brick panelling. The roofs are concrete with a 1 in. layer of asphalt on top. Besides the plant buildings there is an ambulance station with doctor’s room and a small fire station on the byproduct plant side of the main works road.
The principal amenity buildings are on the oven battery, where the space under the service bunker provides clean and dirty locker rooms, showers, toilets and washing facilities, together with a large dining room and kitchen. The kitchen equipment was installed by the N.C.B.; building design and the supply of all other equipment was by Simon-Carves.