Logo Museum
Museum
Friends of Durham Mining Museum
Events Calendar
e-Books and Books for sale
Photograph Gallery
Document Archive
Main Document Archive
History Subsection
Biography Subsection
Obituary Subsection
Newspaper Articles
Local Record Extracts
D.M.A. Document Archive
Transactions of I.M.E.
Miners' Welfare
N.C.B. Archive
The Colliery Engineer
The Colliery Guardian
Mine & Quarry Engineering
Mining Journal
The Science and Art of Mining
Coal Magazine
Coal News
Coke and Gas
Master Name Index
What's new in the site
Mining
Mining History
Colliery Index
Colliery Maps
Company Overviews
Who's Who
Mineral Information
Managers Certificates
Educational Material
Bibliography
Statistics
Workers/Employee Lists
Notes for Family Historians
War Service information
Disasters
Disaster Reports
Names of those killed
Disasters in the 1700s
Disasters in the 1800s
Disasters in the 1900s
Memorials
Awards for Gallantry
On this day ...

Links to other sites of interest
Industrial Heritage Days Out
Former www.pitwork.net web site

Index to site

Contact and address details

Share Page with Social Media

Share on Facebook

Share with Reddit

Share on Delicious


Archives Prev Page Return to Index Next Page Archives
/   \

National Coal Board

North East Area

Horden Colliery

August, 1983


Foreword

Introduction

Horden Colliery is situated on the coast of South East Durham approximately 11 kilometres north of Hartlepool. Shaft sinking commenced in 1900, the shafts passing through some 130 metres of water-bearing magnesian limestone which overlies the Coal Measures. Sinking of the North and South shafts, each 6.1m in diameter and 438m and 401m in depth respectively, was completed in 1904 and the East Pit, 5.2m in diameter and 419m in depth, was completed in 1908.

The North Shaft is the coal winding shaft and is equipped with two 12½ tonne capacity skips. The South Shaft is equipped with cages for the winding of men, materials and stones and the East Shaft is a standby shaft for men winding.

The colliery was developed from the beginning as a large unit, production being originally continued to the lower and better quality seams.

At this time, annual outputs in excess of one million tonnes were obtained and the colliery employed approximately 4000 men. Exhaustion of the lower seams necessitated concentration of production in the generally thinner upper seams, which coupled with various geological problems, has resulted in the colliery producing some 600,000 tonnes per annum saleable and employing under 2000 men over recent years.

Reconstruction Work

Between 1962 and 1967 a reconstruction of the colliery was carried out to modernise the mining, underground transport, winding and coal handling facilities. This was followed in 1974 by a further major project with the aim of combining Horden with the nearby Blackhall Colliery. One of the principal features of this project was the installation of an underground cable belt conveyor ; 6.6km in length, to deal with the combined outputs. From 1977 onwards the Blackhall output was conveyed underground via Horden and treated at the Horden Coal Preparation Plant.

However, due to the large quantities of water which was encountered in the Blackhall workings, Blackhall Colliery was closed in April 1981 and a pumping station established in it to protect Horden Colliery.

A rapid loading station has been constructed on the surface to enable washed smalls to be loaded into British Rail MGR wagons.

Hydraulic Waste Disposal (Fig. 8)

In 1971 a Working Party consisting of representatives of the Department of the Environment, the Department of Trade and Industry and the National Coal Board was formed to examine the aesthetic and pollutive effects of beach tipping, a common practice for waste disposal at several North East Area collieries and to recommend measures which might be taken to alleviate the problems.

As a result of the report published in 1972, the Board undertook to construct a pilot plant at Horden Colliery which would enable waste to be crushed and pumped to the foreshore at a rate of some 120 tonnes/hour.

Initial testing of the plant commenced in November 1977. Since this date many modifications and repairs to the original plant have been carried out and work is currently in hand to extend the pipeline to below the low tide level as part of the continuing trials.

Reserves

Remaining reserves at the colliery lie under the North Sean where the Coal Measures are overlain by unconformable water bearing Permian Strata. The layout of the mine is shown on Fig. 1 and a geological section from West to East is illustrated on Fig. 2.

Details of the individual seams are as follows :—

  1. High Main Seam 'E' (thickness 1.40 to 2.0 metres)
    This seam is currently being worked by continuous miner partial extraction and by a longwall face.
  2. Main Seam 'F' (thickness 0.80 to 0.90 metres)
    The quality of this seam is variable and may deteriorate to the East. The seam is extracted by longwall faces.
  3. Yard Seam 'G' (thickness 0.90 to 1.30 metres)
    This seam is currently being extracted by longwall faces.

Working Undersea

The National Coal Board rules applying to undersea working vary slightly depending on the thickness of extraction, but can be broadly described as follows :—

  1. The effect of mining shall not create a tensile strain on the sea-bed exceeding 10mm/metre.
  2. No longwall extraction shall take place where there is less than 105m of strata to the sea-bed nor where there is less than 60m of Carboniferous strata above the seam. The strata above the Carboniferous is Permian and highly water bearing.
  3. Only partial extraction mining (e.g. bord and pillar system) can be practised where the cover to the sea-bed is between 60 and 105m or where there is only 45 to 60m of Carboniferous strata above the seam.
  4. No mining shall take place where there is less than 60m of strata to the sea-bed nor where there is less than 45m of Carboniferous strata above the seam. The cover to the Base of the Permian in present working areas varies from 45m to 120m in the High Main Seam and from 72m to 93m in the Main and Yard Seams.

Methods of Working

In the High Main Seam reserves where the cover to the Base of the Permian is between 45 and 60m a partial extraction system of mining is practised, as illustrated in Fig. 3, and using Joy Continuous Miners as the coal getting machines.

In the other areas of reserves in the High Main, Main and Yard Seams, where the cover to the Base of the Permian is greater than 60m, two basic methods of longwall working, viz. "Advance" and "Retreat" are used at the colliery. These are illustrated in Figs. 3 & 4, the main difference between the two methods being that in the "Retreat" method the roadways are driven to the far end of the area to be worked and then the face is retreated, using the pre-driven roadways for the necessary conveying, transport and ventilation services. In this way, prior knowledge is gained of the geological conditions of the area, and because the roadways are pre-formed, the rate at which the coal can be extracted is increased.

Face widths at Horden Colliery vary from 100m to 230m and there are normally five faces available for production, two of which are retreat faces. The coal us won by shearers (Fig. 6) which cut and load the coal onto an armoured chain conveyor for transport along the face to a stage loader and belt conveyor situated in the Maingate. From the Maingate the coal is loaded into trunk conveyors which feed into staple bunkers out of which the coal is loaded onto the main cable belt conveyor for transportation to the shaft and winding to the surface. Along the face the roof is supported by powered supports which are operated hydraulically. On advancing faces (Fig. 4) roadside packs are put on at the side of the gates to support the gates for the life of the face, but this is not necessary on retreat faces. The roof between the gates in allowed to collapse, or "cave" behind the supports as they advanced with the face. The area which has been extracted and allowed to collapse is known as the "waste" or "goaf".

Development drivages are done by roadheaders (Fig. 7), dintheaders and bucket loaders.

Underground Transport

The underground workings extend for distance of approximately 7 kilometres under the sea and the mineral transport system consists of a series of belt conveyors which convey the output to the North Shaft where it is wound to the surface in skips of 12½ tonnes capacity. The coal from the High Main Seam is delivered into Nos. 4 and 5 staple bunkers (Fig. 1), each of 800 tonnes capacity, from which it is fed onto the cable belt conveyor for conveying to the shaft. The output from the Main and Yard Seams is delivered through the No. 1 staple bunker, 450 tonnes capacity, onto the same conveying system to the shaft. The purpose of the staple bunkers, is two-fold viz., to provide bunkerage whereby peak loads from the faces can be evened out before feeding the coal at a steady rate onto the main conveying system, and to provide bunkerage whereby the faces can continue to operate even through there may be delays on the coal winding or main coal transport system.

Supplies are transported from the South Shaft to the various seams by a combination of locomotive and rope haulage systems and manriding is by means of the locomotive and rope haulage systems with come additional inbye manriding on belt conveyors.

Ventilation

The mine workings are ventilated by means of a 2,460kw Aerex radial flow can 4.06 metres in diameter which deals with 280cu metres of air per second.

Output and Manpower

The bulk of the output, "washed smalls" is sold to the Central Electricity Generating Board, National Coal Board and independent coke ovens and in the export market. Some output is blended with other coals to meet British Steel requirements and some is sold on the domestic market. The coal is prepared for these markets in the colliery coal preparation plant which has a washing capacity of 500 tonnes/hour.

During the current year output has averaged 2875 tonnes/day at an overall productivity of 1.66 tonnes per manshift. 1737 men are currently employed at the colliery.

August 1983

 

Prev Page Return to Top of Page Next Page

 

mail
Mail:
Webmaster
Back
Back
Home
Home
Open Government Licence   Contains public sector information licensed under the Open Government Licence v3.0.

Copyright © 1999-2024 by The Durham Mining Museum and its contributors
Registered Charity No: 1110608
Page last updated: 31 Dec 2022

Privacy Policy
 
Terms & Conditions
 
Search
Search
Print
Print