Manvers Main coking and byproducts plant
Our description of the N.C.B’s largest coke-oven and byproducts plant is concluded.
The crude benzole from the whole plant is recovered in three stills, which are located on the old site with their oil heaters, columns, coolers and naphthalene trays. The benzole refining units used on the old plant have been transferred to the new benzole refinery, the space thus freed being used for new units comprising two stills, three compound oil heaters, two columns and a set of debenzolised oil coolers. The crude spirit is pumped to storage tanks of the new refinery north-east of the main railway.
The benzole refinery can handle 15,000 gal. of crude spirit a day. which represents the whole of the crude produced at Manvers together with a million gallons a year of crude from other works. This large plant is the result of many years of development. Benzene and toluene were first made at Manvers during the first world war; after the war the plant made only motor spirit, but the manufacture of pure products was resumed during the second world war and a steady market, based on the high quality of the products, was built up. The extension of carbonising capacity provided an opportunity to develop this market and to achieve the utmost economy of operation by concentrating refining at one large plant.
The layout is on the most up-to-date lines and embodies many improvements suggested by the experience of the N.C.B. divisional staff and of SimonCarves. The plant comprises two defronting columns, six batch stills (three of 6,000 gal. and three of 10,000 gal.) each with its own fractionating column and three washers, one of 6,000. gal and two of 10,000 gal. capacity; this includes the plant transferred from the old site. There is also an acid regeneration plant which takes acid from the washers and frees it from tar; the dilute acid produced is used in the sulphate plant. Complete facilities are provided for handling incoming and outgoing products and chemicals, and there is a built-in fire-fighting installation. The plant is self-contained in that it has its own offices, laboratory, workshop, welfare building and cooling water circuit.
The process steam supply is arranged for maximum economy in operation. Steam at 140-150 lb. per sq. in. and 500°F is received from the back-pressure turbines in the power station and passes through a de-superheater before entering the heating coils of the stills. Low-pressure steam at 15 lb. per sq. in. is derived from the exhausts of the reflux and circulating pumps on the plant and is used as direct steam in the defronting colums and acid regeneration plant; it is also used in a special heater which heats the condensate used in the anti-freeze coils in the pure benzene tanks. Any surplus condensate is added to the clean water circulation system which supplies the condensers via a water cooling tower.
Except for the pumps the plant is installed in the open; the pump-house roof forms a platform for the fractionating columns and condensers, the stills being mounted inside a bund wall adjacent to the pump house. The supporting structure for the benzole washers is integral with the pump house, and weather protection is provided on the operating floor of the washer structure. The defronting columns are mounted alongside the washer structure.
Crude benzole is defronted, washed with once-used acid, and then distilled in the primary stills. These produce either motor spirit or semi-pure products; motor spirit is run to storage tanks, while the semipure products are washed again with strong acid before redistillation in the secondary stills. All storage tanks are mounted inside bund walls, and permanent foam lines run from the fire pump house to the various units.
The columns work on the pumped reflux system and are designed to make a wide range of products: for example, three grades of pure benzene of different specifications are normally made, together with toluene, xylene and solvent naphthas. The plant is fully instrumented, and controllers are used wherever appropriate to regulate the stills and columns. Pipelines are painted according to the standard colour code for easy identification. Provision is made for heating the pipe trenches of the benzene lines to prevent solidification in cold weather.
The power station
The power plant has two Parsons turbo-alternators, the turbines being back-pressure machines steamed by three Simon-Carves boilers with automatic control. The boilers are of the tn-drum twin-circulation type with water-wall combustion chambers, and each is equipped with superheater, non-contact type desuperheater, economiser, single-grate mechanical stoker, and two gas burners in each side wall. The steaming conditions are as follows:—
| Steam pressure | 625 lb. per sq. in. |
| Steam temperature | 815°F. |
| Feed water temperature at economiser inlet | 220°F. |
| Continuous maximum rating | 60,000 lb. an hour |
| Continuous peak load | 70,000 lb. an hour |
Two steam reducing valves with automatic electric control are installed to reduce steam pressure from 650 to 160 lb. per sq. in., one valve having a capacity of 130,000 lb. an hour and the other 20,000 lb. an hour. Two spray-type desuperheaters with automatic control can each reduce 130,000 lb. an hour of steam at 160 lb. per sq. in. to a temperature of 550°F. The reducing valves and desuperheaters are used when the turbo-alternators are shut down.
The boilers are arranged for firing by sandwich-fired coal and coke breeze or by coal or coke-oven gas, with provision for future firing by coal and tar fuel. Coal and coke breeze are delivered to overhead boiler bunkers by a conveyor and an automatic travelling tripper with a two-way chute.
Ash and grit are collected in hoppers and discharged into a submerged ash conveyor in the basement, from which they are delivered by belt conveyor to an ash bunker for removal by lorries.
The water treatment plant supplies 12,000 gal. an hour of treated water to the boilers, together with 33,000 gal. an hour of filtered water and 2,000 gal. an hour of soft water to the coke-oven plant.
The 550 V main switchboard consists of one 12-unit metal clad cubicle switchboard.
Coal preparation
The Manvers Main central coal-preparation plant was designed and built by Head Wrightson Colliery Engineering Limited, Sheffield, to treat the output of the Manvers combined mine, a reorganisation scheme which has co-ordinated the working of four collieries with Manvers Main Colliery as the central point of the scheme.
The preparation plant consists of three virtually identical units side by side, each having a capacity of 440 tons an hour. The plant is so arranged that raw coal from any of the three sources can be fed to any one of the three units in the plant as required. Treatment in each unit comprises dense-medium washing for the 8 in. by 2 in. fraction, using froth flotation tailings as medium. Baum jig washing for the 2 in. by 0 fraction and froth flotation for the mm. by 0 fines.
The first unit commenced commercial operation on July 18, 1955, followed by the second unit on October 3, 1955, and the third on June 4, 1956.
Gas dilution plant
The gas dilution plant at Manvers Main will be a Gibbons Heurtey clean gas unit, consisting of two producer gas generators, two sets of gas cleaning equipment, the necessary housing and a coke conveyor leading from the existing conveyor system. Each producer unit will be capable of manufacturing 42,000 cu. ft. of gas an hour at an anticipated gross calorific value of 125 B.t.u. per cu. ft. from coke nuts to 1¼ in.
Each producer generator will have an internal diameter of 4 ft. 11 in., and will be hand charged, mechanically de-ashed, and followed by a primary washing vessel, gas washing fan, spray separator and final scrubbing and cleaning vessel. The gas mains leading from the outlet of these two vessels are jointed in a "Y" branch and the main carried along the outriggers of the conveyor bridge to connect to the Coal Board’s distribution mains.
The gas from the generator will be automatically governed by the inverted bell principle which is a standard feature of all Gibbons Heurtey plants. Four air blown poke holes will be provided on each producer and these will be so fitted that when opened a screen of air will be automatically blown across the top of the poke hole, keeping the gas away from the operator. A comprehensive cubicle-type instrument panel of Elliott’s manufacture will be provided and an electrical distribution board, manufactured by Allen West and Co. Ltd., will also be installed within the producer house.
Some special features of the Manvers contract
The construction of the plant presented a number of special problems, many of which arose from the necessity to maintain uninterrupted gas supplies to the Gas Board under existing commitments. This was achieved by careful planning of the starting and finishing dates of every stage of the work, but complications were caused by the fact that reconstruction of the existing oven batteries had been begun before the extension was settled. The new battery of seventeen compound ovens on the old site was built in order to maintain gas output during the successive reconstructions of the various existing ovens, and a bridge was used to span the 15-oven battery, and later the 13-oven and 14-oven blocks of the old 30-oven battery, so that the charger car could continue to draw coal from the service bunker throughout the progress of the work.
The railways traversing the site introduced other difficulties. Gas mains and conveyors had to cross the tracks on bridges and the erection of these bridges without interrupting traffic called for exact planning and close co-operation with the railway staff. Three conveyor bridges and a gas main bridge had to be erected over the main line, and two conveyor bridges and a gas main bridge over the Wath Curve. The main line bridges were lifted by railway cranes, and it is a tribute to the engineering staffs of the N.C.B., British Railways, Simon-Carves and sub-contractors that these operations were completed without a single mishap.
To make room for the 66-oven battery on the new site the public road on the south-west side had to be moved, which involved building about 300 yards of new road; this work was undertaken by the N.C.B. to the local authority’s specifications.
The storage of the plant items as they were delivered was a major problem. As the cramped site provided no suitable storage space, the N.C.B. made available an area of land about 1½ miles to the east beyond the Bolton-on-Dearne road; here Simon-Carves established a store, with heated buildings for material that could not safely be kept in the open. and a special transport system was organised between store and site.
Owing to the large amount of pipe-fitting work a pipe-fabricating shop was set up in the space below the service bunker of the 66-oven battery, and here a staff of skilled men, including welders holding Lloyds’ certificates, were employed in making up all the special bends and connections required; this saved a great deal of time compared with the normal method of making them up off the site.
The lighting up and setting to work of the whole of the plant were carried out without a hitch.