July, 1958 Reconstruction Moves Outlined to Durham MenPlanned reconstruction at Wearmouth (Durham) was explained to representatives of the consultative committees at Wearmouth, Hylton, Westoe and Boldon, union officials and Durham Divisional officials. First stage will be to install new electric multi-rope friction winding apparatus at the 'C' pit shaft, starting with the pit's annual holiday on August 9, 1958. At the end of the holiday period all but 590 workmen will resume normal work and the remainder will move to Hylton, Westoe and Boldon for about six weeks to complete installation. Wearmouth is being reconstructed to develop reserves of coal under the sea to replace land coal which is becoming exhausted.
|
![]() |
||||||||
|