Logo Museum
Museum
Friends of Durham Mining Museum
Events Calendar
e-Books and Books for sale
Photograph Gallery
Document Archive
Main Document Archive
History Subsection
Biography Subsection
Obituary Subsection
Newspaper Articles
Local Record Extracts
D.M.A. Document Archive
Transactions of I.M.E.
Miners' Welfare
N.C.B. Archive
The Colliery Engineer
The Colliery Guardian
Mine & Quarry Engineering
Mining Journal
The Science and Art of Mining
Coal Magazine
Coal News
Coke and Gas
Master Name Index
What's new in the site
Mining
Mining History
Colliery Index
Colliery Maps
Company Overviews
Who's Who
Mineral Information
Managers Certificates
Educational Material
Bibliography
Statistics
Workers/Employee Lists
Notes for Family Historians
War Service information
Disasters
Disaster Reports
Names of those killed
Disasters in the 1700s
Disasters in the 1800s
Disasters in the 1900s
Memorials
Awards for Gallantry
On this day ...

Links to other sites of interest
Industrial Heritage Days Out
Former www.pitwork.net web site

Index to site

Contact and address details

Share Page with Social Media

Share on Facebook

Share with Reddit

Share on Delicious


Archives Prev Page Return to Index Next Page Archives
/   \

National Coal Board

North East Area

Wearmouth Colliery

February, 1976


Introduction

Wearmouth Colliery is situated in the County Borough of Sunderland on the North Bank of the River Wear and apprroximately 1½ miles from the river mouth. The colliery is over 140 years old, the original shafts named the 'A' and 'B' having been sunk over the years 1826 to 1834. The Maudlin Seam was reached on 15th February 1834, at a depth of 1,563 feet and at an expenditure of £100,000, the first cargo of coal being shipped on the 13th June, 1835. The shafts were deepened later and the Hutton Seam was reached approximately 120ft below the Maudlin Seam on the 4th April 1846.

The Colliery operated with the 'A' and 'B' shafts, 11ft 6ins dia. and 12ft 6ins dia. respectively, until 1910, when a new downcast shaft known as the 'C' shaft 18ft dia. came into operation, sinking of this shaft having commenced in 1906.

After the nationalisation of the coal industry in 1947 it was decided to embark upon a programme of modernisation and reconstruction at certain collieries where there were large reserves to be exploited. Since the existing facilities at Wearmouth Colliery were inadequate to deal with an output of approximately 4,000 saleable tons per day which was considered a minimum figure for a colliery with such large undersea reserves, it was decided in 1954 to reconstruct the colliery at a cost of approximately £6 million.

This reconstruction scheme was completed in 1967 and was followed by a Staiths Reorganisation Project costing £½ million, completed in 1969 and a Post Reconstruction Project costing £1½ million which was itself completed in 1972.

A third project, Major Drift Drivages 1972/76, costing £2 million is currently in progress at the colliery.

Reserves

The main reserves at the colliery lie beneath the sea and are contained in the Five Quarter, High Main, Yard, Maudlin, Low Main and Busty Seams, of which only the Yard, Maudlin and Low Main Seams are being worked at present. The Yard and Maudlin Seams are particularlt suitable for the foundry coking market because of their low ash and sulphur content.

The thickness and quality of the seams up to a distance of three to four miles out to sea have been proved by five boreholes drilled from and off-shore boring tower (fig. 1), reserves proved to date totalling 80 million tonnes, of which some 47 million tonnes are suitable for coking purposes. These boreholes have also confirmed the depth of the sea bed and proved the thickness of the water-bearing Permian Strata overlying the coal measures, information which is vital to the planning of the underground workings.

Reconstruction Projects

The main features of the various reconstruction schemes carried out at the colliery are summarised as follows :—

Reconstruction Scheme 1954-1967

 (a) 
Sinking of a new 24ft dia. shaft, known as the 'D' shaft, to a depth of 2,140 ft and equipping it with a 2,000 HP multi-rope friction drum winder to operate a 20 tons capacity skip (figs. 2 & 3).
 (b) 
Deepening the 'A' and 'C' shafts to the 1,850 B.O.D. level and equipping both shafts with new winding engines of the multi-rope friction drum type (fig 4 and 5).
 (c) 
The erection of a new 400 tons per hour coal preparation plant amd 200 tons per hour thermal drying plant (fig 6).
 (d) 
Improvement of other surface facilities including installation of new mine fans, extension to the pit-head baths and erection of new canteen.
 (e) 
Drivage of new underground roadways to provide the necessary haulage and ventilation facilities for the exploitation of the undersea reserves.
 (f) 
Installation of locomotives and trunk coneyors for transporting the coal to the shaft bottom.
 (g) 
Mechanisation of the coal faces.

Staiths Reorganisation 1966-1969

Erection of bunkers, gantries and conveyors on the riverside to give flexability in the production and bunkering of coal and stone and to improve the efficiency of loading barges for the disposal of stone at sea.

Post Reconstruction Project 1967-1972

 (a) 
The continuation of main drift drivages to allow for the efficient transport of men, stone and materialks and to facilitate the development of further undersea reserves at both the 1,570ft B.O.D. and 1,850ft B.O.D. Horizons.
 (b) 
The installation of a trunk conveying system at the 1,570ft B.O.D. Horizon to improve coal clearance and face machine running times.
 (c) 
The installation of necessary equipment on the surface to enable coking smalls and housecoal doubles to be produced and outloaded either by rail or road.

Major Drivage Project 1972-1976

 (a) 
To further extend the majot drift drivages at the 1,570 ft B.O.D. and 1,850 ft B.O.D. Horizons.
 (b) 
To increase the amount of underground bunkerage by the construction of additional vertical staple bunkers at the 1,850 ft B.O.D. Horizon.
 (c) 
To provide facilities to segregate low and medium sulphur coals at the colliery.

Production and Development

Production at the colliery at present exceeds 4,000 saleable tons per day and is obtained from seven faces all of which are equipped with power roof supports and disc shearers (fig 7). Most faces are also equipped with a second machine, a ranging arm shearer (fig. 8) which takes part of the tailgate roadway caunch.

All main development headings at the colliery are driven using Dosco Roadheader machines and during the past nine years over 34 miles of underground development roadways have been driven.

Because of the long haulage distances involved at the colliery, men are transported inbye from the shaft bottom manriding station (fig. 9) by locomotive (18 mph) to the working places.

Manpower

At present there are approximately 2,300 men employed at the colliery of which 28% are employed at the coal face, 57% elsewhere undeground and 15% at the surface.

 

Prev Page Return to Top of Page Next Page

 

mail
Mail:
Webmaster
Back
Back
Home
Home
Open Government Licence   Contains public sector information licensed under the Open Government Licence v3.0.

Copyright © 1999-2024 by The Durham Mining Museum and its contributors
Registered Charity No: 1110608
Page last updated: 31 Dec 2022

Privacy Policy
 
Terms & Conditions
 
Search
Search
Print
Print